| More |
Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
Professional engineering services
|
As indicated in individual task assignments.
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: As indicated in individual task assignments.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Agreement without a financial exchange or impact |
| Performance Metrics: Prior to submission to the Department, the Consultant shall review all deliverables to ensure the same are accurate and complete at time of submittal and meet or exceed the specified deliverable.
|
| Financial Consequences: The Department will not pay for any unsatisfactory deliverables. In the event the Department deems a deliverable unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable at no additional cost to the Department within 15 consecutive days. If the Consultant fails to resubmit a satisfactory deliverable within the specified timeframe, the Department, in its sole discretion, may terminate the Task Assignment and/or Agreement for failure to perform.
|
| Source Documentation Page Reference: As indicated in individual task assignments. |
| Deliverable Number: |
|
|
|
|
Nonresidential building construction services
|
Task 1, Subtask 1: Three copies of floor plans, exterior elevations and interior elevations describi...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1, Subtask 1: Three copies of floor plans, exterior elevations and interior elevations describing existing conditions. One copy of drawings in AutoCad version 15 and one PDF copy. Task 1 Documents will be completed within 10 calendar days of Notice to proceed.
|
| Deliverable Price: $1,529.83 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Nonresidential building construction services
|
Task 1, Subtask 2: Three copies of cover sheet with index and applicable codes, floor plans, exterio...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1, Subtask 2: Three copies of cover sheet with index and applicable codes, floor plans, exterior and interior elevation sheet and detail sheet(s) describing the Work. Specifications will be included on the Drawings. One copy of drawings in AutoCad version 2015 and one PDF copy. Signed and sealed copies of the Documents will be also included for Permitting. Task I Documents will be completed within 10 calendar days of Notice to proceed with Task 2.
|
| Deliverable Price: $3,675.56 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: TA1, 2 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 2, Subtask 1: Photographic Documentation in 8-1/2 x 11 Booklet Format. Task 1 Travel and Docume...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 2, Subtask 1: Photographic Documentation in 8-1/2 x 11 Booklet Format. Task 1 Travel and Documents will be completed within 14 calendar days of Notice to Proceed. Meals & Mileage Reimbursables $127.46. The Department shall pay the Contractor on a cost reimbursement plus fixed fee basis not to exceed $1,456.21.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete accurate and timely.
|
| Financial Consequences: No Payment will be made for unsatisfactory deliverables. In the event that a Consequences deliverable is deemed unsatisfactory, the Consultant shall re-perfmm the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Depaiiment may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 2, Subtask 2: Submittals will be in 11 x 17 Booklet Format . Thee Booklets will be provided wi...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 2, Subtask 2: Submittals will be in 11 x 17 Booklet Format . Thee Booklets will be provided with one PDF copy of the Booklet. One copy of the Drawings will be provided in AutoCad Revit version 2015. Task 2 Documents will be completed within 30 calendar days of Notice to Proceed. Reimbursables for drawings $45.00. The Department shall pay the Contractor on a cost reimbursement plus fixed fee basis not to exceed $3,705.84
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete accurate and timely.
|
| Financial Consequences: No Payment will be made for unsatisfactory deliverables. In the event that a Consequences deliverable is deemed unsatisfactory, the Consultant shall re-perfmm the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Depaiiment may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 2, Subtask 3: Three copies of Drawings (24 x 36 fo1mat) and Specifications (8-1/2 x 11 format) ...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 2, Subtask 3: Three copies of Drawings (24 x 36 fo1mat) and Specifications (8-1/2 x 11 format) including but not limited to cover sheet with index and applicable codes, floor plans, exterior and interior elevations, details as well as Civil, Structural, HVAC, Plumbing and Electrical Drawings describing the Work. (approximately 24 sheets) One copy of drawings in AutoCad version 2015 and one PDF copy. Signed and sealed copies of the Documents (in adequate quantity as required) will be also included for Permitting. Fixed Architectural-Engineering Fees $14,636.52, Reimbursables (printing and PDF) $300.00. Not to exceed $14,936.52 |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete accurate and timely.
|
| Financial Consequences: No Payment will be made for unsatisfactory deliverables. In the event that a Consequences deliverable is deemed unsatisfactory, the Consultant shall re-perfmm the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 2, Subtask 4: Three copies of Drawings (24 x 36 format) and Specifications (8-1/2 x 11 format)...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 2, Subtask 4: Three copies of Drawings (24 x 36 format) and Specifications (8-1/2 x 11 format) including but not limited to cover sheet with index and applicable codes, survey, site plan, and site utility plan. (approximately 4 sheets) One copy of drawings in AutoCad version 2015 and one PDF copy. Signed and sealed copies of the Documents will be included in the ERP permitting package and additional copies provided for inclusion in the Task 3 Document package. Task 4 Documents will be created coincident with
Task 3 Documents.
|
| Deliverable Price: $8,836.55 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete accurate and timely.
|
| Financial Consequences: No Payment will be made for unsatisfactory deliverables. In the event that a Consequences deliverable is deemed unsatisfactory, the Consultant shall re-perfmm the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: TA2, 7-8 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 3, Subtask 1: Photographic Documentation and written report in 8-1/2 x 11 Booklet Format. Task ...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 3, Subtask 1: Photographic Documentation and written report in 8-1/2 x 11 Booklet Format. Task 1 Travel and Documents will be completed within 10 calendar days of Notice to Proceed. 3 copies and one PDF copy will be provided. Cost not to exceed $3,815.05.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete
accurate and timely.
|
| Financial Consequences: No Payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: page 3 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 3, Subtask 2: Three copies of Drawings (24 x 36 format) and Specifications (8-1/2 x 11 format) ...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 3, Subtask 2: Three copies of Drawings (24 x 36 format) and Specifications (8-1/2 x 11 format) including but not limited to cover sheet with index and applicable codes, floor plans, exterior and interior key note documentation, specifications and details as well as Plumbing and Electrical Drawings describing the Work. (approximately 5 sheets) One copy of drawings in AutoCad version 2015 and one PDF copy. Signed and sealed copies of the Documents (in adequate quantity as required) will be also included for Permitting. Task 2 Documents will be completed within 14 calendar days of Notice to Proceed after the completion of Task I -Project Research. Cost not to exceed $7,103.36
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete accurate and timely.
|
| Financial Consequences: No Payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: page 4 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 4, Subtask 1A: Initial Site Visit - Travel to Kissimmee Prairie Preserve State Park to meet wit...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 4, Subtask 1A: Initial Site Visit - Travel to Kissimmee Prairie Preserve State Park to meet with the Park
Manager and DEP Project Manager. The Purpose of the trip is for the Architect to get a general understanding of the Proposed Location of the bunk house and identify
any Project Constraints. Deliverable: Site meeting report in PDF format. Task cost: Fixed Price $1,398.80, Reimbursable $320.40. Subtask Total not to exceed $1,719.20. |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 4, Subtask 1B: Survey - Provide a topographic survey of the proposed bunk house site including ...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 4, Subtask 1B: Survey - Provide a topographic survey of the proposed bunk house site including ground
elevations, existing above grade improvements and natural features found within the defined project limits. The defined limits will not exceed one acre in area. The Work includes coordination by the Architect. Deliverable: The deliverable for this task is five 24" x 36" hardcopies and one PDF format electronic file depicting the map of the topographic survey. Subtask total = $5,434.34 |
| Deliverable Price: $5,434.34 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 4, Subtask 2A: 60% Civil Engineering Construction Documents - design and preparation of civil e...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 4, Subtask 2A: 60% Civil Engineering Construction Documents - design and preparation of civil engineering construction documents for site and utility improvements to accommodate a new prefabricated 4 bedroom bunk house. Anticipated design elements to include paving and drainage plans for the new parking spaces, water & sewer plans for new septic system and potable well. The potable water system design will include the location of the well and a performance specification for the well based on a 4
bedroom bunk house. Topographic survey will be provided by owner to accommodate civil engineering design if required. The Work includes Coordination by the architect. Deliverable: The deliverable for this task is one 24"x36" hardcopy and PDF format electronic file of 60% level of completion design documents. Subtask Total = $7,265.60. |
| Deliverable Price: $7,265.60 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 4, Subtask 2B: Final Civil Engineering Construction Documents - The design and preparation of c...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 4, Subtask 2B: Final Civil Engineering Construction Documents - The design and preparation of civil engineering construction documents for site and utility improvements to accommodate a new prefabricated 4 bedroom bunk house. Anticipated design elements to include paving and drainage plans for the new parking spaces, water & sewer plans for new septic system and potable well. Plans will include the location for the proposed prefabricated bunk house. Topographic survey will be provided by owner to accommodate civil engineering design. Deliverable: The deliverable for this task is one 24"x36" hardcopy and PDF format electronic
file of final level of completion design documents. Subtask total = $3,212.88 |
| Deliverable Price: $3,212.88 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 4, Subtask 3A: Civil Permitting - Preparation of permit application submittal packages to the f...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 4, Subtask 3A: Civil Permitting - Preparation of permit application submittal packages to the following agencies:
Okeechobee County Health Department (Septic System Permit), South West Water Management District (10-2 Self Certification) - This task includes the preparation of permit applications and submittals to the regulatory agencies. In addition, this task includes plan revision to incorporate regulatory agency comments into the design documents and responses to regulatory agency questions.
Reimbursable Costs include required permit application fees. The Work includes Coordination by the Architect
Deliverable: Permit Application Submittal Package to Okeechobee County Health Department (OKHD) for
septic system permit. Subtask cost not to exceed $3,419.24 |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 4, Subtask 3B: Subsurface Soil Investigation and Geotechnical Report - Provide two (2) Standard...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 4, Subtask 3B: Subsurface Soil Investigation and Geotechnical Report - Provide two (2) Standard Penetration Borings to a depth of 15 feet in accessible
locations near the proposed cabin. Upon completion of the field exploration, provide laboratory testing and an engineering report which includes recommendations for site preparation, foundation design and other geotechnical aspects of the Project. The Work includes coordination by the Architect. Deliverable: The deliverable for this task is one signed and sealed hardcopy and PDF format
electronic file of Final Geotechnical Report. Subtask total cost = $2,766.07 |
| Deliverable Price: $2,766.07 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 4, Subtask 4A: 100% Architectural, Structural and MEP Construction Documents - Architect and Co...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 4, Subtask 4A: 100% Architectural, Structural and MEP Construction Documents - Architect and Consulting Engineers will modify the 100% Construction Documents entitled Blue Spring ADA Cabin, Blue Spring State Park to site adapt the cabin to the proposed location at Kissimmee Prairie Preserve State Park in Okeechobee, Florida. IT is
assumed that the Structural Drawings will need to be modified to accommodate higher windloads. Soil Borings will be required to accommodate Structural Engineering design. Deliverable: The deliverable for this task is one full size 24"x36" hardcopy, one half size copy and PDF format electronic file of I 00% level of completion 100% Construction Documents. Subtask cost not to exceed $7,507.36 |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 4, Subtask 4B: Construction Cost Estimate of 100% Construction Documents - At the completion of...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 4, Subtask 4B: Construction Cost Estimate of 100% Construction Documents - At the completion of the 100% Construction Document, the Architect will provide an estimate of the probable construction cost of the Kissimmee Prairie Bunk House. The basis of the estimate will be the 100% Construction Documents. Deliverable: The deliverable for this task is five copies of the completed estimate and one PDF format electronic file. Subtask total = $2,054.00 |
| Deliverable Price: $2,054.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 4, Subtask 5A: Civil Construction Phase Services - The Civil Engineer and Architect will perfor...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 4, Subtask 5A: Civil Construction Phase Services - The Civil Engineer and Architect will perform the following construction phase services during construction:
Review Shop Drawings provided by the Contractor;
Respond to Contractor's request for information (RFI);
Prepare and submit final certification with contractor and permitting agencies. Deliverable: The deliverable for this task are reviewed shop drawings, RFI responses and final
certification statements in pdf format. Subtask total = $1,713.12 |
| Deliverable Price: $1,713.12 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 4, Subtask 5B: Civil Construction Phase Services-Site Visits - Perform the following constructi...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 4, Subtask 5B: Civil Construction Phase Services-Site Visits - Perform the following construction phase services during construction: Attend up to two site visits during construction to ensure the work is completed in
substantial accordance with the approved and permitted plans and specifications; Attend substantial completion inspection with contractor. Deliverable: The deliverable for this task are field reports from site visits. Subtask total $3,924.18 |
| Deliverable Price: $3,924.18 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 4, Subtask 6A: The Civil Engineer and Architect will perform the following construction phase s...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 4, Subtask 6A: The Civil Engineer and Architect will perform the following construction phase services during construction: Review Shop Drawings provided by the Contractor; Respond to Contractor's request for information (RFI) Deliverable: The deliverable for this task are reviewed shop drawings, RFI responses and other
communications during construction in pdf format. Subtask total = $1,268.06 |
| Deliverable Price: $1,268.06 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 4, Subtask 6B: Structural Construction Phase Services - Site Visits - Perform the following con...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 4, Subtask 6B: Structural Construction Phase Services - Site Visits - Perform the following construction phase services during construction: Attend up to three site visits during construction to ensure the work is completed in substantial accordance with the approved and permitted plans and specifications. Deliverable: The deliverable for this task are field reports from site visits in pdf format. Subtask cost not to exceed $3,452.19 |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 4, Subtask 7A: Architectural and MEP Construction Phase Services - The Civil Engineer and Archi...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 4, Subtask 7A: Architectural and MEP Construction Phase Services - The Civil Engineer and Architect will perform the following construction phase services during construction: Review Shop Drawings provided by the Contractor; Respond to Contractor's request for information (RFI); Deliverable: The deliverable for this task are reviewed shop drawings, RFI responses and other
submittal requirements in pdf format. Subtask total = $2,789.70 |
| Deliverable Price: $2,789.70 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 4, Subtask 7B: Architectural and MEP Construction Phase Services. Description: The Civil Engine...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 4, Subtask 7B: Architectural and MEP Construction Phase Services. Description: The Civil Engineer and Architect will perform the following construction phase
services during construction: Attend up to three site visits during construction by the Architect, Mechanical Engineer
and Electrical Engineer to ensure that the work is completed in accordance with the approved and permitted plans and specifications; Attend substantial completion inspection with Contractor if required
Deliverable: The deliverable for this task are reviewed shop drawings, RFI responses and final certification statements in pdf format. Subtask cost not to exceed $15,210.00 |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 3: Subtask 1C Wetland Deliniation; The deliverable for this task is a map with points overlaid ...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 3: Subtask 1C Wetland Deliniation; The deliverable for this task is a map with points overlaid on an aerial photo showing the flag locations and numbers in PDF format electronic file and one PDF format electronic file depicting the map of the updated topographic survey. CO1: Adds Subtask 1C, increases task amount.
|
| Deliverable Price: $6,631.31 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T3CO1 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 4, Subtask 4C - Modify design documents for 2 RV campsites. Deliverable: The deliverable for th...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 4, Subtask 4C - Modify design documents for 2 RV campsites. Deliverable: The deliverable for this task is three full size 24""x36"" hardcopies, signed and
sealed, one half size copy and PDF format electronic file of 1000/4 level of completion 1000/4
Construction Documents.CO2: Adds Subtask 4C.
|
| Deliverable Price: $1,394.95 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the department to confirm they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 3 |
| Deliverable Number: |
|