Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
Professional engineering services
|
Task 1, Del. 2: Meeting Minutes from two (2) meetings in support of securing an Individual Permit.
|
No Cost
|
| Major Deliverable: Task 1, Del. 2: Meeting Minutes from two (2) meetings in support of securing an Individual Permit.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The deliverable(s) shall be reviewed by Department staff to ensure the documents are complete as described in Task 2. The documents shall be provided electronically in MS Word, AutoCAD, and image .pdf, .jpg, .tif, etc. formats where applicable.
|
| Financial Consequences: "No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of
a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a
satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform."
|
| Source Documentation Page Reference: 3 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1, Del. 1: Response to one (1) comprehensive RAI from the Corps and receipt of Corps Individual...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1, Del. 1: Response to one (1) comprehensive RAI from the Corps and receipt of Corps Individual Permit
|
| Deliverable Price: $11,214.23 |
| Non Price Justification: |
| Performance Metrics: The deliverable(s) shall be reviewed by Department staff to ensure they are complete and meet the requirements described in Task 1b. Documents shall be provided electronically in MS Word, AutoCAD, and image .pdf, .jpg, .tif, etc. formats where applicable.
|
| Financial Consequences: "No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of
a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a
satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform."
|
| Source Documentation Page Reference: 2 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
As indicated in individual task assignments.
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: As indicated in individual task assignments.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Prior to submission to the Department, the Consultant shall review all deliverables to ensure the same are accurate and complete at time of submittal and meet or exceed the specified deliverable.
|
| Financial Consequences: The Department will not pay for any unsatisfactory deliverables. In the event the Department deems a deliverable unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable at no additional cost to the Department within 15 consecutive days. If the Consultant fails to resubmit a satisfactory deliverable within the specified timeframe, the Department, in its sole discretion, may terminate the Task Assignment and/or Agreement for failure to perform.
|
| Source Documentation Page Reference: CN328 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 2, Subtask 8: Additional Mobilization for Bathymetry & Topography, A notice of deployment and ...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 2, Subtask 8: Additional Mobilization for Bathymetry & Topography, A notice of deployment and a digital copy of the re-mobilization report will be emailed to the BDC.
CO1: Add Task 2, Subtask 8 |
| Deliverable Price: $444.97 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 2, Subtask 9: Additional Mobilization for Marine Resources Survey; Scanned field data sheets wi...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 2, Subtask 9: Additional Mobilization for Marine Resources Survey; Scanned field data sheets will be provided to BOC.
CO1: Add Task 2, Subtask 9 |
| Deliverable Price: $5,151.20 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 2, Subtask 7: Coastal Alternatives Permitting Analysis; A summary of the teleconference will be...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 2, Subtask 7: Coastal Alternatives Permitting Analysis; A summary of the teleconference will be emailed to the BDC.
CO1: Decrease in Task 2, Subtask 7 dollar amount |
| Deliverable Price: $1,807.08 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1, Del 3, CO1: Preparation and submittal of UMAM Part 1 and Part 2 forms to the USA CE
CO2 - De...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1, Del 3, CO1: Preparation and submittal of UMAM Part 1 and Part 2 forms to the USA CE
CO2 - Delete subtask 2 from TA1 and move $3,479.52, as shown in the SOW, to Subtask 1b, which is hereby changed to task 1. No change in overall TA1 price.
|
| Deliverable Price: $4,576.55 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 2 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 2, Subtask 1: Bathymetry & Topography
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 2, Subtask 1: Bathymetry & Topography
|
| Deliverable Price: $6,170.90 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 2, Subtask 2: Marine Resources Survey
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 2, Subtask 2: Marine Resources Survey
|
| Deliverable Price: $15,286.60 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 2, Subtask 3: Coastal Studies and Measurements
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 2, Subtask 3: Coastal Studies and Measurements
|
| Deliverable Price: $12,355.12 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 2, Subtask 4: Base Map
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 2, Subtask 4: Base Map
|
| Deliverable Price: $2,563.10 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 2, Subtask 5: Field Observation Report
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 2, Subtask 5: Field Observation Report
|
| Deliverable Price: $5,067.14 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 2, Subtask 6: Coastal Alternatives Modeling
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 2, Subtask 6: Coastal Alternatives Modeling
|
| Deliverable Price: $19,145.42 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 3 Subtask 1 Topography & Beach Profiles: A digital survey file will be emailed to the Bureau of...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 3 Subtask 1 Topography & Beach Profiles: A digital survey file will be emailed to the Bureau of Design and Construction (BDC). Fixed Price total- $9,797.62. Reimbursable Printing cost - $8.00, Mileage cost - $142.00, Survey Equipment cost - $300.00, Handheld Radio cost - $150.00, Snorkel Gear cost - $50.00, RTK R10 GPS cost - $975.00, Handheld GPS cost - $50.00, Upland Camera cost - $50 and Sand Collection Equipment cost - $30.00. Total Reimbursable not to Exceed total Cost of - $1,805.00
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: Pg. 3 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 3 Subtask 2 Coastal Modeling: A digital copy of the Coastal Engineering Report will be emailed ...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task 3 Subtask 2 Coastal Modeling: A digital copy of the Coastal Engineering Report will be emailed to the BDC.
|
| Deliverable Price: $10,914.02 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: Pg. 4 |
| Deliverable Number: |
|