| More |
Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
Professional engineering services
|
Task 1: (2) Two hardcopies of Signed and Sealed Survey Drawings - 22" x 34" will be delivered to the...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 1: (2) Two hardcopies of Signed and Sealed Survey Drawings - 22" x 34" will be delivered to the DEP project manager. The survey drawings will also be delivered to the project manager in electronic .PDF and ACAD format via emails. The Signed and sealed survey drawings, electronic and hardcopy survey will be delivered within six (6) weeks of task assignment execution $4,121.45. Reimbursable Cost $21.00; Reimbursable Mileage Cost $165.54. The Department shall pay the Contractor on a cost reimbursement plus fixed fee basis not to exceed $4,307.99 |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: "The project manager will review the submitted survey drawings both hardcopy and
electronic, to verify they are accurate, complete and include the above mentioned surveyed items and was submitted within six ( 6) weeks of task assignment execution."
|
| Financial Consequences: "No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Consultant shall re-perform the
services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in it sole discretion, terminate the Contract for failure to perform."
|
| Source Documentation Page Reference: TA1 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: (4b) 90% Design drawings include: - 3 Drawings sheets, 2 hardcopy sets of 22" X 34" drawings...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 1: (4b) 90% Design drawings include: - 3 Drawings sheets, 2 hardcopy sets of 22" X 34" drawings will be delivered to the DEP project manager, and the technical specifications will include: I hardcopy set of 8 I /2" X 11" to be delivered to project manager and a copy of the technical specifications will also be delivered to the project manager in electronic .PDF format via emails within one (1) month after delivery of Task IV.A. 60% Design. Fixed Price $3,065.20, Reimbursable (mailing and printing) $35.00. The Department shall pay the contractor on a cost reimbursement plus fixed fee basis not to exceed $3,100.20 |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The project manager will review the revised and new 90% design drawings and technical specifications both hardcopy and electronic format to verify they are accurate, complete, and included the specified sheets and was submitted within one (1) month after delivery of Task IV.A. 60% Design.
|
| Financial Consequences: "No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Consultant shall re-perform the
services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in it sole discretion, terminate the Contract for failure to perform."
|
| Source Documentation Page Reference: TA 1 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: (5) 3 sets of 11" X 17" drawings of the Site Plan, and a permit application fee of $385 will...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 1: (5) 3 sets of 11" X 17" drawings of the Site Plan, and a permit application fee of $385 will be delivered to Sarasota County within one ( 1) month after delivery of Task IV.A. 60% Design. An electronic .PDF copy of the entire permit application package will be emailed to the DEP project manager. Fixed $843.90; Reimbursable (Sarasota County app fee) $385.00. The Department shall pay the contractor on a cost reimbursement plus fixed fee basis not to exceed $1,228.90 |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The project manager will review the application form and permit drawings to verify they were submitted accurately and complete and within one (I) month after delivery of Task IV.A. 60% Design.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Consultant shall re-perform the
services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in it sole discretion, terminate the Contract for failure to perform. |
| Source Documentation Page Reference: TA1 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 5: Construction Pre-Construction Meeting - an email copy of the meeting Agenda and meeting minu...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 5: Construction Pre-Construction Meeting - an email copy of the meeting Agenda and meeting minutes will be submitted via email. |
| Deliverable Price: $1,273.00 |
| Non Price Justification: |
| Performance Metrics: The submitted bid documents will be reviewed by the Department to confirm they are complete, accurate, and timely. |
| Financial Consequences: The Departmentwill not pay for any unsatisfactory deliverables. In the event the Department deems a deliverable unsatisfactory, the Consultant shall re-perform the services needed forsubmittal of a satisfactory deliverable at no additional cost to the Department within 15 consecutive days. If the Consultant fails to resubmit a satisfactory deliverable within thespecified timeframe, the Department, in its sole discretion, may terminate the TaskAssignment and/or Agreement for failure to perform. |
| Source Documentation Page Reference: T5 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 5-2.3.1: TKW will email site visit report - 0ne visit by Engineer or Engineer's representative ...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 5-2.3.1: TKW will email site visit report - 0ne visit by Engineer or Engineer's representative to confirm that the underground utilities and the building foundation is ready to accept installation of the prefabricated restroom building. |
| Deliverable Price: $1,148.00 |
| Non Price Justification: |
| Performance Metrics: The submitted bid documents will be reviewed by the Department to confirm they are complete, accurate, and timely. |
| Financial Consequences: The Departmentwill not pay for any unsatisfactory deliverables. In the event the Department deems a deliverable unsatisfactory, the Consultant shall re-perform the services needed forsubmittal of a satisfactory deliverable at no additional cost to the Department within 15 consecutive days. If the Consultant fails to resubmit a satisfactory deliverable within thespecified timeframe, the Department, in its sole discretion, may terminate the TaskAssignment and/or Agreement for failure to perform. |
| Source Documentation Page Reference: T5 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 5-2.3.2: TKW will email site visit report - 0ne visit by Engineer to witness the ADA sidewalk a...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 5-2.3.2: TKW will email site visit report - 0ne visit by Engineer to witness the ADA sidewalk access construction. |
| Deliverable Price: $1,148.00 |
| Non Price Justification: |
| Performance Metrics: The submitted bid documents will be reviewed by the Department to confirm they are complete, accurate, and timely. |
| Financial Consequences: The Departmentwill not pay for any unsatisfactory deliverables. In the event the Department deems a deliverable unsatisfactory, the Consultant shall re-perform the services needed forsubmittal of a satisfactory deliverable at no additional cost to the Department within 15 consecutive days. If the Consultant fails to resubmit a satisfactory deliverable within thespecified timeframe, the Department, in its sole discretion, may terminate the TaskAssignment and/or Agreement for failure to perform. |
| Source Documentation Page Reference: T5 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 4-5.7: Artifact Analysis - Week 1: An email summary of lab findings will be submitted.
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 4-5.7: Artifact Analysis - Week 1: An email summary of lab findings will be submitted. |
| Deliverable Price: $1,712.00 |
| Non Price Justification: |
| Performance Metrics: Email will be reviewed by the Department to confirm it is complete, accurate, and timely. |
| Financial Consequences: The Departmentwill not pay for any unsatisfactory deliverables. In the event the Department deems a deliverable unsatisfactory, the Consultant shall re-perform the services needed forsubmittal of a satisfactory deliverable at no additional cost to the Department within 15 consecutive days. If the Consultant fails to resubmit a satisfactory deliverable within thespecified timeframe, the Department, in its sole discretion, may terminate the TaskAssignment and/or Agreement for failure to perform. |
| Source Documentation Page Reference: T4 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 4-1.10: Project management week 10 - TKW will email monthly status report letters via email. Or...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 4-1.10: Project management week 10 - TKW will email monthly status report letters via email. Original letter status reports will accompany each monthly invoice that is submitted. |
| Deliverable Price: $550.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. |
| Financial Consequences: The Departmentwill not pay for any unsatisfactory deliverables. In the event the Department deems a deliverable unsatisfactory, the Consultant shall re-perform the services needed forsubmittal of a satisfactory deliverable at no additional cost to the Department within 15 consecutive days. If the Consultant fails to resubmit a satisfactory deliverable within thespecified timeframe, the Department, in its sole discretion, may terminate the TaskAssignment and/or Agreement for failure to perform. |
| Source Documentation Page Reference: T4 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 6, del 2: This is an as-needed subtask which involves engineering review and approval of Shop D...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 6, del 2: This is an as-needed subtask which involves engineering review and approval of Shop Drawing submittals from the Contractor. This task also has a small budget to cover potential requests for technical information which may occur from the Contractor. This task may be necessary to review and approve any alternative prefabricated restroom buildings or product Substitutions that may occur in the course of construction. The budget for this task is for responding to up to seven (7) total Submittal Reviews and up to four (4) total RFI Responses. Deliverable: A .PDF copy via email of the Shop Drawing Submittals and Reviews and RFI responses will be submitted.
|
| Deliverable Price: $2,992.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
|
| Financial Consequences: The Departmentwill not pay for any unsatisfactory deliverables. In the event the Department deems a deliverable unsatisfactory, the Consultant shall re-perform the services needed forsubmittal of a satisfactory deliverable at no additional cost to the Department within 15 consecutive days. If the Consultant fails to resubmit a satisfactory deliverable within the specified timeframe, the Department, in its sole discretion, may terminate the Task Assignment and/or Agreement for failure to perform.
|
| Source Documentation Page Reference: 3-4 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 6, del 3A: Description: ADG and Marten will visit the site at substantial completion and will p...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 6, del 3A: Description: ADG and Marten will visit the site at substantial completion and will prepare/ distribute the final punch list. Deliverable: ADG and Marten will provide .PDF construction status report and punch list via email.
|
| Deliverable Price: $3,144.00 |
| Non Price Justification: |
| Performance Metrics: The submitted bid documents will be reviewed by the Department to confirm they are complete, accurate, and timely.
|
| Financial Consequences: The Departmentwill not pay for any unsatisfactory deliverables. In the event the Department deems a deliverable unsatisfactory, the Consultant shall re-perform the services needed forsubmittal of a satisfactory deliverable at no additional cost to the Department within 15 consecutive days. If the Consultant fails to resubmit a satisfactory deliverable within the specified timeframe, the Department, in its sole discretion, may terminate the Task Assignment and/or Agreement for failure to perform.
|
| Source Documentation Page Reference: 4 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 8, Del. 1 Survey: Two hardcopies of Signed and Sealed Survey Drawings - 22" x 34" will be deliv...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 8, Del. 1 Survey: Two hardcopies of Signed and Sealed Survey Drawings - 22" x 34" will be delivered to the BDC project manager. The survey drawings will also be delivered to the project manager in electronic .PDF and ACAD format via emails. The Signed and sealed survey drawings, electronic and hardcopy survey will be delivered within 30 days of NTP. - CO1 - Additional task time
|
| Deliverable Price: $4,933.20 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 3 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 8, Del. 2: Wastewater Collection System Improvements Study & Conceptual Design: A Draft Study R...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 8, Del. 2: Wastewater Collection System Improvements Study & Conceptual Design: A Draft Study Report that includes summary of existing conditions, schematic drawing exhibits, and evaluation narrative and concept level cost estimates for the two wastewater collection system options will be delivered in electronic .PDF format by E-mail. Final Study Report in pdf format will be delivered to Client by E-mail and two mailed hardcopies of the report will be provided. The Final Study Report will be completed within 60 days of NTP. This task schedule assumes that the BOC project manager will provide draft report recommendations to the Consultant within a week of receipt of the Draft report, and that the Consultant will revise and resubmit the Final Report to reflect Client comments and with the Client-selected wastewater collection system improvement option confirmed. CO1 - Additional task time
|
| Deliverable Price: $5,445.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 4 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 8, Del. 3 60% Design Drawings & Cost Estimate: The design team will submit 60% Design drawings ...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 8, Del. 3 60% Design Drawings & Cost Estimate: The design team will submit 60% Design drawings that include Utilities Plan & Profile and Lift Station Details Drawing sheets. These 60% drawings (11" X 17" size) will be delivered to the BOC project manager and the Park Manager in electronic .PDF format via emails.TKW will also submit 60% Cost Estimate in electronic .PDF format via email to the BDC project manager. The 60% complete drawings and cost estimate will be submitted within 90 days of the NTP. CO1 - Additional task time
|
| Deliverable Price: $6,429.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 5 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 8, Del. 4: 90% Design Drawings and Technical Specifications & Cost Estimate: 90% Design deliver...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 8, Del. 4: 90% Design Drawings and Technical Specifications & Cost Estimate: 90% Design deliverables will include two (2) sets of 11" x 17" drawings and an electronic .PDF file of the drawings. These will be delivered to the BDC project manager along with one set of hardcopy technical specifications and an updated cost estimate. A .PDF copy of the technical specifications and cost estimate will be E-mailed to the BDC project manager and park manager within 120 days of the NTP. CO1 - Additional task time
|
| Deliverable Price: $5,013.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 5 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 8, Del. 5 100% Plans Final Design Documents & Final Cost Estimate: Final documents will include...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 8, Del. 5 100% Plans Final Design Documents & Final Cost Estimate: Final documents will include three (3) sets of 11" X 17" signed and sealed hardcopy drawings delivered to the BDC project manager. Final drawings will also be E-mailed to BDC project manager and park manager in in electronic .PDF and native AutoCAD file format. One (1) hardcopy signed and sealed set of the Final Cost Estimate and Specifications 8 1/2" X 11" will also be delivered to BDC project manager and E-mailed to BDC project manager in electronic .PDF format. All Deliverables will be submitted to the BDC within 150 days of the NTP.
CO1 - Additional task time |
| Deliverable Price: $3,447.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 6 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 8, Del. 6 Permitting: An electronic .PDF copy of the entire permit application package and RFI ...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 8, Del. 6 Permitting: An electronic .PDF copy of the entire permit application package and RFI responses to these agencies will be emailed to the BDC project manager. Fixed Price Cost $3,579.00. Reimbursable Costs not to exceed $750.00. Cost will not exceed $4,329
CO1 - Additional task time |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 7 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 12; Del. 1: TKW will email monthly status report letter via email. Original letter status repor...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 12; Del. 1: TKW will email monthly status report letter via email. Original letter status report will accompany each monthly invoice that is submitted.
|
| Deliverable Price: $550.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 3 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 12; Del. 2: An email copy of the punch list will be submitted via email.
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 12; Del. 2: An email copy of the punch list will be submitted via email.
|
| Deliverable Price: $1,270.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 3 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 12; Del. 3: An email copy of the construction completion certification package, including all s...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 12; Del. 3: An email copy of the construction completion certification package, including all system test results, will be submitted via email.
|
| Deliverable Price: $956.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 4 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 12; Del. 4: An email copy of the construction completion certification package and PDF electron...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 12; Del. 4: An email copy of the construction completion certification package and PDF electronic copy of the signed and sealed Record Drawings will be submitted via email. Two Record Drawing hardcopies, 11"" X 17"", will also be submitted to the BDC, and one set of mylar record drawings will be submitted to Sarasota County under this subtask.
|
| Deliverable Price: $3,224.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 5 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 12; Del. 5: An email summary and electronic copy of statement of work will be completed during ...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 12; Del. 5: An email summary and electronic copy of statement of work will be completed during the workweek and will be submitted to BDC.
|
| Deliverable Price: $3,149.60 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 5 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 12; Del. 6: An email summary of lab findings will be submitted.
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 12; Del. 6: An email summary of lab findings will be submitted.
|
| Deliverable Price: $1,700.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 5 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 12; Del. 7: An email copy of the report will be submitted to BDC Project Manager.
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 12; Del. 7: An email copy of the report will be submitted to BDC Project Manager.
|
| Deliverable Price: $6,056.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 6 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 12; Del. 8: An electronic PDF copy of the Final Report will be submitted to BDC Project Manage...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 12; Del. 8: An electronic PDF copy of the Final Report will be submitted to BDC Project Manager via email.
|
| Deliverable Price: $1,808.90 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 6 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 12; Del. 9: TKW will email PDF of the site visit report.
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 12; Del. 9: TKW will email PDF of the site visit report.
|
| Deliverable Price: $1,555.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 7 |
| Deliverable Number: |
|