| More |
Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
Professional engineering services
|
As indicated in individual task assignments.
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: As indicated in individual task assignments.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Agreement without a financial exchange or impact |
| Performance Metrics: Prior to submission to the Department, the Consultant shall review all deliverables to ensure the same are accurate and complete at time of submittal and meet or exceed the specified deliverable.
|
| Financial Consequences: The Department will not pay for any unsatisfactory deliverables. In the event the Department deems a deliverable unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable at no additional cost to the Department within 15 consecutive days. If the Consultant fails to resubmit a satisfactory deliverable within the specified timeframe, the Department, in its sole discretion, may terminate the Task Assignment and/or Agreement for failure to perform.
|
| Source Documentation Page Reference: As indicated in individual task assignments. |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 1: Survey: The Consultant shall submit three 11”x17” sets of signed and sealed surve...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Subtask 1: Survey: The Consultant shall submit three 11”x17” sets of signed and sealed survey print sets and one (1) electronic copy in AutoCAD to the DEP Project Manager.
A1:Renewal. |
| Deliverable Price: $2,405.00 |
| Non Price Justification: |
| Performance Metrics: "The DEP Project Manager shall review the survey documents for proper signature and seal and for compliance with the “Minimum Technical Standards” outlined above to ensure satisfactory
completion of this Task."
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: 2 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 5, Subtask 8.1: Regional Utilities Fees for Setting Water Meters and Connecting Water and Sewer...
|
Cost Reimbursement
|
| Major Deliverable: Task 5, Subtask 8.1: Regional Utilities Fees for Setting Water Meters and Connecting Water and Sewer Services into Existing Regional Utilities System: The consultant will provide one copy of the Blue Sheet, copies of the check(s) to Regional Utility for payment of fees and receipt of payment from the Utility. Total cost not to exceed $2,286.00. CO6 adds Subtask 8.1
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: """The DEP Project Manager shall review the survey documents for proper signature and seal and for compliance with the “Minimum Technical Standards” outlined above to ensure satisfactory
completion of this Task.
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 2: Development of Conceptual Layout: The Consultant shall submit a Master Plan with ...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Subtask 2: Development of Conceptual Layout: The Consultant shall submit a Master Plan with corresponding presentation materials and documentation showing proof of attendance at the BOCC workshop.
|
| Deliverable Price: $7,549.52 |
| Non Price Justification: |
| Performance Metrics: The DEP Project Manager shall review the master plan development and approve the final proposed plan prior to the BOCC workshop and verify that the Consultant attended the BOCC workshop.
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: 2-3 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 3: The Consultant shall submit a signed and sealed written geotechnical report to th...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Subtask 3: The Consultant shall submit a signed and sealed written geotechnical report to the DEP Project Manager.
|
| Deliverable Price: $5,919.66 |
| Non Price Justification: |
| Performance Metrics: The DEP Project Manager shall review the geotechnical report to verify that all required elements are included and to ensure satisfactory completion of the services rendered. The Consultant shall be notified by the DEP Project Manager of any deficiencies in the deliverables and shall be given reasonable opportunity to provide revised deliverables.
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: 3-4 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 4.1: For each of the four design components above, the Consultant shall provide to t...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Subtask 4.1: For each of the four design components above, the Consultant shall provide to the DEP Project Manager (PM) one (1) electronic copy in pdf format and three (3) sets of 24”x36” 60% complete plans and specifications. CO1- increased deliverable price & added additional deliverables
|
| Deliverable Price: $2,443.27 |
| Non Price Justification: |
| Performance Metrics: The DEP Project Manager shall review each deliverable to ensure that the design components listed above are provided and are satisfactory. The Consultant shall be notified by the DEP Project Manager of any deficiencies in deliverables and shall be given reasonable opportunity to provide revised deliverables.
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: 1 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 4.2: For each of the three design components above, the Consultant shall provide one...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Subtask 4.2: For each of the three design components above, the Consultant shall provide one (1) electronic copy in pdf format and one (1) set of 24”x36” 60%- complete plans and specifications.
|
| Deliverable Price: $6,009.41 |
| Non Price Justification: |
| Performance Metrics: The DEP Project Manager shall review each deliverable to ensure that the design components listed above are provided and are satisfactory. The Consultant shall be notified by the DEP Project Manager of any deficiencies in deliverables and shall be given reasonable opportunity to provide revised deliverables.
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: 5-6 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1, Subtask 4.3: 100%(Final) Design Documents for the Amphitheater; Parking Area & Stormwater Fa...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1, Subtask 4.3: 100%(Final) Design Documents for the Amphitheater; Parking Area & Stormwater Facility; Restroom Renovations; and Landscaping & Irrigation Well. For each of the four design components above, the Consultant shall provide to the DEP Project Manager (PM) one (1) electronic copy in pdf format and three (3) sets of 24"x36" 60% complete plans and specifications. |
| Deliverable Price: $2,443.27 |
| Non Price Justification: |
| Performance Metrics: The DEP Project Manager shall review each deliverable to ensure that the design components listed above are provided and are satisfactory. The Consultant shall be notified by the DEP Project Manager of any deficiencies in deliverables and shall be given reasonable opportunity to provide revised deliverables.
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: 1-2 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 4.4, Change Order 1: The Consultant shall provide to the DEP PM one (1) hard copy a...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Subtask 4.4, Change Order 1: The Consultant shall provide to the DEP PM one (1) hard copy and one (1) electronic copy in PDF format of the structural assessment findings, including recommendations and specifications for minor renovations.
|
| Deliverable Price: $2,695.23 |
| Non Price Justification: |
| Performance Metrics: The DEP Project Manager shall review each deliverable to ensure that the design components listed above are provided and are satisfactory. The Consultant shall be notified by the DEP Project Manager of any deficiencies in deliverables and shall be given reasonable opportunity to provide revised deliverables.
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: 1-2 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 4.5, CO1: The Consultant shall provide to the DEP PM one (1) electronic copy in PDF...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Subtask 4.5, CO1: The Consultant shall provide to the DEP PM one (1) electronic copy in PDF format and three (3) sets of 24”x36” 100% (Final) Design Documents for the major pavilion renovations.
|
| Deliverable Price: $836.54 |
| Non Price Justification: |
| Performance Metrics: "The DEP Project Manager shall review the permit application to ensure satisfactory completion of the services provided. The Consultant shall be notified by the DEP Project Manager of any
deficiencies in the deliverables and shall be given reasonable opportunity to provide revised deliverables."
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: 2 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 4.6, CO3: The Consultant shall provide the DEP Project Manager with one CD in PDF fo...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Subtask 4.6, CO3: The Consultant shall provide the DEP Project Manager with one CD in PDF format of the revised 100% (Final) Design Documents that incorporate the additional plan sheets and specifications in 24" x 36" size. One of the 24" x 36" sets will be provided to the construction contractor.
|
| Deliverable Price: $1,449.30 |
| Non Price Justification: |
| Performance Metrics: The DEP Project Manager will review the Deliverables to ensure that the design components listed above are satisfactorily provided. The Consultant will be notified by the DEP Project Manager of any deficiencies in the Deliverables and be given reasonable opportunity to provide revised Deliverables.
|
| Financial Consequences: "No payment will be made for unsatisfactory deliverables. In the event that a
deliverable is deemed unsatisfactory, the Consultant shall re-perfonn the services needed for submittal of a satisfactory deliverable, atno additional cost to the Department within 15 consecutive days. If a satisfactory
deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform."
|
| Source Documentation Page Reference: 2 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 5.1: The Consultant will perform all necessary work to submit the required stormwate...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Subtask 5.1: The Consultant will perform all necessary work to submit the required stormwater management permit to the NWFWMD.
|
| Deliverable Price: $1,344.75 |
| Non Price Justification: |
| Performance Metrics: The DEP Project Manager shall review the permit application to ensure satisfactory completion of the services provided. The Consultant shall be notified by the DEP Project Manager of any deficiencies in the deliverables and shall be given reasonable opportunity to provide revised deliverables.
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: 7 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 5.2: The Consultant will provide a copy of the approved permit to the DEP Project Ma...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Subtask 5.2: The Consultant will provide a copy of the approved permit to the DEP Project Manager.
|
| Deliverable Price: $1,344.75 |
| Non Price Justification: |
| Performance Metrics: "The DEP Project Manager shall review the approved permit to ensure satisfactory
completion of the services provided. The Consultant shall be notified by the DEP Project Manager of any deficiencies in the deliverables and shall be given reasonable opportunity to provide revised deliverables."
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: 7 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 6: The Consultant shall submit written responses to RFI’s pertaining to the plans an...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Subtask 6: The Consultant shall submit written responses to RFI’s pertaining to the plans and technical specifications; record of attendance; and meeting notes from the pre-bid meeting.
|
| Deliverable Price: $2,657.16 |
| Non Price Justification: |
| Performance Metrics: The DEP Project Manager shall review the RFI responses, attendance record, and meeting notes to ensure satisfactory completion of the services rendered. The Consultant shall be notified by the DEP Project Manager of any deficiencies in the deliverables and shall be given reasonable opportunity to provide revised deliverables.
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: 8 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 7.1: The Consultant shall provide meeting notes from the preconstruction meeting, sh...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Subtask 7.1: The Consultant shall provide meeting notes from the preconstruction meeting, shop drawing submittals returned as “No exceptions”, “Rejected”, or “As Noted”, responses to RFIs, and written weekly field observation reports documenting construction progress.
|
| Deliverable Price: $4,355.87 |
| Non Price Justification: |
| Performance Metrics: The DEP Project Manager shall review meeting notes, shop drawings, RFI responses and field reports to ensure satisfactory completion of the services rendered. The Consultant shall be notified by the DEP Project Manager of any deficiencies in the deliverables and shall be given reasonable opportunity to provide revised deliverables.
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: 8 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 7.2: The Consultant shall provide shop drawing submittals returned as "No Exceptions...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task 1: Subtask 7.2: The Consultant shall provide shop drawing submittals returned as "No Exceptions", "Rejected", or "As Noted", responses to RFIs, and weekly written filed observation reports documenting construction progress and monthly written progress reports to the DEP Project Manager for review. Fixed Price/Unit Rate at $2,800.00/month with the total not to exceed $8,400.00. |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The DEP Project Manager shall review shop drawings, RFI responses, field reports and progress reports to ensure satisfactory completion of the services rendered. The Consultant shall be notified by the DEP Project Manager of any deficiencies in the deliverables and shall be given reasonable opportunity to provide revised deliverables.
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: T1, Page 9 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 8: The Consultant shall submit the Certificate of Substantial Completion of Construc...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Subtask 8: The Consultant shall submit the Certificate of Substantial Completion of Construction, any Punch Lists, and the Verification of Final Completion of Construction to the DEP Project Manager.
|
| Deliverable Price: $582.27 |
| Non Price Justification: |
| Performance Metrics: The DEP Project Manager will review the respective Punch Lists, Certification of Substantial Completion, and the Verification of Final Completion documents to ensure satisfactory completion of this Task.
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: 9 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 9: The Consultant shall submit two (2) electronic copies in pdf format of the record...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Subtask 9: The Consultant shall submit two (2) electronic copies in pdf format of the record drawings for the project to the DEP Project Manager.
|
| Deliverable Price: $750.51 |
| Non Price Justification: |
| Performance Metrics: The DEP Project Manager will review the record drawings to ensure satisfactory completion of the Task.
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: 9-10 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 2: Subtask 1: The Consultants will provide to the DEP PM: • Three 11 ""x17"" printed sets of si...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 2: Subtask 1: The Consultants will provide to the DEP PM: • Three 11 ""x17"" printed sets of signed and sealed survey • CD containing one (1) electronic copy In AutoCAD as well as a PDF file of survey. |
| Deliverable Price: $2,950.00 |
| Non Price Justification: |
| Performance Metrics: "The DEP Project Manager shall review the survey documents for proper signature and seal and for compliance with the ""Minimum Technical
Standards"" outlined above to ensure satisfactory completion of this Task;"
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: TA2 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 2: Subtask 2.1: The Consultants will provide to the DEP PM: • One (1) paper copy of 30% submitt...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 2: Subtask 2.1: The Consultants will provide to the DEP PM: • One (1) paper copy of 30% submittal construction documents • One (1) CD containing a PDF of 30% submittal construction documents. |
| Deliverable Price: $5,197.30 |
| Non Price Justification: |
| Performance Metrics: The Task 2.1 Deliverables will be reviewed by the DEP PM to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: TA2 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 2: Subtask 2.2: The 60% design submittal for the Construction Documents shall include,
at a min...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 2: Subtask 2.2: The 60% design submittal for the Construction Documents shall include,
at a minimum, the following: • Outline specifications
• Geotechnical Report • Cover Sheet • Updated Demolition/Clearing Plan • Updated Site Plan with proposed dock improvements located • Updated Elevations of proposed dock improvements • Sections (min. of 2) of dock • Details and Enlarged Sections showing construction materials • Grading and any pertinent store water design documents. |
| Deliverable Price: $6,493.43 |
| Non Price Justification: |
| Performance Metrics: "The Task 2.2 Deliverables will be reviewed by the DEP PM to confirm that they are complete, accurate, and timely."
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: TA2 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 2: Subtask 2.3: The Consultants will provide to the DEP PM: • One (1) paper copy of 90% submit...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 2: Subtask 2.3: The Consultants will provide to the DEP PM: • One (1) paper copy of 90% submittal construction documents • One (1) paper copy of 90% Opinion of Probable Construction Cost (OPCC)
• One ( 1 ) CD containing PDF of 90% submittal construction documents o PDF of OPCC. |
| Deliverable Price: $1,433.70 |
| Non Price Justification: |
| Performance Metrics: "The Task 2.3 Deliverables will be reviewed by the OEP PM to confirm that they are complete, accurate, and timely."
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: TA2 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 2: Subtask 2.4: The Consultants will provide to the DEP PM: • Five (5) paper copy sets of signe...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 2: Subtask 2.4: The Consultants will provide to the DEP PM: • Five (5) paper copy sets of signed and sealed plans • One ( 1) paper copy of final OPCC • One ( 1 ) CD containing PDF of signed and sealed plans o PDF of final OPCC o Design files in AutoCAD 2015 of signed and sealed plans . |
| Deliverable Price: $1,421.29 |
| Non Price Justification: |
| Performance Metrics: "The Task 2.4 Deliverables will be reviewed by the DEP PM to confirm that they are complete, accurate, and timely"
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: TA2 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 2: Subtask 3.1: Permit approvals
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 2: Subtask 3.1: Permit approvals
|
| Deliverable Price: $3,676.35 |
| Non Price Justification: |
| Performance Metrics: "DEP Contract Manager shall review pennant applications to ensure satisfactory completion of the services provided. The Consultant shall be notified by the DEP Project Manager of any deficiencies in deliverables and shall be given reasonable opportunity to provide revised deliverables. DEP Project Manager shall review approved penults to ensure satisfactory completion of the services provided. The Consultant shall be notified by the DEP Project Manager of any deficiencies in deliverables and shall be given reasonable opportunity to provide revised deliverables.
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: TA2 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 2: Subtask 4: Written responses to RFl's pertaining to the plans and technical specifications.
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 2: Subtask 4: Written responses to RFl's pertaining to the plans and technical specifications.
|
| Deliverable Price: $2,319.88 |
| Non Price Justification: |
| Performance Metrics: DEP Project Manager shall review the RFI responses to
ensure satisfactory completion of the services rendered. The Consultant shall be notified by the DEP Project Manager of any deficiencies In deliverables and shall be given reasonable opportunity to provide revised deliverables.
|
| Financial Consequences: No payment will be made for incomplete or unsatisfactory Deliverables. In the event that a Deliverable is deemed incomplete or unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory Deliverable at no additional cost to the DEP within fifteen (15) consecutive days. If a satisfactory Deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the Contract for failure to Perform.
|
| Source Documentation Page Reference: TA2 |
| Deliverable Number: |
|