| More |
Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
Nonresidential building construction services
|
Master Contract with Mead and Hunt, Inc. to complete the FKOHT - Bridges Project in Monroe County, F...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Master Contract with Mead and Hunt, Inc. to complete the FKOHT - Bridges Project in Monroe County, Florida.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 1: Preliminary Engineering Research and Inventory: Electronic files (PFD files) summ...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Subtask 1: Preliminary Engineering Research and Inventory: Electronic files (PFD files) summarizing understanding of documents provided by FDEP. This
may include spreadsheets tabulating aspects of each bridge or brief summaries of the documents and/or
technical memos.
|
| Deliverable Price: $19,032.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 3 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 2A: Bridge Assessment: Field Inspection; Visual: PDF of field notes and photo record...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 1: Subtask 2A: Bridge Assessment: Field Inspection; Visual: PDF of field notes and photo record documenting general work performed. Reimbursable total cost is $15,851 not to exceed $95,279.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 4 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 2B: Bridge Assessment: Drone:Drone video recordings with GPS positioning. Reimbursab...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 1: Subtask 2B: Bridge Assessment: Drone:Drone video recordings with GPS positioning. Reimbursable total cost is $2,678 not to exceed $10,130.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 4 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 2C: Bridge Assessment: Report: PDF of Assessment Report signed and sealed by Enginee...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Subtask 2C: Bridge Assessment: Report: PDF of Assessment Report signed and sealed by Engineer of Record.
|
| Deliverable Price: $27,018.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 4 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 3A1: Cultural Resources: Agency Coordination (Meetings 1 & 2 meetings): First two me...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Subtask 3A1: Cultural Resources: Agency Coordination (Meetings 1 & 2 meetings): First two meetings final meeting minutes summarizing results of initial
coordination with FDEP and FDHR/SHPO. (PDF file).
|
| Deliverable Price: $10,552.50 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 6 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
"Task 1: Subtask 3A2: Agency Coordination (Up to 2 additional meetings): Last two additional meeting...
|
Fixed Price - Lump Sum
|
| Major Deliverable: "Task 1: Subtask 3A2: Agency Coordination (Up to 2 additional meetings): Last two additional meeting final meeting minutes summarizing results of
initial coordination with FDEP and FDHR/SHPO. (PDF file)."
|
| Deliverable Price: $10,552.50 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 6 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 3B: FDOT District 6 Coordination: PDF of notes and important facts from the FDOT Dis...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Subtask 3B: FDOT District 6 Coordination: PDF of notes and important facts from the FDOT District 6 coordination. Technical Memo (PDF) outlining the environmental documentations requirements (PD&E or NEPA) for compliance with state and/or federal requirements depending on funding sources.
|
| Deliverable Price: $18,354.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 6 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 3C: Preliminary Historical/Engineering Research and Inventory: Technical Memo outlin...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 1: Subtask 3C: Preliminary Historical/Engineering Research and Inventory: Technical Memo outlining results of research and inventory. Reimbursable total cost is $4,085 not to exceed $56,555.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 6 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Subtask 3D: Cultural Resources Management Technical Memorandum: Digital Technical Memo outli...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Subtask 3D: Cultural Resources Management Technical Memorandum: Digital Technical Memo outlining cultural resource management.
|
| Deliverable Price: $12,990.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 6 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
"Task 1: Subtask 4A: Environmental Services (Terramar): Rapid Environmental Condition Assessment: Su...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: "Task 1: Subtask 4A: Environmental Services (Terramar): Rapid Environmental Condition Assessment: Summary report of the bridges evaluated with descriptions of habitats, coral resources
and photos of typical environmental conditions organized by bridge location. This will serve as an
agency briefing document for Task 4B meetings. Reimbursable total cost is $2,875 not to exceed $44,763."
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 10 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
"Task 1: Subtask 4B: Agency pre-application meetings: Summary memorandum of the mee??ng notes with t...
|
Fixed Price - Lump Sum
|
| Major Deliverable: "Task 1: Subtask 4B: Agency pre-application meetings: Summary memorandum of the mee??ng notes with the various regulatory agencies,
including South Florida Water Management District, US Army Corps of Engineers, and Florida Keys
Na??onal Marine Sanctuary."
|
| Deliverable Price: $19,712.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 10 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Change Order 1: Task 5A: PDF of 60% phase 11x17 constructon plans with Construction Cost Est...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Change Order 1: Task 5A: PDF of 60% phase 11x17 constructon plans with Construction Cost Estimate.
|
| Deliverable Price: $278,196.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 4 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Change Order 1: Task 5B: PDF of 90% phase 11x17 construction plans with Construction Cost Es...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Change Order 1: Task 5B: PDF of 90% phase 11x17 construction plans with Construction Cost Estimate.
|
| Deliverable Price: $167,052.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 4 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Change Order 1: Task 5C: PDF of Signed and Sealed final 11x17 construction plans.
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Change Order 1: Task 5C: PDF of Signed and Sealed final 11x17 construction plans.
|
| Deliverable Price: $111,252.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 4 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Change Order 1: Task 6A1: Draft documentation submital packet for FDEP review. (PDF file).
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Change Order 1: Task 6A1: Draft documentation submital packet for FDEP review. (PDF file).
|
| Deliverable Price: $20,388.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 6 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Change Order 1: Task 6A2: Final documentation submital packet for FDHR/SHPO. (PDF file).
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Change Order 1: Task 6A2: Final documentation submital packet for FDHR/SHPO. (PDF file).
|
| Deliverable Price: $4,854.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 6 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Change Order 1: PDF of notes from meetings with FDHR/SHPO meetings.
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Change Order 1: PDF of notes from meetings with FDHR/SHPO meetings.
|
| Deliverable Price: $10,506.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 7 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Change Order 1: Task 6.C.1: Draft MSFs (PDF file).
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Change Order 1: Task 6.C.1: Draft MSFs (PDF file).
|
| Deliverable Price: $35,646.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 9 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Change Order 1: Task 6.C.2: Final MSFs for submital to FDHR/SHPO. (PDF file).
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Change Order 1: Task 6.C.2: Final MSFs for submital to FDHR/SHPO. (PDF file).
|
| Deliverable Price: $32,628.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 9 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Change Order 1: Task 7A – South Florida Water Management District ERP Permitting. The delive...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Change Order 1: Task 7A – South Florida Water Management District ERP Permitting. The deliverable for this task will be all application submital documents and the
South Florida Water Management District Environmental Resource Permit. |
| Deliverable Price: $12,320.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 11 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Change Order 1: Subtask 7B: Benthic Resource Assessment for In-Water Slabs. A writen benthic...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 1: Change Order 1: Subtask 7B: Benthic Resource Assessment for In-Water Slabs. A writen benthic resource assessment that meets the current requirements of
FKNMS. Fixed Price Cost: $17,024.00. Reimbursable Cost: $1,150.00 |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 12 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Change Order 1: Task 7C - FKNMS Permit Application and Processing. The deliverable for this ...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Change Order 1: Task 7C - FKNMS Permit Application and Processing. The deliverable for this task will be all application submital documents and the
Florida Keys National Marine Sanctuary authorization. |
| Deliverable Price: $13,664.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 13 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 1: Change Order 1: Task 7D - USACE Permit Application and Processing. The deliverable for this ...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Change Order 1: Task 7D - USACE Permit Application and Processing. The deliverable for this task will be all application submital documents and the US
Army Corps of Engineers No Permit Required authorization. |
| Deliverable Price: $12,320.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 14 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
"Task 1: Change Order 1: Subtask 7E: Bat Survey. A written Bat Survey Report that summarizes the obs...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: "Task 1: Change Order 1: Subtask 7E: Bat Survey. A written Bat Survey Report that summarizes the observations made on the bridges
proposed for rehabilition including a concise conclusion regarding the presence / absence on
bats. Fixed Price Cost: $14,784.00. Reimbursable Cost: $2,300.00"
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: 15 |
| Deliverable Number: |
|