Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
Professional engineering services
|
Task Assignment 25:
Task 1: No Dam Break Condition Inundation Modeling and Mapping for the S-159 St...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment 25:
Task 1: No Dam Break Condition Inundation Modeling and Mapping for the S-159 Structure at Tampa Bypass Canal and S-161 Structure at Harney Canal Task 2: Dam Break Inundation Modeling for the S-159 Structure at Tampa Bypass Canal and S-161 Structure at Harney Canal. Task 3: Dam Break Inundation Mapping Report Supplement for S-159 Structure at Tampa Bypass Canal and S-161 Structure at Harney Canal. Task 4: Inundation Modeling and Mapping, Emergency Action Plan (EAP) Dam Failure Map Supplement for S-159 Structure at Tampa Bypass Canal and S-161 Structure at Harney Canal.
|
| Deliverable Price: $98,197.28 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T25 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment 26: Subtask 301-This subtask must not exceed $15174.52 Community Engagement: Creatio...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment 26: Subtask 301-This subtask must not exceed $15174.52 Community Engagement: Creation and Restoration of Wellands Workshop. Assistance with planning and conducting 1-day workshop; memorandum documenting workshop and participant feedback. Subtask 302.1-This subtask must not exceed $9353.27 Training and Capacfly Building Event (1) - Marco Shores. Assistance with planning for and participation in event memorandum documenting event. Subtask 302.2- This subtask must not exceed $10517.52. Training and Capacity Building Event (2) - Marco Shores. Assistance with planning for and participation In event; memorandum documenting event. Subtask 303- This subtask must not exceed $16804.47 Scientific Data Validation and Adaptive Management. Memorandum outlining recommendations.
|
| Deliverable Price: $51,849.78 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T26 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment 24: Subtask 19 - A schedule revision is requested to extend the deliverable date fo...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 24: Subtask 19 - A schedule revision is requested to extend the deliverable date for Subtask 19 only; there is no change proposed to TA scope, fee, or final completion date. The extension is necessary following SFWMD permit clarification; an exemption request was submitted as planned before the original TA deadline. However, SFWMD submitted RAls, requested a site visit, and requires permit modification in lieu of the previously completed exemption,
CO1: TA24 CO1 to extend end date 9/1/26. CO1 amount $0.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T24 CO1 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment Number 22, Task 4, Project domain watershed Hydrologic modeling inputs for control s...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment Number 22, Task 4, Project domain watershed Hydrologic modeling inputs for control structures S-161 and S-159 HHP dam system. 1)Provide watershed subareas map contributing flow to the selected points of interest for the S-161 and S-159 HHP dam system impoundments and downstream flooding impact area, along the TBC: March 17, 2025 |
| Deliverable Price: $14,937.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T22 CO1 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment Number 22:
Task 3, LiDAR Data Compilation and topographic data integration. 1) Com...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment Number 22:
Task 3, LiDAR Data Compilation and topographic data integration. 1) Compile DEM from 2017 LiDAR and topographic data developed in Task 2 for the control structures S-161, and S-159 Upper, Middle, and Lower and the downstream flooding impact area along the TBC. Due dates: February 17, 2025
|
| Deliverable Price: $13,463.80 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T22 CO1 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment Number 22:
Task 2, Field Survey Data Acquisition. 1.) 1)Provide e-mail notification...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment Number 22:
Task 2, Field Survey Data Acquisition. 1.) 1)Provide e-mail notification to the FDSP at least one
week prior to the scheduled field site visit to conduct the
required field surveying work.
2) Provide electronic file of field surveying and
topographic data for control structures S-161 and S-159 Upper,
Middle, and Lower HHP dam system. Due dates: January 24, 2025
SSMC = $29,508.56
MM = $8,335.60 |
| Deliverable Price: $37,844.16 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T22 CO1 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment Number 22:
Task 1, Field Reconnaissance Site Visit and Coordination with FDEP, and S...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment Number 22:
Task 1, Field Reconnaissance Site Visit and Coordination with FDEP, and SWFWMD representatives. 1.) Draft & Final Site Reconnaissance Summary Reports, including Appendices with Figures and Excel Tables summarizing
pertinent available data. Due dates: December 16 2024
|
| Deliverable Price: $4,608.40 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T22 CO1 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment 24: Subtask 20 - SME Services -- As-needed plus mileage N/A : SME services ongoing...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 24: Subtask 20 - SME Services -- As-needed plus mileage N/A : SME services ongoing as needed; time and materials not to exceed $4869.88
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T24 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment 24: Subtask 18 - Permit Minor Modification -
Bring Work Schedule Into Compliance Mi...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment 24: Subtask 18 - Permit Minor Modification -
Bring Work Schedule Into Compliance Minor modification request : Permit Minor Modification to amend project area and update work schedule for client review by February 27, 2026.
|
| Deliverable Price: $5,909.64 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T24 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment 24: Subtask 17 - Time Zero + 60 Vegetation and
Fish Sampling 60 Months (Year S) Mon...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment 24: Subtask 17 - Time Zero + 60 Vegetation and
Fish Sampling 60 Months (Year S) Monitoring Report with Fish Sampling Results : Year 5 (TZ+ 60 Months) Vegetation and Fish Monitoring and Report by November 20, 2028.
|
| Deliverable Price: $10,223.76 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T24 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment 24: Subtask 15 - Time Zero + 36 Vegetation and
Fish Sampling 36 Months (Year 3) Mo...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment 24: Subtask 15 - Time Zero + 36 Vegetation and
Fish Sampling 36 Months (Year 3) Monitoring Report with Fish Sampling Results : Year 3 (TZ + 36 Months) Vegetation and Fish Monitoring and Report by November 20, 2026.
20, 2027.
|
| Deliverable Price: $10,223.76 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T24 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment Number 23, Task 9, Dam Break Inundation Mapping including EAP Dam Failure Maps for P...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment Number 23, Task 9, Dam Break Inundation Mapping including EAP Dam Failure Maps for P-1 Dam Structure at Lake Lena
1) Electronically submit a draft of the Dam Break Inundation Mapping Report for the Sunny Day Dam Break, 100-year Dam Break and PMP Dam Break scenarios for the P-1 Dam structure, including the EAP Failure Maps (for worst case dam failure). Change Order 5: Extend deliverable due date to 03/10/2026
2) After receiving FDSP approval on the Draft Report, submit the Final
Dam Break Inundation Mapping Report for Sunny Day, 100-year and
PMP Dam failures, and the EAP Failure maps (for worst case dam
failure). Change Order 5: Extend deliverable due date to 03/24/2026
CO1: Extended deliverable date and update project manager CO2: Extended deliverable due date
CO4: Extended deliverable due date
CO5: Extended deliverable due dates for T23_CO5 Project 2 tasks 4-9
|
| Deliverable Price: $26,204.96 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T23 CO5 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment Number 23, Task 8, Dam Break Inundation Modeling for P-1 Dam Structure at Lake Lena...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment Number 23, Task 8, Dam Break Inundation Modeling for P-1 Dam Structure at Lake Lena
1) Electronically submit a draft of Inundation Modeling Report for the Sunny Day Dam Break, the 100-year Dam Break and PMP Dam Break scenarios for P-1 Dam Structure Change Order 5: Extend deliverable due date to 02/10/2026
2) After approval of the Draft report, submit the Final Inundation
Modeling Report for the Sunny Day, 100-year and PMP Dam failures. Change Order 5: Extend deliverable due date to 02/24/2026
CO1: Extended deliverable date and update project manager CO2: Extended deliverable due date
CO4: Extended deliverable due date
CO5: Extended deliverable due dates for T23_CO5 Project 2 tasks 4-9
|
| Deliverable Price: $24,033.62 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T23 CO5 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment Number 23, Task 7,No Dam Break Condition Inundation Modeling and Mapping
for P-1 Dam...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment Number 23, Task 7,No Dam Break Condition Inundation Modeling and Mapping
for P-1 Dam Structure at Lake Lena
1)Electronically submit Flood Inundation Maps for the P-1 Dam structure site and d/s locations with maximum flood depths and elevations. Change Order 5: Extend deliverable due date to 01/13/2026
2) Electronically submit Draft Inundation Modeling and Mapping report for 100-yr, 1/2 PMP and PMP storms with overtopping analyses. Change Order 5: Extend deliverable due date to 01/13/2026
3) After approval of the Draft documents, submit the Final Dam Break Inundation Modeling analysis and Mapping, submit the Final Report electronic file including all associated modeling data and incorporating the responses to FDSP review comments. Change Order 5: Extend deliverable due date to 01/27/2026"
CO1: Extended deliverable date and update project manager CO2: Extended deliverable due date CO3: Extended deliverable due date
CO4: Extended deliverable due date
CO5: Extended deliverable due dates for T23_CO5 Project 2 tasks 4-9
|
| Deliverable Price: $15,945.20 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T23 CO5 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment Number 23, Task 6, Dam Break Inundation Mapping including EAP Dam Failure
Maps for P...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment Number 23, Task 6, Dam Break Inundation Mapping including EAP Dam Failure
Maps for P-3 Dam Structure at Lake Arietta
1) Electronically submit a draft of the Dam Break Inundation Mapping Report for the Sunny Day Dam Break, 100-year Dam Break and PMP Dam Break scenarios for the P-3 Dam structure, and the EAP Dam Failure Maps. Change Order 5: Extend deliverable due date to 12/09/2025
2) After approval of the Draft document, submit the Final Dam Break
Inundation Mapping Report for Sunny Day, 100-year and PMP Dam
failures and the EAP Dam Failure Maps Change Order 5: Extend deliverable due date to 12/23/2025
CO1: Extended deliverable date and update project manager CO2: Extended deliverable due date
CO3: Extended deliverable due date
CO4: Extended deliverable due date
CO5: Extended deliverable due dates for T23_CO5 Project 2 tasks 4-9
|
| Deliverable Price: $15,799.20 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T23 CO5 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment Number 23, Task 5,Dam Break Inundation Modeling for P-3 Dam Structure at Lake Ariett...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment Number 23, Task 5,Dam Break Inundation Modeling for P-3 Dam Structure at Lake Arietta
1) Electronically submit a draft of Inundation Modeling Report for the Sunny Day Dam Break, the 100-year Dam Break and PMP Dam Break scenarios for P-3 Dam Structure, which includes the project
information, analysis assumptions, methodology, input and output
data for breach scenarios, Tables and Figures for review by FDEP. Change Order 5: Extend deliverable due date to 11/10/2025
2) After approval of the Draft report submit the Final Inundation
Modeling Report for the Sunny Day, 100-year and PMP Dam failures.
CO1: Extended deliverable date and update project manager CO2: Extended deliverable due date
CO3: Extended deliverable due date
CO4: Extended deliverable due date
CO5: Extended deliverable due dates for T23_CO5 Project 2 tasks 4-9
|
| Deliverable Price: $15,451.32 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T23 CO5 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment Number 23, Task 4, No Dam Break Condition Inundation Modeling and Mapping for P-3 D...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment Number 23, Task 4, No Dam Break Condition Inundation Modeling and Mapping for P-3 Dam Structure at Lake Arietta 1) Electronically submit the No Dam Break Flood Inundation Maps for the P-3 dam structure site & d/s locations with Max depths/elevations.
2) Electronically submit a Draft No Dam Break Inundation Modeling and Mapping Report which includes results of the 100-year 24-hour storm computer modeling, the ½ PMP and the PMP storm overtopping analyses.3) After approval of the Draft Report, Submit the Final No Dam Break Inundation Modeling and Mapping report : August 18, 2025; August 18, 2025; August 29th, 2025
CO1: Extended deliverable date and update project manager CO2: Extended deliverable due date
CO3: Extended deliverable due date
CO4: Extended deliverable due date
CO5: Extended deliverable due dates for T23_CO5 Project 2 tasks 4-9
|
| Deliverable Price: $14,859.12 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T23 CO5 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment Number 23, Task 3, Dam Break Inundation Mapping including EAP Dam Failure Maps for F...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment Number 23, Task 3, Dam Break Inundation Mapping including EAP Dam Failure Maps for Flint Creek Dam Structure at Lake Thonotosassa 1) Electronically submit a Draft of the Dam Break Inundation Mapping Report for the Sunny Day Dam Break 100-year Dam Break and PMP Dam break scenarios, and Draft EAP Dam Failure map. 2) After approval of Draft documents, submit the Final Dam Break Inundation Mapping Report for the Sunny Day Dam Break, the 100-year Dam Break and PMP Dam Break scenarios, and Final EAP Dam Failure map. Due dates: June 30, 2025, July 11, 2025
Change Order 1: Extended deliverable date and update project manager Change Order 2: Extended deliverable due date
Change Order 3: Extended deliverable due date
Change Order 4: Extended deliverable due date
|
| Deliverable Price: $16,255.56 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T23 CO4 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment Number 23, Task 2, Dam Break Inundation Modeling for Flint Creek Dam Structure at La...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment Number 23, Task 2, Dam Break Inundation Modeling for Flint Creek Dam Structure at Lake Thonotosassa 1) Electronically submit a Draft Inundation Modeling Report for the Sunny Day Dam Break, 100-year Dam Break and PMP Dam Break scenarios. 2) After approval of the Draft Report, electronically submit the Final Inundation Modeling Report for the Sunny Day Dam Break, 100-year Dam Break and PMP Dam Break scenarios. Due dates: May 30, 2025, June 16, 2025
Change Order 1: Extended deliverable date and update project manager Change Order 2: Extended deliverable due date Change Order 3: Extended deliverable due date
Change Order 4: Extended deliverable due date
|
| Deliverable Price: $14,969.68 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T23 CO |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment Number 23, Task 1, No Dam Break Condition Inundation Modeling and Mapping for Flint...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment Number 23, Task 1, No Dam Break Condition Inundation Modeling and Mapping for Flint
Creek Dam Structure at Lake Thonotosassa 1) Electronically submit the No Dam Break Flood Inundation Maps for dam structure site and d/s locations, with Max Flood depths and elevations 2) Electronically submit a Draft Inundation Modeling and Mapping Report including 100-year storm modeling, ½ PMP and the PMP storm overtopping analyses. 3) After approval of the Draft document, submit the Final No Dam Break electronic version of the Report. Due dates: April 28,2025,April 28,2025, May 9, 2025
Change Order 1: Extended deliverable date and update project manager Change Order 2: Extended deliverable due date
Change Order 3: Extended Deliverable due date.
Change Order 4: Extended deliverable due date |
| Deliverable Price: $14,894.64 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T23 CO4 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment Number 21, Task 202 Restoration Monitoring Coordinator Guidance and Community Trai...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment Number 21, Task 202 Restoration Monitoring Coordinator Guidance and Community Training. 1. Quarterly Reports - see Quarterly Report Schedule under Schedule of Fees ($7,000/report for a total of $35,000).
Due dates: Task No. 5, 2024 Quarter 4 Report, Due Date: January 15, 2025 Task No. 6, 2025 Quarter 1 Report, Due Date: April 24, 2025 Task No. 7, 2025 Quarter 2 Report, Due Date: July 15, 2025 Task No. 8, 2025 Quarter 3 Report, Due Date: October 15, 2025 Task No. 9, 2025 Quarter 4 Report, Due Date: November 30, 2025"
CO1: Revise deliverable due dates and key personnel table
CO2: Revise deliverable due dates
|
| Deliverable Price: $35,000.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T21 CO2 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment Number 21, Task 201 1. Creation and Restoration of Wetlands Workshop.
1. Workshop ...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment Number 21, Task 201 1. Creation and Restoration of Wetlands Workshop.
1. Workshop Summary Report and PDF of Presentations ($35,000). Due date: November 30, 2025
CO1: Revise deliverable due dates and key personnel table
CO2: Revise deliverable due dates
|
| Deliverable Price: $35,000.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T21 CO2 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment Number 21, Task 200 1. Site Visit ($5,000). Due date January 31, 2025. 2. Draf...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment Number 21, Task 200 1. Site Visit ($5,000). Due date January 31, 2025. 2. Draft Monitoring Plan ($20,000). Due Date: September 30,2025. 3. Final Monitoring Plan ($10,000). Due date: November 30, 2025.
CO1: Revise deliverable due dates and key personnel table
CO2: Revise deliverable due dates
|
| Deliverable Price: $35,000.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T21 CO2 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task Assignment Number 20, Task 4, Host online 2023 Florida Dam Safety Technical Seminar. 1.) Time Z...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignment Number 20, Task 4, Host online 2023 Florida Dam Safety Technical Seminar. 1.) Time Zero + 24 Months Monitoring Report 2.) Provide FDEP with an attendee log, final agenda, and secure pdf of presentations to support invoicing only. Due dates:June 20, 2025
|
| Deliverable Price: $10,000.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: Task Assignment 19, Scope of Sevices, page 5 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
"Task Assignment Number 20, Task 3, TZ+ 18 Vegetation and Fish Sampling. 1.) Host online Technical ...
|
Fixed Price - Lump Sum
|
| Major Deliverable: "Task Assignment Number 20, Task 3, TZ+ 18 Vegetation and Fish Sampling. 1.) Host online Technical Seminar and provide Certificates of Attendance to documented attendees, including certificates with PDH hours for registered Professional Engineers.
2.) Provide FDEP with an attendee log, final agenda, and secure pdf of presentations to support invoicing only.Due dates: November 1, 2024"
|
| Deliverable Price: $10,000.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: Task Assignment 19, Scope of Sevices, page 5 |
| Deliverable Number: |
|