| More |
Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
CIVIL ENGINEERS
|
Professional Civil Engineering Services. Deliverables established on a Task Assignment basis.
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Professional Civil Engineering Services. Deliverables established on a Task Assignment basis. |
| Deliverable Price: $0.00 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Deliverables reviewed to ensure compliance with specifications in contract and each executed task assignment. |
| Financial Consequences: No payment for unsatisfactory deliverables or servcies. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Civil engineering
|
Task 2: (1) 11"x17" hardcopy and pdf file of the collected topographic data located within the defin...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task 2: (1) 11"x17" hardcopy and pdf file of the collected topographic data located within the defined project area $1,988.50. (2) Upon completion of preliminary layout design, WGI will submit three 11"x17" hardcopy exhibits, one of each layout as well as a pdf file of each layout $7,081. (3) One hard copy estimate report along with a pdf file for the cost estimate $873. Hourly rates: 2 man Field Crew $116.40, CADD Technician $77.60, Environmental Scientist $111.55, Sr. Professional Surveyor $145.50, Project Manager $169.75, Sr. Professional Engineer $145.50. |
| Deliverable Price: $9,942.50 |
| Non Price Justification: |
| Performance Metrics: (1) Deliverable will be reviewed by the Department to confirm it is complete, accurate and timely. Subsequently, the deliverable for this task will be in compliance with the Standards of Practice as set forth by the Florida Board of Professional Surveyors and Mappers in Chapter 5J-17 F.A.C. (pursuant to Section 472.027 F.S.). (2) Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely. (3) Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely. |
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform. |
| Source Documentation Page Reference: TA2 |
| Deliverable Number: |
|
|
|
|
Civil engineering
|
Task 1: (st 1) Three (3) hard copies of a 24"x36" survey base sheet and a PDF file via email $4,127....
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task 1: (st 1) Three (3) hard copies of a 24"x36" survey base sheet and a PDF file via email $4,127.35. (st 2) Three (3) hard copies of a 24"x36" 60% construction plan and a PDF file via email $2,155.82. (st 3) One written report of the results of the site plan review and a PDF file via email $4,596.25. (st 3) Three (3) hard copies of a 24"x36" 100% construction plan and a PDF file via email $2,155.83. (st 4) A copy of the submitted permit application, secured permit and South Florida Water Management District certification and a PDF file via email $597.70. Additional survey, site plan revisions, engineering design, sign and seal restroom drawings, permitting $10,261.65. CO1 - added new deliverable and increased funding.Additional survey, site plan revisions, engineering design, sign and seal restroom drawings, permitting $10,261.65. CO2 - Additional A/E services to include: architectural, geotechnical, mechanical, electrical, plumbing engineering, signed and scaled restroom construction drawings, permit fee, revise plumbing drawings, structural review of truss shop drawing, coordination sub-consultants $8,900.06. |
| Deliverable Price: $32,794.66 |
| Non Price Justification: |
| Performance Metrics: Professional services completed in order to obtain permits, bid project and receive appropriate construction completion certificates. |
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T1CO2 |
| Deliverable Number: |
|
|
|
1
|
Professional engineering services
|
Task 3: Upon completion of the design, WGI will submit 3- 11 "x 17" hardcopy signed and sealed drawi...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 3: Upon completion of the design, WGI will submit 3- 11 "x 17" hardcopy signed and sealed drawings and a PDF file of the design. Deliverables for Task I will be submitted to FDEP within 10 business days after receiving notification to proceed by FDEP.
|
| Deliverable Price: $2,056.40 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: TA3 |
| Deliverable Number: 1 |
|
|
|
2
|
Professional engineering services
|
Task 3: Upon completion of the design, WGI will submit a completed permit application and drawings t...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 3: Upon completion of the design, WGI will submit a completed permit application and drawings to FDOT. Deliverables for Task 2 will be submitted to FDOT within 15 business days after receiving notification to proceed by FDEP.
|
| Deliverable Price: $1,164.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: TA3 |
| Deliverable Number: 2 |
|
|
|
3
|
Professional engineering services
|
Task 3: WGI will submit written clarification, if needed, within 3 business days after receiving a
r...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 3: WGI will submit written clarification, if needed, within 3 business days after receiving a
request from FDEP.
|
| Deliverable Price: $1,746.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm they are complete, accurate and timely.
|
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: TA3 |
| Deliverable Number: 3 |
|