Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
ENVIRONMENTAL CLEANUP AND RESTORATION
|
Task 1: Reported discharge inspections, installation inspections, closure inspections, and re-insp...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: Reported discharge inspections, installation inspections, closure inspections, and re-inspections for at least 85% of listed facilities. |
| Deliverable Price: $518,831.67 |
| Non Price Justification: |
| Performance Metrics: The CONTRACTOR should have completed the following required routine compliance inspections unless otherwise indicated in the Task Assignment;
1.After Four Months should have completed 33% of inspections.
2.After 8 months should have completed 66% of inspections.
3.After 12 months should have completed 100% of inspections
If number of required routine compliance inspections falls below twenty percent (20%) for the fourth month, thirty percent (30%) for the fifth month, forty percent (40%) for the sixth month, forty-eight percent (48%) for the seventh month, fifty-seven percent (57%) for the eighth month, sixty-five percent (65%) for the ninth month, seventy-three percent (73%) for the tenth month or eighty-two percent for (82%) the eleventh month, then the CONTRACTOR shall submit a Corrective Action Plan, within ten (10) days of receipt of a written request from the DEP Task Manager.
|
| Financial Consequences: If the CONTRACTOR does not successfully implement the Plan as approved by the DEP Task Manager for the remaining months of the Task Assignment, the DEP may withhold further payment of monthly invoices until such time as the CONTRACTOR comes into compliance with those performance levels as outlined in the Performance Metrics. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
ENVIRONMENTAL CLEANUP AND RESTORATION
|
Task 2: Reported discharge inspections, installation inspections, closure inspections, and re-insp...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 2: Reported discharge inspections, installation inspections, closure inspections, and re-inspections for at least 75% of listed facilities./ Change Order No. 2 decreased funds. |
| Deliverable Price: $499,401.75 |
| Non Price Justification: |
| Performance Metrics: The CONTRACTOR should have completed the following required routine compliance inspections unless otherwise indicated in the Task Assignment;
1.After Four Months should have completed 33% of inspections.
2.After 8 months should have completed 66% of inspections.
3.After 12 months should have completed 100% of inspections
If number of required routine compliance inspections falls below twenty percent (20%) for the fourth month, thirty percent (30%) for the fifth month, forty percent (40%) for the sixth month, forty-eight percent (48%) for the seventh month, fifty-seven percent (57%) for the eighth month, sixty-five percent (65%) for the ninth month, seventy-three percent (73%) for the tenth month or eighty-two percent for (82%) the eleventh month, then the CONTRACTOR shall submit a Corrective Action Plan, within ten (10) days of receipt of a written request from the DEP Task Manager.
|
| Financial Consequences: If the CONTRACTOR does not successfully implement the Plan as approved by the DEP Task Manager for the remaining months of the Task Assignment, the DEP may withhold further payment of monthly invoices until such time as the CONTRACTOR comes into compliance with those performance levels as outlined in the Performance Metrics. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
ENVIRONMENTAL CLEANUP AND RESTORATION
|
Task 3: Reported discharge inspections, installation inspections, closure inspections, and re-insp...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 3: Reported discharge inspections, installation inspections, closure inspections, and re-inspections for at least 75% of listed facilities. |
| Deliverable Price: $377,684.86 |
| Non Price Justification: |
| Performance Metrics: The CONTRACTOR should have completed the following required routine compliance inspections unless otherwise indicated in the Task Assignment;
1.After Four Months should have completed 33% of inspections.
2.After 8 months should have completed 66% of inspections.
3.After 12 months should have completed 100% of inspections
If number of required routine compliance inspections falls below twenty percent (20%) for the fourth month, thirty percent (30%) for the fifth month, forty percent (40%) for the sixth month, forty-eight percent (48%) for the seventh month, fifty-seven percent (57%) for the eighth month, sixty-five percent (65%) for the ninth month, seventy-three percent (73%) for the tenth month or eighty-two percent for (82%) the eleventh month, then the CONTRACTOR shall submit a Corrective Action Plan, within ten (10) days of receipt of a written request from the DEP Task Manager.
|
| Financial Consequences: If the CONTRACTOR does not successfully implement the Plan as approved by the DEP Task Manager for the remaining months of the Task Assignment, the DEP may withhold further payment of monthly invoices until such time as the CONTRACTOR comes into compliance with those performance levels as outlined in the Performance Metrics. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
ENVIRONMENTAL CLEANUP AND RESTORATION
|
Task 4: Reported discharge inspections, installation inspections, closure inspections, and re-inspe...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 4: Reported discharge inspections, installation inspections, closure inspections, and re-inspections for at least 90% of listed facilities. |
| Deliverable Price: $487,015.32 |
| Non Price Justification: |
| Performance Metrics: The CONTRACTOR should have completed the following required routine compliance inspections unless otherwise indicated in the Task Assignment;
1.After Four Months should have completed 33% of inspections.
2.After 8 months should have completed 66% of inspections.
3.After 12 months should have completed 100% of inspections
If number of required routine compliance inspections falls below twenty percent (20%) for the fourth month, thirty percent (30%) for the fifth month, forty percent (40%) for the sixth month, forty-eight percent (48%) for the seventh month, fifty-seven percent (57%) for the eighth month, sixty-five percent (65%) for the ninth month, seventy-three percent (73%) for the tenth month or eighty-two percent for (82%) the eleventh month, then the CONTRACTOR shall submit a Corrective Action Plan, within ten (10) days of receipt of a written request from the DEP Task Manager.
|
| Financial Consequences: If the CONTRACTOR does not successfully implement the Plan as approved by the DEP Task Manager for the remaining months of the Task Assignment, the DEP may withhold further payment of monthly invoices until such time as the CONTRACTOR comes into compliance with those performance levels as outlined in the Performance Metrics. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
ENVIRONMENTAL CLEANUP AND RESTORATION
|
Task 5: Reported discharge inspections, installation inspections, closure inspections, and re-insp...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 5: Reported discharge inspections, installation inspections, closure inspections, and re-inspections for at least 60% of listed facilities. |
| Deliverable Price: $360,393.60 |
| Non Price Justification: |
| Performance Metrics: The CONTRACTOR should have completed the following required routine compliance inspections unless otherwise indicated in the Task Assignment;
1.After Four Months should have completed 33% of inspections.
2.After 8 months should have completed 66% of inspections.
3.After 12 months should have completed 100% of inspections
If number of required routine compliance inspections falls below twenty percent (20%) for the fourth month, thirty percent (30%) for the fifth month, forty percent (40%) for the sixth month, forty-eight percent (48%) for the seventh month, fifty-seven percent (57%) for the eighth month, sixty-five percent (65%) for the ninth month, seventy-three percent (73%) for the tenth month or eighty-two percent for (82%) the eleventh month, then the CONTRACTOR shall submit a Corrective Action Plan, within ten (10) days of receipt of a written request from the DEP Task Manager.
|
| Financial Consequences: If the CONTRACTOR does not successfully implement the Plan as approved by the DEP Task Manager for the remaining months of the Task Assignment, the DEP may withhold further payment of monthly invoices until such time as the CONTRACTOR comes into compliance with those performance levels as outlined in the Performance Metrics. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
ENVIRONMENTAL CLEANUP AND RESTORATION
|
Perform compliance inspections on storage tank systems in Duval county. Deliverables will be establ...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Perform compliance inspections on storage tank systems in Duval county. Deliverables will be established on a Task Assignment basis. |
| Deliverable Price: $0.00 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: The CONTRACTOR should have completed the following required routine compliance inspections unless otherwise indicated in the Task Assignment;
1.After Four Months should have completed 33% of inspections.
2.After 8 months should have completed 66% of inspections.
3.After 12 months should have completed 100% of inspections
If number of required routine compliance inspections falls below twenty percent (20%) for the fourth month, thirty percent (30%) for the fifth month, forty percent (40%) for the sixth month, forty-eight percent (48%) for the seventh month, fifty-seven percent (57%) for the eighth month, sixty-five percent (65%) for the ninth month, seventy-three percent (73%) for the tenth month or eighty-two percent for (82%) the eleventh month, then the CONTRACTOR shall submit a Corrective Action Plan, within ten (10) days of receipt of a written request from the DEP Task Manager.
|
| Financial Consequences: If the CONTRACTOR does not successfully implement the Plan as approved by the DEP Task Manager for the remaining months of the Task Assignment, the DEP may withhold further payment of monthly invoices until such time as the CONTRACTOR comes into compliance with those performance levels as outlined in the Performance Metrics. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
ENVIRONMENTAL CLEANUP AND RESTORATION
|
Task 8: Routine $357.45, UST System Install $1,157.79, UST Piping Install $385.93, Component Install...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 8: Routine $357.45, UST System Install $1,157.79, UST Piping Install $385.93, Component Install $192.96, UST System Closure $771.85, UST Piping Closure $385.93, Component Closure $192.96, AST System Install $578.89, AST Piping Install $192.96, AST Piping Closure $192.96, AST System Closure $385.93., Compliant $190.11,Discharge $190.11 Enforcement $190.11, Non-Compliance $190.11. |
| Deliverable Price: $252,190.73 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance to the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
1. Contractor should have completed 33% of inspections within 4 months (by October 2013).
2.Contractor should have completed 66% of inspections within 8 months (by February 2014).
3.Contractor must have completed 100% of inspections by June 2014.
However, if number of routine compliance inspections falls below twenty percent (20%) for the fourth month, thirty percent (30%) for the fifth month, forty percent (40%) for the sixth month, forty-eight percent (48%) for the seventh month, fifty-seven percent (57%) for the eighth month, sixty-five percent (65%) for the ninth month, seventy-three percent (73%) for the tenth month or eighty-two percent for (82%) the eleventh month, then the Contractor shall submit a Corrective Action Plan, within ten (10) days of receipt of a written request from the DEP Task Manager. |
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
ENVIRONMENTAL CLEANUP AND RESTORATION
|
Task 6: Reported discharge inspections, installation inspections, closure inspections, and re-inspec...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task 6: Reported discharge inspections, installation inspections, closure inspections, and re-inspections for 554 of the 1,030 facilities. Fees: Routine $352.17, UST System Install $1,140.68, UST Piping Install $380.23; Component Install $190.11, UST System Closure $760.45; UST Piping Closure $380.23, Component Closure $190.11, AST System Install $570.34, AST Piping Install $190.11, AST Piping Closure $190.11, AST System Closure $380.23, Compliant $190.11, Discharge $190.11, Enforcement $190.11, Non Compliance $190.11./CO1- increased tank closure inspections by 11 and Install Inspections by 11.n CO2- increased funding. |
| Deliverable Price: $265,596.03 |
| Non Price Justification: |
| Performance Metrics: The CONTRACTOR should have completed the following required routine compliance inspections unless otherwise indicated in the Task Assignment;
1.After Four Months should have completed 33% of inspections.
2.After 8 months should have completed 66% of inspections.
3.After 12 months should have completed 100% of inspections
If number of required routine compliance inspections falls below twenty percent (20%) for the fourth month, thirty percent (30%) for the fifth month, forty percent (40%) for the sixth month, forty-eight percent (48%) for the seventh month, fifty-seven percent (57%) for the eighth month, sixty-five percent (65%) for the ninth month, seventy-three percent (73%) for the tenth month or eighty-two percent for (82%) the eleventh month, then the CONTRACTOR shall submit a Corrective Action Plan, within ten (10) days of receipt of a written request from the DEP Task Manager.
|
| Financial Consequences: If the CONTRACTOR does not successfully implement the Plan as approved by the DEP Task Manager for the remaining months of the Task Assignment, the DEP may withhold further payment of monthly invoices until such time as the CONTRACTOR comes into compliance with those performance levels as outlined in the Performance Metrics. |
| Source Documentation Page Reference: Task Assignment 6 |
| Deliverable Number: |
|
|
|
|
Inspection
|
Task 11 : The Contractor shall Conduct Compliance Assistance Visits (CAVs) at approximately 250 faci...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 11 : The Contractor shall Conduct Compliance Assistance Visits (CAVs) at approximately 250 facilities identified in Exhibit # 1 (provided electronically). Compliance Assistance Visit (CAV) Inspector(s) should have experience with the Petroleum Storage Tank Program.
• The County shall invoice monthly at the rate of $190.11 per Compliance Assistance Visit.
CO1- reduce 100 CAV and funding $-19,011.00 |
| Deliverable Price: $28,516.50 |
| Non Price Justification: |
| Performance Metrics: The Compliance Assistance Visits must be conducted 21 to 30 days prior to a scheduled Routine Compliance Assurance Inspection tasked under a separate Task Assignment. The Facility must be contacted 5 days prior to and accept the offer for the Compliance Assistance Visit offer.
• The Compliance Assistance Visit Inspector must review the facility’s compliance history (last 2 inspections) with the Facility Owner or Representative and conduct an informal site walkthrough using the Compliance Assistance Checklist and Form Exhibit # 2. A copy of the Checklist and completed form must be provided to the Facility Owner or Representative at the conclusion of the visit. An electronic copy of the completed form must be uploaded into Oculus. These CAVs are outreach events, not Compliance Assurance Inspections, the inspector shall not cite discovered violations. |
| Financial Consequences: If the CONTRACTOR fails to perform in a timely and proper manner, in the judgment of the DEP, the DEP may terminate this Contract by thirty (30) days written notice, specifying the effective time/date of termination. In this event, the CONTRACTOR shall be compensated for any work satisfactorily completed. |
| Source Documentation Page Reference: T11 & CO1 |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 9: Reported discharge inspections, installation inspections, closure inspections, and re-inspe...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 9: Reported discharge inspections, installation inspections, closure inspections, and re-inspections for 584 facilities. Fees: Routine $357.45, UST System Install $1,157.79, UST Piping Install $385.93, Component Install $192.96, UST System Closure $771.85, UST Piping Closure $385.93, Component Closure $192.96, AST System Install $578.89, AST Piping Install $192.96, AST Piping Closure $192.96, AST System Closure $385.93., Compliant $190.11,Discharge $190.11 Enforcement $190.11, Non-Compliance $190.11. CO1 - increased funding. CO2 - Increase amount for Variable Inspections
|
| Deliverable Price: $287,750.80 |
| Non Price Justification: |
| Performance Metrics: The CONTRACTOR should have completed the following required routine compliance inspections unless otherwise indicated in the Task Assignment;
1.After Four Months should have completed 33% of inspections. Due October 2014.
2.After 8 months should have completed 66% of inspections. Due February 2015.
3.After 12 months should have completed 100% of inspections. Due June 2015.
If number of required routine compliance inspections falls below twenty percent (20%) for the fourth month, thirty percent (30%) for the fifth month, forty percent (40%) for the sixth month, forty-eight percent (48%) for the seventh month, fifty-seven percent (57%) for the eighth month, sixty-five percent (65%) for the ninth month, seventy-three percent (73%) for the tenth month or eighty-two percent for (82%) the eleventh month, then the CONTRACTOR shall submit a Corrective Action Plan, within ten (10) days of receipt of a written request from the DEP Task Manager. |
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract. |
| Source Documentation Page Reference: TA9CO2 |
| Deliverable Number: |
|
|
|
|
Inspection
|
Task 12 : This Task assignment provides funding to offset the acquisition of vehicle for expansion o...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 12 : This Task assignment provides funding to offset the acquisition of vehicle for expansion of compliance verification activities under this Contract and any subsequent renewal contract. The Contractor is solely responsible for the maintenance, operation and ownership of the vehicle. CO1- Voids previous task. |
| Deliverable Price: $15,000.00 |
| Non Price Justification: |
| Performance Metrics: "This Task assignment provides funding to offset the acquisition of vehicle for expansion of compliance verification activities under this Contract and any subsequent renewal contract. The Contractor must perform all Enforcement Actions in accordance with Guidance Document F (Level of Effort). The contractor is reminded of the Performance Levels stated in paragraph 7B of the contract: Following the effective date of Each Task Assignment, the CONTRACTOR shall complete the following percentage of the required routine compliance inspections unless otherwise indicated in the Task Assignment:(1) After four (4) months, thirty-three percent (33%) of inspections shall be completed.
(2) After eight (8) months, sixty-six (66%) of inspections shall be completed.
(3) After (12) months, one hundred percent (100%) of inspections shall be completed.
The Contractor will not conduct the Discharge Prevention Response Certificate (DPRC) inspections detailed in Paragraph 9 of the contract.
The FDEP will adjust the funding level of this task assignment as needed to complete the scope of services described within this Task Assignment.
"
|
| Financial Consequences: If the CONTRACTOR fails to perform in a timely and proper manner, in the judgment of the DEP, the DEP may terminate this Contract by thirty (30) days written notice, specifying the effective time/date of termination. In this event, the CONTRACTOR shall be compensated for any work satisfactorily completed.
|
| Source Documentation Page Reference: T12CO1 |
| Deliverable Number: |
|
|
|
|
Inspection
|
Task 10 : The Contractor shall complete the following services in accordance with the requirements i...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 10 : The Contractor shall complete the following services in accordance with the requirements in DEP Contract No. GC 679: - Conduct routine compliance inspections at the 449 facilities identified in Exhibit #1 (provided electronically). Perform inspections for all reported complaints, discharges, installations and closures involving storage tank systems within Duval Counties. Compensation will only occur for routine annual compliance inspections conducted at the facilities explicitly identified in Exhibit Fees: Routine - $464.00 UST System Install - $1,140.68 UST Piping install - $380.23 Component install - $190.11 UST System closure - $760.45 UST Piping closure - $380.23 Component closure - $190.11 AST System install - $570.34 AST Piping install - $190.11 AST Piping closure - $190.11 AST System closure- $380.23 Compliant - $190.11 Discharge - $190.11 Enforcement - $190.11 Non-compliance - $190.11. CO1- increase funding. |
| Deliverable Price: $274,086.72 |
| Non Price Justification: |
| Performance Metrics: "The Contractor must perform all Enforcement Actions in accordance with Guidance Document F (Level of Effort). The contractor is reminded of the Performance Levels stated in paragraph 7B of the contract: Following the effective date of Each Task Assignment, the CONTRACTOR shall complete the following percentage of the required routine compliance inspections unless otherwise indicated in the Task Assignment:(1) After four (4) months, thirty-three percent (33%) of inspections shall be completed.
(2) After eight (8) months, sixty-six (66%) of inspections shall be completed.
(3) After (12) months, one hundred percent (100%) of inspections shall be completed.
The Contractor will not conduct the Discharge Prevention Response Certificate (DPRC) inspections detailed in Paragraph 9 of the contract.
The FDEP will adjust the funding level of this task assignment as needed to complete the scope of services described within this Task Assignment.
"
|
| Financial Consequences: If the CONTRACTOR fails to perform in a timely and proper manner, in the judgment of the DEP, the DEP may terminate this Contract by thirty (30) days written notice, specifying the effective time/date of termination. In this event, the CONTRACTOR shall be compensated for any work satisfactorily completed.
|
| Source Documentation Page Reference: TA10CO1 |
| Deliverable Number: |
|
|
|
|
Inspection
|
Task 14 : This Task assignment provides funding to offset the acquisition of vehicle for expansion ...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 14 : This Task assignment provides funding to offset the acquisition of vehicle for expansion of compliance verification activities under this Contract and any subsequent renewal contract. The Contractor is solely responsible for the maintenance, operation and ownership of the vehicle.
|
| Deliverable Price: $15,000.00 |
| Non Price Justification: |
| Performance Metrics: The Contractor must perform all Enforcement Actions in accordance with Guidance Document F (Level of Effort). The contractor is reminded of the Performance Levels stated in paragraph 7B of the contract: Following the effective date of Each Task Assignment, the CONTRACTOR shall complete the following percentage of the required routine compliance inspections unless otherwise indicated in the Task Assignment:(1) After four (4) months, thirty-three percent (33%) of inspections shall be completed.
(2) After eight (8) months, sixty-six (66%) of inspections shall be completed.
(3) After (12) months, one hundred percent (100%) of inspections shall be completed.
The Contractor will not conduct the Discharge Prevention Response Certificate (DPRC) inspections detailed in Paragraph 9 of the contract.
The FDEP will adjust the funding level of this task assignment as needed to complete the scope of services described within this Task Assignment.
|
| Financial Consequences: If the CONTRACTOR fails to perform in a timely and proper manner, in the judgment of the DEP, the DEP may terminate this Contract by thirty (30) days written notice, specifying the effective time/date of termination. In this event, the CONTRACTOR shall be compensated for any work satisfactorily completed.
|
| Source Documentation Page Reference: Attachment B |
| Deliverable Number: |
|
|
|
|
Inspection
|
Task 15 : The Contractor is Authorized to acquire Reference Standard listed below for Rule 62-761 an...
|
Cost Reimbursement
|
| Major Deliverable: Task 15 : The Contractor is Authorized to acquire Reference Standard listed below for Rule 62-761 and 62-762 FAC. API STD653; API 1604; API 1615; API RP 1637; API RP2350; PEIIRP200-13; PEI/RP1200-12; PEI/RPI00-11; STI SPOO1; STISP031; NFPAJ; NFP30A.
|
| Deliverable Price: $1,451.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Contractor is Authorized to acquire Reference Standard for Rule 62-761 and 62-762 FAC as stated in Task Notification Form.
|
| Financial Consequences: If the CONTRACTOR fails to perform in a timely and proper manner, in the judgment of the DEP, the DEP may terminate this Contract by thirty (30) days written notice, specifying the effective time/date of termination. In this event, the CONTRACTOR shall be compensated for any work satisfactorily completed.
|
| Source Documentation Page Reference: Attachment B |
| Deliverable Number: |
|
|
|
1
|
Inspection
|
Task 13 : The Contractor shall complete the following services in accordance with the requirements i...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 13 : The Contractor shall complete the following services in accordance with the requirements in DEP Contract No. GC 679: - Conduct routine compliance inspections at the 604 facilities identified in Exhibit #1 (provided electronically). Perform inspections for all reported complaints, discharges, installations and closures involving storage tank systems within Duval Counties.
Compensation will only occur for routine annual compliance inspections conducted at the facilities explicitly identified in Exhibit Fees: Routine - $464.00 UST System Install - $1,140.68 UST Piping install - $380.23 Component install - $190.11 UST System closure - $760.45 UST Piping closure - $380.23 Component closure - $190.11 AST System install - $570.34 AST Piping install - $190.11 AST Piping closure - $190.11 AST System closure- $380.23 Compliant - $190.11 Discharge - $190.11 Enforcement - $190.11 Non-compliance - $190.11. CO1- Increase in funding for Variable Inspections. CO2: Reduction of 3 Routine Inspection Facilities from original assignment of 604 Routine Inspection Facilities for Task 13 ($1,392.00).
|
| Deliverable Price: $379,100.03 |
| Non Price Justification: |
| Performance Metrics: The Contractor must perform all Enforcement Actions in accordance with Guidance Document F (Level of Effort). The contractor is reminded of the Performance Levels stated in paragraph 7B of the contract: Following the effective date of Each Task Assignment, the CONTRACTOR shall complete the following percentage of the required routine compliance inspections unless otherwise indicated in the Task Assignment:(1) After four (4) months, thirty-three percent (33%) of inspections shall be completed.
(2) After eight (8) months, sixty-six (66%) of inspections shall be completed.
(3) After (12) months, one hundred percent (100%) of inspections shall be completed.
The Contractor will not conduct the Discharge Prevention Response Certificate (DPRC) inspections detailed in Paragraph 9 of the contract.
The FDEP will adjust the funding level of this task assignment as needed to complete the scope of services described within this Task Assignment.
|
| Financial Consequences: If the CONTRACTOR fails to perform in a timely and proper manner, in the judgment of the DEP, the DEP may terminate this Contract by thirty (30) days written notice, specifying the effective time/date of termination. In this event, the CONTRACTOR shall be compensated for any work satisfactorily completed.
|
| Source Documentation Page Reference: Attachment B |
| Deliverable Number: 1 |
|