Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
Professional engineering services
|
Task 8, Subtask 8A - FDEP ERP field Permit or Exemption - One electronic copy to BDC Project Manager...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 8, Subtask 8A - FDEP ERP field Permit or Exemption - One electronic copy to BDC Project Manager. Permit x 1 = $500.00, Project Manager $125.46 x 4 hrs. = $501.84, Environmental Scientist $135.57 x hrs. = $1,084.56; GIS Technician $92.04 x 8 hrs. = $736.32. Subtask total $2,822.72. |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform
|
| Source Documentation Page Reference: CO1 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 8, Subtask 3: 60% Civil/Structural Drawings, 1 electronic copy (for review only). Send pdf copy...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 8, Subtask 3: 60% Civil/Structural Drawings, 1 electronic copy (for review only). Send pdf copy via email to BDC Project Manager the Engineers Opinion of Probable Construction Costs. |
| Deliverable Price: $15,451.68 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. |
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: Task 8 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 8, Subtask 7: 60% Civil/Structural Drawings, 1 electronic copy (for review only). Send pdf copy...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 8, Subtask 7: 60% Civil/Structural Drawings, 1 electronic copy (for review only). Send pdf copy of the Engineer Opinion of Probable Construction Costs via email to BDC Project Manager. |
| Deliverable Price: $8,970.48 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 8, Subtask 4A: Permitting; FDEP ERP Field Permit or Exemption / One Electronic copy to BDC Proj...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 8, Subtask 4A: Permitting; FDEP ERP Field Permit or Exemption / One Electronic copy to BDC Project Manager. Fixed Price Cost $3,059.04. Permits not to exceed $500.00. Task total not to exceed $3,559.04.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 9: Subtask 1 Structural; Structural Assessment Report, the Engineers Opinion of Probable Constr...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 9: Subtask 1 Structural; Structural Assessment Report, the Engineers Opinion of Probable Construction Costs I electronic copy sent to BDC project manager via email. Fixed Price Costs: $8,497.44 Reimbursable Costs for travel at .445 mileage rate: $71.20 Task total not to exceed: $8,568.64
|
| Deliverable Price: $0.00 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 9: Subtassk 2A; Boundary Survey Services; Deliverable will be a signed and sealed plot of the B...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 9: Subtassk 2A; Boundary Survey Services; Deliverable will be a signed and sealed plot of the Boundary Survey, pdf and native AutoCad digital file delivered to BCD Project Manager. CO1: Adds Subtask 2A, increases task amount
|
| Deliverable Price: $5,632.68 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 3 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 9: Subtask 2B; Topographic Survey Services; Deliverable will be a DTM, an AutoCAD, and a signed...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 9: Subtask 2B; Topographic Survey Services; Deliverable will be a DTM, an AutoCAD, and a signed and sealed plot of the Topographic Survey./One Electronic copy to BOC Project Manager. CO1 : Adds Subtask 2B, increases task amount
|
| Deliverable Price: $6,253.74 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 3 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 9: Subtask 2C; 3D Laser Scan of Home; Deliverable will be a signed and sealed Surveyor's Rep011...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 9: Subtask 2C; 3D Laser Scan of Home; Deliverable will be a signed and sealed Surveyor's Rep011 describing methods implemented, accuracies, and the results of the scan data. An electronic copy of the registered point cloud in AutoCAD ReCAP format or to any AutoCAD compatible format, (i.e .. LAS, .PTS, .XYZ) requested by the CLIENT. CO1: Adds Subtask 2C, increases task amount
|
| Deliverable Price: $8,241.24 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 4 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 9: Subtask 3, Geotechnical; One(]) Signed & Sealed hard copies and electronic files via email t...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 9: Subtask 3, Geotechnical; One(]) Signed & Sealed hard copies and electronic files via email to BDC Project Manager.CO1: Adds Subtask 3, increases task amount
|
| Deliverable Price: $4,778.82 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 4 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 9: Subtask 4 Strcutrual/Life Safety Assessment; Structural/Life Safety Site Assessment Report, ...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 9: Subtask 4 Strcutrual/Life Safety Assessment; Structural/Life Safety Site Assessment Report, the Engineer's Opinion of Probable Construction Costs, 1 electronic copy (for review only). Send pdf copy via email to BDC Project Manager. Fixed Price Cost: $35,890.80 Reimbursable cost for travel at .445 mileage rate: $213.60 Task total not to exceed: $36104.40 CO1: Adds Subtask 4, increases task amount
|
| Deliverable Price: $0.00 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 5 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 9: Subtask 5A Representation of Civil Engieering Services; Development Meetings - Meeting Minut...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 9: Subtask 5A Representation of Civil Engieering Services; Development Meetings - Meeting Minutes/ One Electronic copy to BOC Project Manager. CO1: Adds Subtask 5A, increases task amount
|
| Deliverable Price: $2,007.36 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 6 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 9: Subtask 5B Drainage Statement; Drainage Statement/ One Electronic copy to BOC Project Manage...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 9: Subtask 5B Drainage Statement; Drainage Statement/ One Electronic copy to BOC Project Manager. CO1: Adds Subtask 5B, increases task amount
|
| Deliverable Price: $5,191.92 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 7 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 9: Subtask 5C Engineering Design; Engineering Design-Meeting Minutes, Conceptual grading, drain...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 9: Subtask 5C Engineering Design; Engineering Design-Meeting Minutes, Conceptual grading, drainage, paving documents for review and comment by BOC Project Manager/ One Electronic copy to BOC Project Manager. Co1: Adds Subtask 5C, increases task amount
|
| Deliverable Price: $15,036.48 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 7 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 9: Subtask 5D Regulatory Agency Permitting; Permits - DERM and Coral Gables (PGD) Permit or Exe...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 9: Subtask 5D Regulatory Agency Permitting; Permits - DERM and Coral Gables (PGD) Permit or Exemption/ One Electronic copy to BOC Project Manager Fixed Price Cost: $6583.68 Reimbursable cost for travel at .445 mileage rate: $642.20 Task total not to exceed: $7226.08
|
| Deliverable Price: $0.00 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 7 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 9: Subtask 6A Conceptual Landscape Design; Development Meetings - Meeting Minutes I One Electro...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 9: Subtask 6A Conceptual Landscape Design; Development Meetings - Meeting Minutes I One Electronic copy to BDC Project Manager. CO1: Adds Subtask 6A, increases task amount
|
| Deliverable Price: $4,355.52 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 8 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 9: Subtask 6B Design Development Package; Landscape Development Documents I One Electronic copy...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 9: Subtask 6B Design Development Package; Landscape Development Documents I One Electronic copy to BDC Project Manager, pdf and native Auto Cad digital file delivered to BCD Project Manager. An opinion of probable construction costs to be delivered digitally to BDC Project Manager. Fixed Price Cost: $7104.42 Reimbursable cost for travel at .445 mileage rate: $213.60 Task total not to exceed: $9240.42. CO1: Adds Subtask 6B, increases task amount
|
| Deliverable Price: $0.00 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 8 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 9: Subtask 7A Conceptual Archietctural Design; Summa1y report, including conceptual design draw...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 9: Subtask 7A Conceptual Archietctural Design; Summa1y report, including conceptual design drawings, as noted above in Subtask 7A. CO1: Adds Subtask 7A, increases task amount
|
| Deliverable Price: $7,979.40 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 9 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 9: Subtask 7B Design Development Package; Design Development drawings for design solution, spec...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 9: Subtask 7B Design Development Package; Design Development drawings for design solution, specification review comments and recommendations, pdf digital file delivered to BDC Project Manager. An opinion of probable construction costs to be delivered digitally to BDC Project manager. Fixed Price Cost: $8519.68 Reimbursable cost for travel at ..45 mileage rate: $651.48 Task total not to exceed: $9171.16 CO1: Adds Subtask 7B, increases task amount
|
| Deliverable Price: $0.00 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 9 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 9: Subtask 8 60% Construction Documents; 60% Civil, Structural and Landscape Drawings, one pdf ...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 9: Subtask 8 60% Construction Documents; 60% Civil, Structural and Landscape Drawings, one pdf drawing, updated opinion of probable cost delivered electronically to BDC Pr??ject Manager. CO1: Adds Subtask 8, increases task amount
|
| Deliverable Price: $22,103.34 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 10 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 9: Subtask 9 100% Construction Documents; 100% Construction Drawings, 2 Signed & Sealed copies,...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 9: Subtask 9 100% Construction Documents; 100% Construction Drawings, 2 Signed & Sealed copies, 1 Signed & Sealed Electronic copy, updated opinion of probable cost and the native AutoCad dwgs and suppott files to BOC Project Manager. Fixed Price Cost: $15970.98 Reimbursable cost for travel at .445 mileage rate: $100.00 Task total not to exceed: $16070.98 Co1: Adds Subtask 9, increases task amount
|
| Deliverable Price: $0.00 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 11 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 5: Permit from SFWMD for drainage. Fixed price $796.08; reimbursable permit $250. Cost not to e...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 5: Permit from SFWMD for drainage. Fixed price $796.08; reimbursable permit $250. Cost not to exceed $1,046.08
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform
|
| Source Documentation Page Reference: 6 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 5: Permit from Okeechobee County Health Department (FDEP) for septic system. Fixed price $1,341...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 5: Permit from Okeechobee County Health Department (FDEP) for septic system. Fixed price $1,341.24; reimbursable permit $415. Cost not to exceed $1,756.24
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform
|
| Source Documentation Page Reference: 6 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 5: Permit from State Fire Marshal. Fixed price $796.08; reimbursable permit $250. Cost not to e...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 5: Permit from State Fire Marshal. Fixed price $796.08; reimbursable permit $250. Cost not to exceed $1,046.08
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform
|
| Source Documentation Page Reference: 7 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 5: Subtask 1A - Site Review Report including field photos and field notes. Cost not to exceed $...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 5: Subtask 1A - Site Review Report including field photos and field notes. Cost not to exceed $3,899.52. Subtask 1B - Design Documentation Report including all necessary design standards $868.20.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform
|
| Source Documentation Page Reference: 3 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 6, Subtask 2: Pre-construction - Meeting minutes to be delivered with accompanying photographs ...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 6, Subtask 2: Pre-construction - Meeting minutes to be delivered with accompanying photographs in .pdf format. Fixed price $1,415.16; reimbursable mileage not to exceed $97.01. Total cost not to exceed $1,512.17.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|