| More |
Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
CIVIL ENGINEERS
|
Professional Coastal Engineering Services. Deliverables established on a task assignment basis.
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Professional Coastal Engineering Services. Deliverables established on a task assignment basis. |
| Deliverable Price: $0.00 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Established per task assignment. |
| Financial Consequences: No payment for unsatisfactory services. |
| Source Documentation Page Reference: Contract |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Two hardcopies of an alternatives evaluation report will be provided to the FDEP summarizing...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Two hardcopies of an alternatives evaluation report will be provided to the FDEP summarizing the work performed. A pdf copy on a disk will also be provided. The report will be delivered within 45 calendar days of the notice to proceed. Not to exceed $10223.39
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re??perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform
|
| Source Documentation Page Reference: TA1 |
| Deliverable Number: |
|
|
|
T1-2A
|
Professional engineering services
|
Task 1-2A: Deliverables will consist of a topographic survey map and cross-sections certified by a F...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 1-2A: Deliverables will consist of a topographic survey map and cross-sections certified by a Florida Professional Surveyor and Mapper. Three (3) hardcopies (ANSI D sized) and one (1) pdf will be provided. The survey will be completed within one month of the notice to proceed. Fixed cost $18,518.52. Reimbursable Travel not to exceed $930.38. Total cost not to exceed $19,448.90.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
|
| Financial Consequences: "No payment will be made for unsatisfactory deliverables. In the event that a
deliverable is deemed unsatisfactory, the Consultant shall re-perfonn the services needed for submittal of a satisfactory deliverable, atno additional cost to the Department within 15 consecutive days. If a satisfactory
deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform."
|
| Source Documentation Page Reference: page 3-4 |
| Deliverable Number: T1-2A |
|
|
|
T1-2B
|
Professional engineering services
|
Task 1-2B: Deliverable will consist of a geotechnical engineering report (one hardcopy and one pdf)....
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 1-2B: Deliverable will consist of a geotechnical engineering report (one hardcopy and one pdf). All geotechnical testing and reporting will be completed within 5 weeks of the notice to proceed. Fixed cost $6,572.26 and reimbursable cost of $491.39. Cost not to exceed $7,063.65.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
|
| Financial Consequences: "No payment will be made for unsatisfactory deliverables. In the event that a
deliverable is deemed unsatisfactory, the Consultant shall re-perfonn the services needed for submittal of a satisfactory deliverable, atno additional cost to the Department within 15 consecutive days. If a satisfactory
deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: page 5 |
| Deliverable Number: T1-2B |
|
|
|
T1-3
|
Professional engineering services
|
Task 1-3: Deliverable will be meeting attendance and meeting minutes (one hardcopy). The meeting wil...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 1-3: Deliverable will be meeting attendance and meeting minutes (one hardcopy). The meeting will occur within 2 weeks of the completion of the survey and the geotechnical testing and will scheduled at a mutually acceptable date with FDEP staff. Fixed cost $1,546.40 and reimbursable cost $126.38. Cost not to exceed $1,672.78.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
|
| Financial Consequences: "No payment will be made for unsatisfactory deliverables. In the event that a
deliverable is deemed unsatisfactory, the Consultant shall re-perfonn the services needed for submittal of a satisfactory deliverable, atno additional cost to the Department within 15 consecutive days. If a satisfactory
deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: page 6 |
| Deliverable Number: T1-3 |
|
|
|
T1-4
|
Professional engineering services
|
Task 1-4: Deliverable will consist of a CAD file and three (3) hardcopies of design development draw...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1-4: Deliverable will consist of a CAD file and three (3) hardcopies of design development drawings (ANSI D) plus an opinion of probable construction cost. The design development drawings and the cost estimate will be provided within two (2) months of the notice to proceed. |
| Deliverable Price: $7,532.68 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
|
| Financial Consequences: "No payment will be made for unsatisfactory deliverables. In the event that a
deliverable is deemed unsatisfactory, the Consultant shall re-perfonn the services needed for submittal of a satisfactory deliverable, atno additional cost to the Department within 15 consecutive days. If a satisfactory
deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T1CO1 page 8 |
| Deliverable Number: T1-4 |
|