"Task 3 : The Contractor shall complete the following services in accordance with the requirements i...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: "Task 3 : The Contractor shall complete the following services in accordance with the requirements in DEP Contract No. GC 911: - Conduct routine compliance inspections at the 643 facilities identified in Exhibit #1 (provided electronically). Perform inspections for all reported complaints, discharges, installations and closures involving storage tank systems within Dade County.
Compensation will only occur for routine annual compliance inspections conducted at the facilities explicitly identified in Exhibit #1 (provided electronically). Routine $515.50, UST System Install $1,425.85, UST System Closure $920.15, UST System Closure-Tank count greater than 10 $1,350, AST System Install $712.93, AST System Closure $418.25, Compliance Assistance-Component $209.12, Compliance Assistance- Re inspection $209.12, Complaint $209.12, Discharge $209.12 ."
Task not to exceed $390,154.50. CO1: Performance Measures for Invoice 4, reduced to from 33% to 23%.CO2: reductions of $38,662.50 & 75 Routine Compliance Inspections.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: The Contractor must perform all Enforcement Actions in accordance with Guidance Document F (Level of Effort). Following the effective date of Each Task Assignment, the CONTRACTOR shall complete the following percentage of the required routine compliance inspections unless otherwise indicated in the Task Assignment: (1) After four (4) months, thirty-three percent (33%) of inspections shall be completed. (2) After eight (8) months, sixty-six (66%) of inspections shall be completed. (3) After (12) months, one hundred percent (100%) of inspections shall be completed. FDEP will adjust the funding level of this task assignment as needed to complete the scope of services described within this Task Assignment.
|
| Financial Consequences: If the CONTRACTOR fails to perform in a timely and proper manner, in the judgment of the DEP, the DEP may terminate this Contract by thirty (30) days written notice, specifying the effective time/date of termination. In this event, the CONTRACTOR shall be compensated for any work satisfactorily completed.
|
| Source Documentation Page Reference: Attachment C |
| Deliverable Number: |
|
|
|
|
Inspection
|
Task 1 : The Contractor shall complete the following services in accordance with the requirements in...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1 : The Contractor shall complete the following services in accordance with the requirements in DEP Contract No. GC 911: - Conduct routine compliance inspections at the 643 facilities identified in Exhibit #1 (provided electronically). Perform inspections for all reported complaints, discharges, installations and closures involving storage tank systems within Dade County.
Compensation will only occur for routine annual compliance inspections conducted at the facilities. Routine $515.50, UST System Install $1,140.68, UST Piping Install $380.23, Component Install $190.11, UST System Closure $836.50, UST Piping Closure $418.25, Component Closure $209.12, AST System Install $570.34, AST Piping Install $190.11, AST Piping Closure $190.11, AST System Closure $380.23, Compliant $190.11,Discharge $190.11 Enforcement $190.11, Non-Compliance $190.11, Compliance Assistance Re-inspect $190.11.The Department reserves the right to retain 10% on the Compliance Routine Inspection (CRI) as specified in paragraph 21 reimbursement criteria for the amount retained. CO1 - Increase in funds ($4,164.72). CO2 - Due to the recent Hurricanes, after four (4) months, the first performance measures for GC911-1 Dade County shall be to complete twenty six percent (26%) of Routine Compliance Inspections.
|
| Deliverable Price: $420,962.46 |
| Non Price Justification: |
| Performance Metrics: The Contractor must perform all Enforcement Actions in accordance with Guidance Document F (Level of Effort). Following the effective date of Each Task Assignment, the CONTRACTOR shall complete the following percentage of the required routine compliance inspections unless otherwise indicated in the Task Assignment:(1) After four (4) months, thirty-three percent (33%) of inspections shall be completed.(2) After eight (8) months, sixty-six (66%) of inspections shall be completed.(3) After (12) months, one hundred percent (100%) of inspections shall be completed.
FDEP will adjust the funding level of this task assignment as needed to complete the scope of services described within this Task Assignment.
|
| Financial Consequences: If the CONTRACTOR fails to perform in a timely and proper manner, in the judgment of the DEP, the DEP may terminate this Contract by thirty (30) days written notice, specifying the effective time/date of termination. In this event, the CONTRACTOR shall be compensated for any work satisfactorily completed.
|
| Source Documentation Page Reference: Attachment B |
| Deliverable Number: |
|
|
|
|
Inspection
|
Task 2 : Conduct routine compliance inspections at the 643 facilities identified in Exhibit #1 (prov...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 2 : Conduct routine compliance inspections at the 643 facilities identified in Exhibit #1 (provided electronically). Perform inspections for all reported complaints, discharges, installations and closures involving storage tank systems within Dade County.
Compensation will only occur for routine annual compliance inspections conducted at the facilities explicitly identified in Exhibit #1 (provided electronically). Routine $545.00, UST System Install $1,425.85, UST System Closure $920.15, AST System Install $712.93, AST System Closure $418.25, Compliance Assistance-Component $209.12, Compliance Assistance- Re inspection $209.12, Complaint $209.12, Discharge $209.12; Inspection staff to attend annual meeting Spring. 2019. Variable Inspections $39,650.00 Task Total = $448, 285.00
CO1: Updated scope of work
CO2: Revision to language regarding annual meeting.
CO3: Funding Increase for variable inspections.
CO4: Funding Increase for variable inspections. |
| Deliverable Price: $448,285.00 |
| Non Price Justification: |
| Performance Metrics: The Contractor must perform all Enforcement Actions in accordance with Guidance Document F (Level of Effort). Following the effective date of Each Task Assignment, the CONTRACTOR shall complete the following percentage of the required routine compliance inspections unless otherwise indicated in the Task Assignment:(1) After four (4) months, thirty-three percent (33%) of inspections shall be completed.(2) After eight (8) months, sixty-six (66%) of inspections shall be completed.(3) After (12) months, one hundred percent (100%) of inspections shall be completed.
FDEP will adjust the funding level of this task assignment as needed to complete the scope of services described within this Task Assignment.
|
| Financial Consequences: If the CONTRACTOR fails to perform in a timely and proper manner, in the judgment of the DEP, the DEP may terminate this Contract by thirty (30) days written notice, specifying the effective time/date of termination. In this event, the CONTRACTOR shall be compensated for any work satisfactorily completed.
|
| Source Documentation Page Reference: CO4 |
| Deliverable Number: |
|
|
|
|
Inspection
|
Task 4: Routine Inspections at the facilities identified in Exhibit #1. Routine Inspection $515.50; ...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 4: Routine Inspections at the facilities identified in Exhibit #1. Routine Inspection $515.50; UST System Install $1,425.85; UST System Install - tank count greater than 10 - $2,100; UST System Closure $920.15; UST System Closure - tank count greater than 10 - $1350; AST System Install $712.93; AST System Closure $418.25; Compliance Assistance - Component $209.12; Compliance Assistance - Reinspection $209.12; Complaint $209.12; Discharge $209.12.Total task not to exceed $406,650.00.
A1: Allows Cost Reimbursement for travel. |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Contractor must perform all Enforcement Actions in accordance with Guidance Document F (Level of Effort). Following the effective date of Each Task Assignment, the CONTRACTOR shall complete the following percentage of the required routine compliance inspections unless otherwise indicated in the Task Assignment: (1) After four (4) months, thirty-three percent (33%) of inspections shall be completed. (2) After eight (8) months, sixty-six (66%) of inspections shall be completed. (3) After (12) months, one hundred percent (100%) of inspections shall be completed. FDEP will adjust the funding level of this task assignment as needed to complete the scope of services described within this Task Assignment.
|
| Financial Consequences: If the CONTRACTOR fails to perform in a timely and proper manner, in the judgment of the DEP, the DEP may terminate this Contract by thirty (30) days written notice, specifying the effective time/date of termination. In this event, the CONTRACTOR shall be compensated for any work satisfactorily completed.
|
| Source Documentation Page Reference: A1 |
| Deliverable Number: |
|
|
|
|
Inspection
|
Task 5: Routine Inspection $515.50; UST System Install $1,425.85; UST System Install - tank count gr...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 5: Routine Inspection $515.50; UST System Install $1,425.85; UST System Install - tank count greater than 10 - $2,100; UST System Closure $920.15; UST System Closure - tank count greater than 10 - $1350; AST System Install $712.93; AST System Closure $418.25; Compliance Assistance - Component $209.12; Compliance Assistance - Reinspection $209.12; Complaint $209.12; Discharge $209.12, Ethanol Inspection $209.12. CO1: Increase in funds for Variable Inspections for $21,000. A net increase of $21,000. Total Task not to exceed $396,825. |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Contractor must perform all Enforcement Actions in accordance with Guidance Document F (Level of Effort). Following the effective date of Each Task Assignment, the CONTRACTOR shall complete the following percentage of the required routine compliance inspections unless otherwise indicated in the Task Assignment: (1) After four (4) months, thirty-three percent (33%) of inspections shall be completed. (2) After eight (8) months, sixty-six (66%) of inspections shall be completed. (3) After (12) months, one hundred percent (100%) of inspections shall be completed. FDEP will adjust the funding level of this task assignment as needed to complete the scope of services described within this Task Assignment. |
| Financial Consequences: If the CONTRACTOR fails to perform in a timely and proper manner, in the judgment of the DEP, the DEP may terminate this Contract by thirty (30) days written notice, specifying the effective time/date of termination. In this event, the CONTRACTOR shall be compensated for any work satisfactorily completed. |
| Source Documentation Page Reference: CO1 |
| Deliverable Number: |
|
|
|
|
Inspection
|
Task 7: Submit Contractual Services Invoice with verified Payment Calculation Sheet, along with FIRS...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 7: Submit Contractual Services Invoice with verified Payment Calculation Sheet, along with FIRST Report (Compliance and Activity by Date Range) and Tracking Form (Monthly percentage of Routine Inspections Completed) Compensation will only occur for routine annual compliance inspections conducted at the facilities explicitly identified Exhibit 1 and variable inspections identified in supporting documentation. Submit travel reimbursement forms, supporting receipts, and agenda for 2023-2024 training. Routine Inspection $785.00; UST System Install $1,425.85; UST System Install - tank count greater than 10 - $2,100; UST System Closure $920.15; UST System Closure - tank count greater than 10 - $1350; AST System Install $712.93; AST System Closure $418.25; Compliance Assistance - Component $209.12; Compliance Assistance - Reinspection $209.12; Complaint $209.12; Discharge $209.12, Ethanol Inspection $209.12. Total Task not to exceed $.460,918.10.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Contractor must perform all Enforcement Actions in accordance with Guidance Document F (Level of Effort). Following the effective date of Each Task Assignment, the CONTRACTOR shall complete the following percentage of the required routine compliance inspections unless otherwise indicated in the Task Assignment: (1) After four (4) months, thirty-three percent (33%) of inspections shall be completed. (2) After eight (8) months, sixty-six (66%) of inspections shall be completed. (3) After (12) months, one hundred percent (100%) of inspections shall be completed. FDEP will adjust the funding level of this task assignment as needed to complete the scope of services described within this Task Assignment.
|
| Financial Consequences: If the CONTRACTOR fails to perform in a timely and proper manner, in the judgment of the DEP, the DEP may terminate this Contract by thirty (30) days written notice, specifying the effective time/date of termination. In this event, the CONTRACTOR shall be compensated for any work satisfactorily completed.
|
| Source Documentation Page Reference: T7 |
| Deliverable Number: |
|
|
|
|
Inspection
|
Task 6:Routine Inspection $545.00; UST System Install $1,425.85; UST System Install - tank count gre...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 6:Routine Inspection $545.00; UST System Install $1,425.85; UST System Install - tank count greater than 10 - $2,100; UST System Closure $920.15; UST System Closure - tank count greater than 10 - $1350; AST System Install $712.93; AST System Closure $418.25; Compliance Assistance - Component $209.12; Compliance Assistance - Reinspection $209.12; Complaint $209.12; Discharge $209.12, Ethanol Inspection $209.12. Total task not to exceed $.393,525.00. TACO 1 - Increase in funds for Variable Inspectuions for $10,000. Total task not to exceed $403,325.
CO1: increase |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Contractor must perform all Enforcement Actions in accordance with Guidance Document F (Level of Effort). Following the effective date of Each Task Assignment, the CONTRACTOR shall complete the following percentage of the required routine compliance inspections unless otherwise indicated in the Task Assignment: (1) After four (4) months, thirty-three percent (33%) of inspections shall be completed. (2) After eight (8) months, sixty-six (66%) of inspections shall be completed. (3) After (12) months, one hundred percent (100%) of inspections shall be completed. FDEP will adjust the funding level of this task assignment as needed to complete the scope of services described within this Task Assignment.
|
| Financial Consequences: If the CONTRACTOR fails to perform in a timely and proper manner, in the judgment of the DEP, the DEP may terminate this Contract by thirty (30) days written notice, specifying the effective time/date of termination. In this event, the CONTRACTOR shall be compensated for any work satisfactorily completed.
|
| Source Documentation Page Reference: Attachment C |
| Deliverable Number: |
|
|
|
|
Inspection
|
Task 8:
Routine I...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 8:
Routine Inspection $800.00; UST System Install $1,425.85; UST System Install - tank count greater than 10 - $2,100; UST System Closure $920.15; UST System Closure - tank count greater than 10 - $1350; AST System Install $712.93; AST System Closure $418.25; Compliance Assistance - Component $209.12; Compliance Assistance - Reinspection $209.12; Complaint $209.12; Discharge $209.12, Ethanol Inspection $209.12. Total Task not to exceed $.592,783.10.
Total Task amount should not exceed $627,783.10.
CO1: Increase in funds for Variable Inspections for $35,000.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Contractor must perform all Enforcement Actions in accordance with Guidance Document F (Level of Effort). Following the effective date of Each Task Assignment, the CONTRACTOR shall complete the following percentage of the required routine compliance inspections unless otherwise indicated in the Task Assignment: (1) After four (4) months, thirty-three percent (33%) of inspections shall be completed. (2) After eight (8) months, sixty-six (66%) of inspections shall be completed. (3) After (12) months, one hundred percent (100%) of inspections shall be completed. FDEP will adjust the funding level of this task assignment as needed to complete the scope of services described within this Task Assignment.
|
| Financial Consequences: If the CONTRACTOR fails to perform in a timely and proper manner, in the judgment of the DEP, the DEP may terminate this Contract by thirty (30) days written notice, specifying the effective time/date of termination. In this event, the CONTRACTOR shall be compensated for any work satisfactorily completed.
|
| Source Documentation Page Reference: T8 CO1 |
| Deliverable Number: |
|
|
|
|
Inspection
|
Task 9: Routine Inspection $800.00; UST System Install $1,425.85; UST System Install - tank count gr...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 9: Routine Inspection $800.00; UST System Install $1,425.85; UST System Install - tank count greater than 10 - $2,100; UST System Closure $920.15; UST System Closure - tank count greater than 10 - $1350; AST System Install $712.93; AST System Closure $418.25; Compliance Assistance - Component $209.12; Compliance Assistance - Reinspection $209.12; Complaint $209.12; Discharge $209.12, Ethanol Inspection $209.12. Total Task not to exceed $.612,790.38.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Contractor must perform all Enforcement Actions in accordance with Guidance Document F (Level of Effort). Following the effective date of Each Task Assignment, the CONTRACTOR shall complete the following percentage of the required routine compliance inspections unless otherwise indicated in the Task Assignment: (1) After four (4) months, thirty-three percent (33%) of inspections shall be completed. (2) After eight (8) months, sixty-six (66%) of inspections shall be completed. (3) After (12) months, one hundred percent (100%) of inspections shall be completed. FDEP will adjust the funding level of this task assignment as needed to complete the scope of services described within this Task Assignment.
|
| Financial Consequences: f the CONTRACTOR fails to perform in a timely and proper manner, in the judgment of the DEP, the DEP may terminate this Contract by thirty (30) days written notice, specifying the effective time/date of termination. In this event, the CONTRACTOR shall be compensated for any work satisfactorily completed.
|
| Source Documentation Page Reference: T9 |
| Deliverable Number: |
|
|
|
|
Inspection
|
Task 10: Routine Inspection $800.00; UST System Install $1,425.85; UST System Install - tank count g...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 10: Routine Inspection $800.00; UST System Install $1,425.85; UST System Install - tank count greater than 10 - $2,100; UST System Closure $920.15; UST System Closure - tank count greater than 10 - $1350; AST System Install $712.93; AST System Closure $418.25; Compliance Assistance - Component $209.12; Compliance Assistance - Reinspection $209.12; Complaint $209.12; Discharge $209.12, Ethanol Inspection $209.12. Attend 2026-2027 training meeting. Submit travel reimbursement form, supporting receipts and agenda for 2026-2027 training. Total Task not to exceed $.612,163.38.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Contractor must perform all Enforcement Actions in accordance with Guidance Document F (Level of Effort). Following the effective date of Each Task Assignment, the CONTRACTOR shall complete the following percentage of the required routine compliance inspections unless otherwise indicated in the Task Assignment: (1) After four (4) months, thirty-three percent (33%) of inspections shall be completed. (2) After eight (8) months, sixty-six (66%) of inspections shall be completed. (3) After (12) months, one hundred percent (100%) of inspections shall be completed. FDEP will adjust the funding level of this task assignment as needed to complete the scope of services described within this Task Assignment.
|
| Financial Consequences: If the CONTRACTOR fails to perform in a timely and proper manner, in the judgment of the DEP, the DEP may terminate this Contract by thirty (30) days written notice, specifying the effective time/date of termination. In this event, the CONTRACTOR shall be compensated for any work satisfactorily completed.
|
| Source Documentation Page Reference: T10 |