Amendment
|
$0.00
|
DC44FCO1
|
Decrease in cost, increase in time
|
09/18/2026
|
09/18/2026
|
|
|
Amendment
|
$0.00
|
DC07DCO1
|
Decrease in cost
|
09/17/2026
|
09/17/2026
|
|
|
Amendment
|
$0.00
|
DC16DCO1
|
Decrease in cost
|
09/15/2026
|
09/15/2026
|
|
|
Amendment
|
$0.00
|
DC044G
|
interim source removal
|
09/01/2026
|
09/01/2026
|
|
|
Amendment
|
$0.00
|
DC33DCO2
|
Decrease in cost
|
08/28/2026
|
08/28/2026
|
|
|
Amendment
|
$0.00
|
PA391CO2
|
"Coral Springs (ERIC_7415) Cost Increase 9/30/2026"
|
08/21/2026
|
08/21/2026
|
|
|
Amendment
|
$0.00
|
PA510CO2
|
City of Hialeah (ERIC_7419) Cost Decrease 09/25/2026
|
08/07/2026
|
08/07/2026
|
|
|
Amendment
|
$0.00
|
DC22DCO1
|
Increase in cost, increase in time
|
08/06/2026
|
08/06/2026
|
|
|
Amendment
|
$0.00
|
DC02ECO2
|
Decrease in cost
|
08/04/2026
|
08/04/2026
|
|
|
Amendment
|
$0.00
|
DC08ECO1
|
Decrease in cost
|
08/03/2026
|
08/03/2026
|
|
|
Amendment
|
$0.00
|
DC11ECO2
|
Decrease in cost
|
07/31/2026
|
07/31/2026
|
|
|
Amendment
|
$0.00
|
DC11DCO3
|
Decrease in cost
|
07/28/2026
|
07/28/2026
|
|
|
Amendment
|
$0.00
|
DC11ECO1
|
Decrease in cost
|
07/20/2026
|
07/20/2026
|
|
|
Amendment
|
$0.00
|
DC19CCO1
|
Decrease in cost
|
07/20/2026
|
07/20/2026
|
|
|
Amendment
|
$0.00
|
DC045A
|
Site Recon and MAGS
|
06/29/2026
|
06/29/2026
|
|
|
Amendment
|
$0.00
|
HW013B
|
Annual Groundwater Monitoring
|
06/25/2026
|
06/25/2026
|
|
|
Amendment
|
$0.00
|
DC020D
|
Annual Groundwater Monitoring
|
06/24/2026
|
06/24/2026
|
|
|
Amendment
|
$0.00
|
DC016D
|
SVE Decommissioning
|
06/24/2026
|
06/24/2026
|
|
|
Amendment
|
$0.00
|
HW010D
|
Annual Groundwater Monitoring
|
06/24/2026
|
06/24/2026
|
|
|
Amendment
|
$0.00
|
DC034D
|
Annual Groundwater Monitoring
|
06/24/2026
|
06/24/2026
|
|
|
Amendment
|
$0.00
|
PA510CO1
|
City of Hialeah (ERIC_7419) Cost Increase 09/25/2026
|
06/23/2026
|
06/23/2026
|
|
|
Amendment
|
$0.00
|
DC030D
|
Annual Groundwater Monitoring
|
06/22/2026
|
06/22/2026
|
|
|
Amendment
|
$0.00
|
DC044F
|
Professional Land Survey and Groundwater Sampling
|
06/22/2026
|
06/22/2026
|
|
|
Amendment
|
$125,000.00
|
FIL21
|
Funding Increase
|
06/08/2026
|
06/08/2026
|
|
|
Amendment
|
$0.00
|
DC37CCO1
|
Decrease in cost
|
05/27/2026
|
05/27/2026
|
|
|
Amendment
|
$0.00
|
DC17DCO1
|
Increase in cost, increase in time
|
05/18/2026
|
05/18/2026
|
|
|
Amendment
|
$0.00
|
DC007D
|
monitoring well abandonment
|
05/18/2026
|
05/18/2026
|
|
|
Amendment
|
$0.00
|
DC038C
|
Groundwater, Soil, and Septic sampling
|
05/14/2026
|
05/14/2026
|
|
|
Amendment
|
$0.00
|
DC33DCO1
|
Increase in cost
|
05/14/2026
|
05/14/2026
|
|
|
Amendment
|
$0.00
|
DC03ECO2
|
Decrease in cost
|
05/08/2026
|
05/08/2026
|
|
|
Amendment
|
$0.00
|
DC029D
|
Annual groundwater monitorin
|
04/29/2026
|
04/29/2026
|
|
|
Amendment
|
$0.00
|
DC13DCO1
|
Decrease in cost
|
04/29/2026
|
04/29/2026
|
|
|
Amendment
|
$0.00
|
DC025D
|
Annual Groundwater Monitoring
|
04/22/2026
|
04/22/2026
|
|
|
Amendment
|
$0.00
|
DC022D
|
SVE Decommissioning and Well Abandonment
|
04/21/2026
|
04/21/2026
|
|
|
Amendment
|
$0.00
|
DC018D
|
Annual Groundwater Monitoring
|
04/21/2026
|
04/21/2026
|
|
|
Amendment
|
$0.00
|
DC010C
|
Interim Source Removal Plan (ISRP)
|
04/16/2026
|
04/16/2026
|
|
|
Amendment
|
$0.00
|
DC15CCO1
|
Decrease in cost, increase in time
|
04/15/2026
|
04/15/2026
|
|
|
Amendment
|
$0.00
|
DC003F
|
rebound evaluation
|
04/14/2026
|
04/14/2026
|
|
|
Amendment
|
$0.00
|
DC033D
|
Annual Groundwater Monitoring
|
04/09/2026
|
04/09/2026
|
|
|
Amendment
|
$200,000.00
|
FIL20
|
Funding Increment Increase
|
04/07/2026
|
04/07/2026
|
|
|
Amendment
|
$0.00
|
DC044E
|
ISRP
|
04/02/2026
|
04/02/2026
|
|
|
Amendment
|
$0.00
|
DC005E
|
ISRP preparation information gathering
|
03/31/2026
|
03/31/2026
|
|
|
Amendment
|
$0.00
|
DC09DC02
|
Increase in cost
|
03/27/2026
|
03/27/2026
|
|
|
Amendment
|
$0.00
|
PA510
|
City of Hialeah (ERIC_7419) 09/25/2026
|
03/24/2026
|
03/24/2026
|
|
|
Amendment
|
$0.00
|
PA391CO1
|
Coral Springs (ERIC_7415) Cost Increase 8/31/2026
|
03/20/2026
|
03/20/2026
|
|
|
Amendment
|
$0.00
|
DC008E
|
Verification soil sampling
|
03/12/2026
|
03/12/2026
|
|
|
Amendment
|
$0.00
|
DC002F
|
Roof inspection
|
03/03/2026
|
03/03/2026
|
|
|
Amendment
|
$0.00
|
DC019C
|
Soil and groundwater sampling
|
02/25/2026
|
02/25/2026
|
|
|
Amendment
|
$0.00
|
PA362CO5
|
City of Hialeah ERIC_7419 Cost increase 6/30/2026
|
02/12/2026
|
02/12/2026
|
|
|
Amendment
|
$0.00
|
DC41CCO1
|
Decrease in cost
|
02/10/2026
|
02/10/2026
|
|
|
Amendment
|
$0.00
|
DC09DC01
|
Increase in time
|
02/09/2026
|
02/09/2026
|
|
|
Amendment
|
$0.00
|
HW02DC02
|
Decrease in cost
|
02/09/2026
|
02/09/2026
|
|
|
Amendment
|
$0.00
|
DC037C
|
Supplemental Site Assessment
|
02/04/2026
|
02/04/2026
|
|
|
Amendment
|
$0.00
|
DC13BCO6
|
Entered in Error
|
02/02/2026
|
02/02/2026
|
|
|
Amendment
|
$0.00
|
DC011E
|
SVE System Decommissioning
|
01/27/2026
|
01/27/2026
|
|
|
Amendment
|
$0.00
|
DC014C
|
SVE construction
|
01/21/2026
|
01/21/2026
|
|
|
Amendment
|
$0.00
|
DC013D
|
Verification Soil Sampling
|
01/14/2026
|
01/14/2026
|
|
|
Amendment
|
$0.00
|
HW02DCO1
|
Decrease in cost
|
01/13/2026
|
01/13/2026
|
|
|
Amendment
|
$0.00
|
DC07CCO1
|
Decrease in cost
|
01/12/2026
|
01/12/2026
|
|
|
Amendment
|
$0.00
|
DC11DCO2
|
Increase in cost
|
01/09/2026
|
01/09/2026
|
|
|
Amendment
|
$0.00
|
DC032D
|
Groundwater Monitoring
|
01/05/2026
|
01/05/2026
|
|
|
Amendment
|
$0.00
|
PA362CO4
|
City of Hialeah ERIC_7419 Cost decrease 6/30/2026
|
12/31/2025
|
12/31/2025
|
|
|
Amendment
|
$0.00
|
DC24BCO1
|
Decrease in cost, increase in time
|
12/23/2025
|
12/23/2025
|
|
|
Amendment
|
$0.00
|
DC42CCO1
|
Decrease in cost
|
12/10/2025
|
12/10/2025
|
|
|
Amendment
|
$0.00
|
DC02ECO1
|
Decrease in cost
|
12/10/2025
|
12/10/2025
|
|
|
Amendment
|
$0.00
|
HW03DCO2
|
Increase in cost, increase in time
|
12/03/2025
|
12/03/2025
|
|
|
Amendment
|
$0.00
|
DC044D
|
Soil Sampling
|
12/03/2025
|
12/03/2025
|
|
|
Amendment
|
$0.00
|
DC012D
|
MAGS Re-Testing
|
11/21/2025
|
11/21/2025
|
|
|
Amendment
|
$0.00
|
DC017D
|
Groundwater Monitoring
|
11/12/2025
|
11/12/2025
|
|
|
Amendment
|
$0.00
|
DC041C
|
Site Assessment
|
11/04/2025
|
11/04/2025
|
|
|
Amendment
|
$0.00
|
HW002D
|
Annual Groundwater Monitoring
|
10/17/2025
|
10/17/2025
|
|
|
Amendment
|
$250,000.00
|
FIL19
|
Funding Increment Increase
|
10/02/2025
|
10/02/2025
|
|
|
Amendment
|
$0.00
|
DC002E
|
Conduct PARM
|
09/25/2025
|
09/25/2025
|
|
|
Amendment
|
$0.00
|
DC031C
|
Interim Source Removal Plan (ISRP)
|
09/25/2025
|
09/25/2025
|
|
|
Amendment
|
$0.00
|
DC26CCO3
|
Cost decrease
|
09/25/2025
|
09/25/2025
|
|
|
Amendment
|
$0.00
|
PA362CO3
|
Cost adjustment for change in scope of work 6/30/2026
|
09/25/2025
|
09/25/2025
|
|
|
Amendment
|
$0.00
|
DC024B
|
Groundwater Sampling
|
09/24/2025
|
09/24/2025
|
|
|
Amendment
|
$0.00
|
DC009D
|
VEW Abandonment and Site Restoration
|
09/18/2025
|
09/18/2025
|
|
|
Amendment
|
$0.00
|
DC007C
|
Site Recon and Groundwater Monitoring
|
09/10/2025
|
09/10/2025
|
|
|
Amendment
|
$0.00
|
DC34CCO1
|
Reconcile Work Change Directive 1
|
09/08/2025
|
09/08/2025
|
|
|
Amendment
|
$0.00
|
DC32CCO1
|
Cost Decrease
|
08/21/2025
|
08/21/2025
|
|
|
Amendment
|
$0.00
|
HW13ACO2
|
Cost decrease.
|
08/13/2025
|
08/13/2025
|
|
|
Amendment
|
$0.00
|
PA391
|
Site Assessment. 8/31/2026
|
08/13/2025
|
08/13/2025
|
|
|
Amendment
|
$0.00
|
DC30CCO2
|
Cost Decrease
|
08/07/2025
|
08/07/2025
|
|
|
Amendment
|
$0.00
|
DC08DCO2
|
Cost Decrease
|
08/01/2025
|
08/01/2025
|
|
|
Amendment
|
$0.00
|
HW03DCO1
|
Correct labor hour errors on original scope
|
07/29/2025
|
07/29/2025
|
|
|
Amendment
|
$0.00
|
DC26CCO2
|
Change in cost.
|
07/24/2025
|
07/24/2025
|
|
|
Amendment
|
$0.00
|
DC11DCO1
|
Cost increase and time extension
|
07/18/2025
|
07/18/2025
|
09/25/2026
|
|
Amendment
|
$0.00
|
PA362CO2
|
Additional labor cost 6/30/2026
|
07/18/2025
|
07/18/2025
|
|
|
Amendment
|
$0.00
|
DC20CCO1
|
Cost decrease
|
07/15/2025
|
07/15/2025
|
|
|
Amendment
|
$0.00
|
DC13CCO2
|
Removal of labor and equipment costs. Cost decrease
|
07/15/2025
|
07/15/2025
|
|
|
Amendment
|
$0.00
|
DC22CCO1
|
Cost Reduction
|
07/11/2025
|
07/11/2025
|
|
|
Amendment
|
$0.00
|
DC034C
|
Annual Groundwater Monitoring
|
07/09/2025
|
07/09/2025
|
|
|
Amendment
|
$0.00
|
HW13ACO1
|
Reconcile WCD 1
|
07/02/2025
|
07/02/2025
|
|
|
Amendment
|
$0.00
|
DC044C
|
MAGS Re-Testing
|
06/29/2025
|
06/29/2025
|
|
|
Amendment
|
$0.00
|
HW10CCO4
|
Cost Reduction
|
06/27/2025
|
06/27/2025
|
|
|
Amendment
|
$0.00
|
DC042C
|
MAGS Re-Testing
|
06/26/2025
|
06/26/2025
|
|
|
Amendment
|
$0.00
|
DC028C
|
MAGS Re-Testing
|
06/25/2025
|
06/25/2025
|
|
|
Amendment
|
$0.00
|
HW003D
|
Groundwater Monitoring
|
06/19/2025
|
06/19/2025
|
|
|
Amendment
|
$0.00
|
DC30CC01
|
Cost Increase
|
06/11/2025
|
06/11/2025
|
|
|
Amendment
|
$0.00
|
DC25CCO1
|
Cost Decrease
|
06/11/2025
|
06/11/2025
|
|
|
Amendment
|
$0.00
|
DC01ACO5
|
Cost Increase
|
06/05/2025
|
06/05/2025
|
|
|
Amendment
|
$0.00
|
DC04BCO1
|
Cost Decrease
|
05/21/2025
|
05/21/2025
|
|
|
Amendment
|
$0.00
|
PA362CO1
|
Cost adjustment for increased subcons. 6/30/2026
|
05/21/2025
|
05/21/2025
|
|
|
Amendment
|
$0.00
|
DC02DCO4
|
Cost Decrease
|
05/14/2025
|
05/14/2025
|
|
|
Amendment
|
$75,000.00
|
FIL18
|
Funding Increment Increase
|
05/14/2025
|
05/14/2025
|
|
|
Amendment
|
$0.00
|
DC001F
|
Site Review Meeting
|
05/13/2025
|
05/13/2025
|
|
|
Amendment
|
$0.00
|
DC26CCO1
|
Cost Increase and task time extension 1/22/2026
|
05/12/2025
|
05/12/2025
|
|
|
Amendment
|
$0.00
|
DC05DCO1
|
Reconciles WCD 1 & 2
|
05/12/2025
|
05/12/2025
|
|
|
Amendment
|
$0.00
|
HW013A
|
Annual GWM
|
05/12/2025
|
05/12/2025
|
|
|
Amendment
|
$0.00
|
DC011D
|
Conduct PARM
|
05/12/2025
|
05/12/2025
|
|
|
Amendment
|
$0.00
|
DC31BCO4
|
Cost Decrease
|
05/09/2025
|
05/09/2025
|
|
|
Amendment
|
$50,000.00
|
FIL17
|
Funding Increment Increase
|
04/15/2025
|
04/15/2025
|
|
|
Amendment
|
$0.00
|
DC29CCO1
|
Cost Decrease
|
04/07/2025
|
04/07/2025
|
|
|
Amendment
|
$0.00
|
DC02DCO3
|
Cost increase
|
04/07/2025
|
04/07/2025
|
|
|
Amendment
|
$0.00
|
DC08DCO1
|
WCD reconciliation
|
04/07/2025
|
04/07/2025
|
|
|
Amendment
|
$0.00
|
DC43BCO3
|
Cost Decrease
|
04/07/2025
|
04/07/2025
|
|
|
Amendment
|
$0.00
|
DC33CCO1
|
Cost reduction
|
04/04/2025
|
04/04/2025
|
|
|
Amendment
|
$0.00
|
DC44BCO2
|
Cost Reduction
|
03/31/2025
|
03/31/2025
|
|
|
Amendment
|
$0.00
|
DC13CCO1
|
Cost Reduction
|
03/21/2025
|
03/21/2025
|
|
|
Amendment
|
$0.00
|
HW10CCO3
|
Cost Reduction
|
03/21/2025
|
03/21/2025
|
|
|
Amendment
|
$475,000.00
|
FIL16
|
Funding Increment increase
|
03/18/2025
|
03/18/2025
|
|
|
Amendment
|
$0.00
|
DC44BCO1
|
Cost Reduction
|
03/12/2025
|
03/12/2025
|
|
|
Amendment
|
$0.00
|
PA362
|
Site Assessment. 6/30/2025
|
03/12/2025
|
03/12/2025
|
|
|
Amendment
|
$0.00
|
DC02DCO2
|
Time Extension
|
03/10/2025
|
03/10/2025
|
|
|
Amendment
|
$0.00
|
DC43BCO2
|
Cost Decrease
|
03/05/2025
|
03/05/2025
|
|
|
Amendment
|
$0.00
|
PA268CO2
|
Reconcile WCD 1 and 2 5/30/2025
|
02/26/2025
|
02/26/2025
|
|
|
Amendment
|
$0.00
|
DC03ECO1
|
Cost Decrease
|
02/24/2025
|
02/24/2025
|
|
|
Amendment
|
$0.00
|
DC43BCO1
|
Cost Decrease
|
02/24/2025
|
02/24/2025
|
|
|
Amendment
|
$0.00
|
PA320CO2
|
Time Extension
|
02/19/2025
|
02/19/2025
|
|
|
Amendment
|
$0.00
|
DC31BCO3
|
Cost Decrease
|
02/19/2025
|
02/19/2025
|
|
|
Amendment
|
$0.00
|
PA321CO2
|
Time Extension
|
02/18/2025
|
02/18/2025
|
|
|
Amendment
|
$0.00
|
DC21CCO1
|
Cost Decrease
|
02/18/2025
|
02/18/2025
|
|
|
Amendment
|
$150,000.00
|
FIL15
|
Funding Increment Increase
|
02/06/2025
|
02/06/2025
|
|
|
Amendment
|
$0.00
|
DC026C
|
Annual Groundwater Sampling
|
02/05/2025
|
02/05/2025
|
|
|
Amendment
|
$0.00
|
DC020C
|
Annual Groundwater Monitoring and Well Installation
|
02/05/2025
|
02/05/2025
|
|
|
Amendment
|
$0.00
|
DC032C
|
O&M
|
12/20/2024
|
12/20/2024
|
|
|
Amendment
|
$0.00
|
DC029C
|
LTM. 7/4/2025
|
12/20/2024
|
12/20/2024
|
|
|
Amendment
|
$0.00
|
DC24ACO9
|
Cost reduction
|
12/20/2024
|
12/20/2024
|
|
|
Amendment
|
$0.00
|
DC31BCO2
|
Change in Scope
|
12/19/2024
|
12/19/2024
|
|
|
Amendment
|
$0.00
|
DC008D
|
O&M
|
12/19/2024
|
12/19/2024
|
|
|
Amendment
|
$0.00
|
DC025C
|
Long Term Monitoring
|
12/19/2024
|
12/19/2024
|
|
|
Amendment
|
$0.00
|
DC013C
|
O&M and Groung Monitoring 10/23/2025
|
12/17/2024
|
12/17/2024
|
|
|
Amendment
|
$0.00
|
DC16BCO4
|
Cost Decrease
|
12/17/2024
|
12/17/2024
|
|
|
Amendment
|
$0.00
|
DC021C
|
(O&M) and Groundwater Monitoring
|
12/12/2024
|
12/12/2024
|
|
|
Amendment
|
$0.00
|
PA268CO1
|
No Cost Time Extension 3/31/2025
|
12/12/2024
|
12/12/2024
|
|
|
Amendment
|
$0.00
|
DC033C
|
LTM
|
12/11/2024
|
12/11/2024
|
|
|
Amendment
|
$0.00
|
DC004B
|
LTM
|
12/11/2024
|
12/11/2024
|
|
|
Amendment
|
$350,000.00
|
FIL14
|
Funding Increment Increase
|
12/11/2024
|
12/11/2024
|
|
|
Amendment
|
$0.00
|
PA321CO1
|
Cost Decrease
|
12/11/2024
|
12/11/2024
|
|
|
Amendment
|
$0.00
|
DC005D
|
Long Term Monitoring
|
12/11/2024
|
12/11/2024
|
|
|
Amendment
|
$0.00
|
DC016C
|
O&M
|
12/11/2024
|
12/11/2024
|
|
|
Amendment
|
$0.00
|
DC015C
|
O&M
|
12/10/2024
|
12/10/2024
|
|
|
Amendment
|
$0.00
|
DC003E
|
O&M
|
12/10/2024
|
12/10/2024
|
|
|
Amendment
|
$0.00
|
DC022C
|
O&M and Ground Monitoring
|
12/09/2024
|
12/09/2024
|
|
|
Amendment
|
$0.00
|
DC030C
|
Groundwater Monitoring
|
12/09/2024
|
12/09/2024
|
|
|
Amendment
|
$0.00
|
PA320CO1
|
Cost Decrease
|
12/09/2024
|
12/09/2024
|
|
|
Amendment
|
$0.00
|
DC018C
|
LTM
|
12/09/2024
|
12/09/2024
|
|
|
Amendment
|
$0.00
|
DC01ACO4
|
Cost Decrease
|
11/18/2024
|
11/18/2024
|
|
|
Amendment
|
$0.00
|
DC01ACO3
|
Cost Increase
|
10/31/2024
|
10/31/2024
|
|
|
Amendment
|
$25,000.00
|
FIL13
|
Funding Increment Increase
|
10/28/2024
|
10/28/2024
|
|
|
Amendment
|
$89,703.87
|
FIL12
|
Funding Increment increase
|
10/10/2024
|
10/10/2024
|
|
|
Amendment
|
$0.00
|
DC34BCO1
|
Cost Decrease
|
09/20/2024
|
09/20/2024
|
|
|
Amendment
|
$0.00
|
DC21BCO3
|
Cost Increase
|
09/18/2024
|
09/18/2024
|
|
|
Amendment
|
$0.00
|
DC16BCO3
|
Cost Increase
|
09/18/2024
|
09/18/2024
|
|
|
Amendment
|
$0.00
|
DC15BCO3
|
Cost Increase
|
09/16/2024
|
09/16/2024
|
|
|
Amendment
|
$0.00
|
DC13BCO2
|
Cost Increase
|
09/12/2024
|
09/12/2024
|
|
|
Amendment
|
$0.00
|
DC02DCO1
|
Cost Increase
|
09/12/2024
|
09/12/2024
|
|
|
Amendment
|
$0.00
|
DC03DCO1
|
Descopes and zeroes out all cost /labor hours
|
09/06/2024
|
09/06/2024
|
|
|
Amendment
|
$0.00
|
DC08CO3
|
Cost increase & change in scope
|
09/05/2024
|
09/05/2024
|
|
|
Amendment
|
$0.00
|
DC22BCO2
|
Cost Increase
|
09/01/2024
|
09/01/2024
|
|
|
Amendment
|
$0.00
|
HW10CCO2
|
Time extension
|
08/30/2024
|
08/30/2024
|
|
|
Amendment
|
$0.00
|
DC11CCO3
|
Cost Reduction/labor hour change
|
08/27/2024
|
08/27/2024
|
|
|
Amendment
|
$0.00
|
DC24ACO8
|
Cost reduction
|
08/16/2024
|
08/16/2024
|
|
|
Amendment
|
$0.00
|
DC12CCO3
|
Cost reduction
|
08/16/2024
|
08/16/2024
|
|
|
Amendment
|
$0.00
|
PA321
|
Site Assessment
|
07/31/2024
|
07/31/2024
|
|
|
Amendment
|
$0.00
|
PA320
|
Site Reconnaissance and PSW Sampling
|
07/30/2024
|
07/30/2024
|
|
|
Amendment
|
$0.00
|
DC05CCO3
|
increase in time
|
07/23/2024
|
07/23/2024
|
|
|
Amendment
|
$0.00
|
DC42BCO3
|
CO: Cost Reduction
|
07/15/2024
|
07/15/2024
|
|
|
Amendment
|
$0.00
|
DC05CCO2
|
Cost Decrease
|
07/15/2024
|
07/15/2024
|
|
|
Amendment
|
$0.00
|
DC11CC02
|
Cost decrease due to change in staff and scope
|
07/12/2024
|
07/12/2024
|
|
|
Amendment
|
$0.00
|
DC11CCO2
|
Personnel Change
|
07/12/2024
|
07/12/2024
|
|
|
Amendment
|
$0.00
|
DC13BCO1
|
Cost reduction
|
07/10/2024
|
07/10/2024
|
|
|
Amendment
|
$100,000.00
|
FIL11
|
Funding Increment Increase
|
07/09/2024
|
07/09/2024
|
|
|
Amendment
|
$0.00
|
DC41BCO2
|
Cost Reduction
|
07/08/2024
|
07/08/2024
|
|
|
Amendment
|
$0.00
|
DC03CCO3
|
Task time extension
|
07/08/2024
|
07/08/2024
|
|
|
Amendment
|
$0.00
|
DC16BCO2
|
Cost reduction
|
07/08/2024
|
07/08/2024
|
|
|
Amendment
|
$0.00
|
DC22BCO1
|
Reduction in Scope of Work
|
07/08/2024
|
07/08/2024
|
|
|
Amendment
|
$0.00
|
DC035C
|
Site Restoration
|
06/27/2024
|
06/27/2024
|
|
|
Amendment
|
$0.00
|
DC034B
|
Long Term Monitoring
|
06/27/2024
|
06/27/2024
|
12/07/2024
|
|
Amendment
|
$0.00
|
DC040C
|
VEW Abandonment
|
06/27/2024
|
06/27/2024
|
|
|
Amendment
|
$0.00
|
DC044B
|
Site Assessment
|
06/27/2024
|
06/27/2024
|
|
|
Amendment
|
$0.00
|
DC043B
|
Site Assessment
|
06/26/2024
|
06/26/2024
|
05/28/2025
|
|
Amendment
|
$0.00
|
HW002C
|
Long Term Monitoring
|
06/24/2024
|
06/24/2024
|
|
|
Amendment
|
$0.00
|
DC017C
|
Long Term Monitoring
|
06/24/2024
|
06/24/2024
|
|
|
Amendment
|
$0.00
|
DC02CCO1
|
WCD Reconciliation
|
06/10/2024
|
06/10/2024
|
|
|
Amendment
|
$0.00
|
DC002D
|
Excavation
|
06/03/2024
|
06/03/2024
|
|
|
Amendment
|
$0.00
|
DC32BCO1
|
Cost Reduction
|
05/31/2024
|
05/31/2024
|
|
|
Amendment
|
$0.00
|
DC15BCO2
|
Cost Reduction
|
05/31/2024
|
05/31/2024
|
|
|
Amendment
|
$0.00
|
DC08CCO2
|
Cost Reduction
|
05/31/2024
|
05/31/2024
|
|
|
Amendment
|
$0.00
|
DC12CCO2
|
Cost Increase
|
05/31/2024
|
05/31/2024
|
|
|
Amendment
|
$0.00
|
DC23CCO
|
Entered in Error
|
05/30/2024
|
05/30/2024
|
|
|
Amendment
|
$0.00
|
DC23CCO1
|
Cost Increase
|
05/30/2024
|
05/30/2024
|
|
|
Amendment
|
$0.00
|
HW10CCO1
|
Increase in time
|
05/15/2024
|
05/15/2024
|
|
|
Amendment
|
$0.00
|
DC42BCO2
|
Cost Decrease
|
05/07/2024
|
05/07/2024
|
|
|
Amendment
|
$0.00
|
DC37BCO4
|
Cost Reduction
|
04/30/2024
|
04/30/2024
|
|
|
Amendment
|
$0.00
|
DC24ACO7
|
Phase or reason for TACO
|
04/29/2024
|
04/29/2024
|
|
|
Amendment
|
$0.00
|
DC03CCO2
|
WCD Reconciliation
|
04/25/2024
|
04/25/2024
|
|
|
Amendment
|
$0.00
|
DC35BCO3
|
Cost Reduction
|
04/18/2024
|
04/18/2024
|
|
|
Amendment
|
$0.00
|
DC38BCO3
|
Cost Reduction
|
04/12/2024
|
04/12/2024
|
|
|
Amendment
|
$0.00
|
DC21BCO2
|
Cost Reduction
|
04/06/2024
|
04/06/2024
|
|
|
Amendment
|
$0.00
|
DC25BCO2
|
Decrease in cost
|
04/04/2024
|
04/04/2024
|
|
|
Amendment
|
$0.00
|
DC07BCO3
|
WCD #2 and #3 reconciliation
|
04/04/2024
|
04/04/2024
|
|
|
Amendment
|
$0.00
|
DC014B
|
Bid Specification
|
04/04/2024
|
04/04/2024
|
|
|
Amendment
|
$292,767.60
|
FIL10
|
Funding Increment Increase
|
04/02/2024
|
04/02/2024
|
|
|
Amendment
|
$0.00
|
DC24ACO6
|
Increase in cost and time
|
04/01/2024
|
04/01/2024
|
|
|
Amendment
|
$0.00
|
HW01BCO2
|
Decrease in cost
|
04/01/2024
|
04/01/2024
|
|
|
Amendment
|
$0.00
|
DC26BCO4
|
Decrease in price, increase in time
|
03/26/2024
|
03/26/2024
|
|
|
Amendment
|
$0.00
|
DC36BCO2
|
cost adjustment for change in scope of work
|
03/20/2024
|
03/20/2024
|
|
|
Amendment
|
$0.00
|
DC20BCO2
|
Cost adjustment for change in scope of work
|
03/20/2024
|
03/20/2024
|
|
|
Amendment
|
$0.00
|
DC12CCO1
|
Increase in Cost and Time
|
03/19/2024
|
03/19/2024
|
|
|
Amendment
|
$0.00
|
DC08CCO1
|
Cost adjustment for change in scope of work
|
03/18/2024
|
03/18/2024
|
|
|
Amendment
|
$0.00
|
DC35BCO2
|
Cost adjustment for change in scope of work
|
03/18/2024
|
03/18/2024
|
|
|
Amendment
|
$0.00
|
DC41BCO1
|
No Cost Time Extension
|
03/12/2024
|
03/12/2024
|
|
|
Amendment
|
$0.00
|
DC06BCO4
|
No Cost Time Extension
|
03/12/2024
|
03/12/2024
|
|
|
Amendment
|
$0.00
|
HW10BCO2
|
decrease in cost, increase in time
|
03/05/2024
|
03/05/2024
|
|
|
Amendment
|
$0.00
|
DC21BCO1
|
Cost adjustment for change in scope of work
|
02/25/2024
|
02/25/2024
|
|
|
Amendment
|
$0.00
|
DC25BCO1
|
Task time extension and decrease in cost
|
02/22/2024
|
02/22/2024
|
|
|
Amendment
|
$0.00
|
DC18BCO2
|
Cost adjustment for change in scope of work
|
02/20/2024
|
02/20/2024
|
|
|
Amendment
|
$0.00
|
DC40BCO2
|
Cost adjustment for change in scope of work
|
02/16/2024
|
02/16/2024
|
|
|
Amendment
|
$0.00
|
HW01BCO1
|
Cost adjument for change in scope of work
|
02/14/2024
|
02/14/2024
|
|
|
Amendment
|
$0.00
|
DC37BCO3
|
Cost adjusment for change in scope of work
|
02/14/2024
|
02/14/2024
|
|
|
Amendment
|
$0.00
|
DC33BCO1
|
Cost adjustment for change in scope of work
|
02/13/2024
|
02/13/2024
|
|
|
Amendment
|
$0.00
|
DC16BCO1
|
Cost adjsutment for change in the scope of work
|
02/09/2024
|
02/09/2024
|
|
|
Amendment
|
$0.00
|
HW11ACO1
|
Cost adjustment for change in scope of work
|
02/08/2024
|
02/08/2024
|
|
|
Amendment
|
$0.00
|
DC24ACO5
|
Increase in Time
|
02/08/2024
|
02/08/2024
|
|
|
Amendment
|
$0.00
|
DC38BCO2
|
cost adjustment for change in scope of work
|
02/06/2024
|
02/06/2024
|
|
|
Amendment
|
$0.00
|
DC10BCO3
|
Cost adjustment for change in scope of work
|
02/05/2024
|
02/05/2024
|
|
|
Amendment
|
$0.00
|
DC002C
|
ISR
|
01/31/2024
|
01/31/2024
|
|
|
Amendment
|
$0.00
|
DC15BCO1
|
Cost adjustment for change in scope of work
|
01/26/2024
|
01/26/2024
|
|
|
Amendment
|
$0.00
|
DC03CCO1
|
Cost adjustment for change in scope of work
|
01/26/2024
|
01/26/2024
|
|
|
Amendment
|
$0.00
|
DC42BCO1
|
Cost adjustment for change in scope of work
|
01/26/2024
|
01/26/2024
|
|
|
Amendment
|
$0.00
|
DC31BCO1
|
Cost adjustment for change in scope of work
|
01/24/2024
|
01/24/2024
|
|
|
Amendment
|
$0.00
|
DC32ACO1
|
Cost adjustment for change in scope of work
|
01/22/2024
|
01/22/2024
|
|
|
Amendment
|
$0.00
|
DC11CCO1
|
Cost adjustment for change in scope of work
|
01/22/2024
|
01/22/2024
|
|
|
Amendment
|
$0.00
|
DC027C
|
MAGS Sampling and SRCR prep
|
01/11/2024
|
01/11/2024
|
|
|
Amendment
|
$0.00
|
DC023C
|
Abandon Vapor Extraction Wells
|
01/11/2024
|
01/11/2024
|
|
|
Amendment
|
$0.00
|
DC011C
|
O&M
|
01/07/2024
|
01/07/2024
|
|
|
Amendment
|
$0.00
|
DC05CCO1
|
No Cost task time extension
|
12/29/2023
|
12/29/2023
|
|
|
Amendment
|
$0.00
|
DC19BCO1
|
Cost Increase + Task Time Extension
|
12/27/2023
|
12/27/2023
|
|
|
Amendment
|
$0.00
|
DC01ACO2
|
Increase in cost
|
12/15/2023
|
12/15/2023
|
|
|
Amendment
|
$0.00
|
DC10BCO2
|
No cost time extension
|
12/15/2023
|
12/15/2023
|
|
|
Amendment
|
$0.00
|
DC18BCO1
|
cost adjustment for change in scope of work
|
12/13/2023
|
12/13/2023
|
|
|
Amendment
|
$0.00
|
HW07ACO3
|
No Cost Time Extension
|
12/06/2023
|
12/06/2023
|
|
|
Amendment
|
$0.00
|
DC02BCO2
|
Cost reduction and time extension
|
12/06/2023
|
12/06/2023
|
|
|
Amendment
|
$0.00
|
DC07BCO2
|
Increase in cost
|
12/05/2023
|
12/05/2023
|
|
|
Amendment
|
$0.00
|
PA265
|
Desktop File Review - Delray Beach - Well #8; ERIC_18440
|
12/05/2023
|
12/05/2023
|
|
|
Amendment
|
$0.00
|
PA268
|
SAR & T&D (IDW) - Coral Springs FTF; ERIC_7415
|
11/28/2023
|
11/28/2023
|
|
|
Amendment
|
$0.00
|
DC26BCO3
|
No Cost Time extension
|
11/28/2023
|
11/28/2023
|
|
|
Amendment
|
$0.00
|
DC06BCO3
|
No Cost Time Extension
|
11/27/2023
|
11/27/2023
|
|
|
Amendment
|
$1,400,000.00
|
FIL9
|
Funding Increment Increase
|
11/20/2023
|
11/20/2023
|
|
|
Amendment
|
$0.00
|
DC20BCO1
|
Cost adjustment for change in scope of work
|
11/16/2023
|
11/16/2023
|
|
|
Amendment
|
$0.00
|
DC35BCO1
|
Reduce drilling costs
|
11/07/2023
|
11/07/2023
|
|
|
Amendment
|
$0.00
|
DC37BCO2
|
Cost reduction and time extension
|
11/01/2023
|
11/01/2023
|
|
|
Amendment
|
$0.00
|
DC36BCO1
|
Reduction in scope of work
|
10/31/2023
|
10/31/2023
|
|
|
Amendment
|
$0.00
|
PA266
|
Desktop File Review - Pompano Beach - Well #6; ERIC_18439
|
10/31/2023
|
10/31/2023
|
|
|
Amendment
|
$0.00
|
HW003C
|
RAPA
|
10/20/2023
|
10/20/2023
|
|
|
Amendment
|
$0.00
|
DOD02
|
Document review
|
10/16/2023
|
10/16/2023
|
|
|
Amendment
|
$0.00
|
DC06BCO2
|
Reduce subcontract costs
|
10/16/2023
|
10/16/2023
|
|
|
Amendment
|
$0.00
|
DC043A
|
Site assessment work plan
|
10/12/2023
|
10/12/2023
|
|
|
Amendment
|
$0.00
|
HW012A
|
Critical Response TA
|
10/12/2023
|
10/12/2023
|
|
|
Amendment
|
$0.00
|
DC044A
|
Site assessment work plan
|
10/12/2023
|
10/12/2023
|
|
|
Amendment
|
$0.00
|
HW10BCO1
|
Change of Scope
|
10/12/2023
|
10/12/2023
|
|
|
Amendment
|
$100,664.18
|
FIL8
|
Funding Increment Increase
|
10/09/2023
|
10/09/2023
|
|
|
Amendment
|
$0.00
|
DC40BCO1
|
Cost reduction and time extension
|
10/06/2023
|
10/06/2023
|
|
|
Amendment
|
$0.00
|
PA257
|
SAWP & Site Recon, City of Miami FRTC; ERIC_7422
|
10/05/2023
|
10/05/2023
|
|
|
Amendment
|
$0.00
|
HW07ACO2
|
Remove sites due to access issues
|
09/25/2023
|
09/25/2023
|
|
|
Amendment
|
$0.00
|
DC37BCO1
|
Reconcile WCD 1
|
09/22/2023
|
09/22/2023
|
|
|
Amendment
|
$0.00
|
DC001E
|
Annual Site Review Meeting
|
09/07/2023
|
09/07/2023
|
|
|
Amendment
|
$183,724.12
|
FIL7
|
Funding Increment Increase
|
08/29/2023
|
08/29/2023
|
|
|
Amendment
|
$0.00
|
DC38BCO1
|
Reconciles WCD #1
|
08/24/2023
|
08/24/2023
|
|
|
Amendment
|
$0.00
|
DC16ACO3
|
Reconciles WCD #5
|
08/22/2023
|
08/22/2023
|
|
|
Amendment
|
$0.00
|
DC11BCO2
|
Added 1 quarter of O&M
|
08/21/2023
|
08/21/2023
|
|
|
Amendment
|
$0.00
|
DC26BCO2
|
Added private lab costs and additional boundry survey.
|
08/17/2023
|
08/17/2023
|
|
|
Amendment
|
$0.00
|
HW07ACO1
|
Reconciles WCD #1
|
08/15/2023
|
08/15/2023
|
|
|
Amendment
|
$0.00
|
DC02BCO1
|
Reconciles WCD #1
|
08/10/2023
|
08/10/2023
|
|
|
Amendment
|
$0.00
|
DC24ACO4
|
Additional Driller Costs and Time Extension
|
07/27/2023
|
07/27/2023
|
|
|
Amendment
|
$0.00
|
HW09ACO2
|
Added creation of new figures
|
07/18/2023
|
07/18/2023
|
|
|
Amendment
|
$1,967,421.41
|
FIL6
|
Funding Increment Increase
|
07/17/2023
|
07/17/2023
|
|
|
Amendment
|
$0.00
|
DC07BCO1
|
Added an additonal Groundwater Monitoring Report
|
07/17/2023
|
07/17/2023
|
|
|
Amendment
|
$0.00
|
DC023B
|
Groundwater Sampling
|
06/30/2023
|
06/30/2023
|
|
|
Amendment
|
$0.00
|
DC021B
|
Operation and Maintenance
|
06/30/2023
|
06/30/2023
|
|
|
Amendment
|
$0.00
|
DC025B
|
Well Install and Supplemental Site Assessment
|
06/30/2023
|
06/30/2023
|
|
|
Amendment
|
$0.00
|
DC007B
|
Semi-Annual Groundwater Monitoring
|
06/30/2023
|
06/30/2023
|
|
|
Amendment
|
$0.00
|
DC012C
|
Quarterly Groundwater Monitoring
|
06/30/2023
|
06/30/2023
|
|
|
Amendment
|
$0.00
|
DC003D
|
11 Month Operation and Maintenance
|
06/30/2023
|
06/30/2023
|
|
|
Amendment
|
$0.00
|
DC031B
|
Supplemental Site Assessment
|
06/29/2023
|
06/29/2023
|
|
|
Amendment
|
$0.00
|
DC041B
|
Site Assessment
|
06/29/2023
|
06/29/2023
|
|
|
Amendment
|
$0.00
|
HW010C
|
Supplemental Site Assessment
|
06/29/2023
|
06/29/2023
|
|
|
Amendment
|
$0.00
|
DC040B
|
Site Assessment
|
06/29/2023
|
06/29/2023
|
|
|
Amendment
|
$0.00
|
HW001B
|
Supplemental Site Assessment
|
06/29/2023
|
06/29/2023
|
|
|
Amendment
|
$0.00
|
DC035B
|
Site Assessment
|
06/28/2023
|
06/28/2023
|
|
|
Amendment
|
$0.00
|
HW002B
|
Annual Groundwater Monitoring
|
06/28/2023
|
06/28/2023
|
|
|
Amendment
|
$0.00
|
DC042B
|
Site Assessment
|
06/28/2023
|
06/28/2023
|
|
|
Amendment
|
$0.00
|
DC008C
|
12 Month Operation and Maintenance + Groundwater Monitoring
|
06/28/2023
|
06/28/2023
|
|
|
Amendment
|
$0.00
|
DC032B
|
12 Month Operation and Maintenance + Groundwater Monitoring
|
06/28/2023
|
06/28/2023
|
|
|
Amendment
|
$0.00
|
DC003C
|
SVE system installation
|
06/28/2023
|
06/28/2023
|
|
|
Amendment
|
$0.00
|
DC06BCO1
|
Outsourcing lab work to private lab
|
06/27/2023
|
06/27/2023
|
|
|
Amendment
|
$0.00
|
DC018B
|
Monitoring Well Install and Annual Groundwater Monitoring
|
06/27/2023
|
06/27/2023
|
|
|
Amendment
|
$0.00
|
DC019B
|
Groundwater Monitoring
|
06/26/2023
|
06/26/2023
|
|
|
Amendment
|
$0.00
|
DC009C
|
Supplemental Site Assessment
|
06/26/2023
|
06/26/2023
|
|
|
Amendment
|
$0.00
|
DC033B
|
Annual Groundwater Monitoring
|
06/26/2023
|
06/26/2023
|
|
|
Amendment
|
$0.00
|
DC020B
|
Annual Groundwater Monitoring
|
06/23/2023
|
06/23/2023
|
|
|
Amendment
|
$0.00
|
PA249CO1
|
Time Ext - SAWP - City of Hialeah FTF; ERIC_7419
|
06/23/2023
|
06/23/2023
|
|
|
Amendment
|
$0.00
|
DC10BCO1
|
Expanded Phase II scope
|
06/21/2023
|
06/21/2023
|
|
|
Amendment
|
$0.00
|
HW011A
|
Groundwater Sampling
|
06/21/2023
|
06/21/2023
|
|
|
Amendment
|
$0.00
|
HW010B
|
Groundwater Sampling
|
06/21/2023
|
06/21/2023
|
|
|
Amendment
|
$0.00
|
DC005C
|
Supplemental Site Assessment
|
06/21/2023
|
06/21/2023
|
|
|
Amendment
|
$0.00
|
DC017B
|
Groundwater Monitoring
|
06/21/2023
|
06/21/2023
|
|
|
Amendment
|
$0.00
|
DC24ACO3
|
Obtaining ROW and changing Sonic Well Installation to DPT.
|
06/21/2023
|
06/21/2023
|
|
|
Amendment
|
$0.00
|
DC15ACO1
|
Additional VOH samples
|
06/21/2023
|
06/21/2023
|
|
|
Amendment
|
$0.00
|
DC21ACO1
|
Reconciles WCD 1
|
06/21/2023
|
06/21/2023
|
|
|
Amendment
|
$0.00
|
DC038B
|
Site Assessment
|
06/20/2023
|
06/20/2023
|
|
|
Amendment
|
$0.00
|
DC036B
|
Site Assessment
|
06/16/2023
|
06/16/2023
|
|
|
Amendment
|
$0.00
|
DC037B
|
Site Assessment
|
06/16/2023
|
06/16/2023
|
|
|
Amendment
|
$0.00
|
HW09ACO1
|
Reconciles WCD 1
|
06/12/2023
|
06/12/2023
|
|
|
Amendment
|
$0.00
|
DC016B
|
Operation and Maintenance
|
06/07/2023
|
06/07/2023
|
|
|
Amendment
|
$0.00
|
DC08BCO2
|
Reconcile WCD 1
|
06/07/2023
|
06/07/2023
|
|
|
Amendment
|
$0.00
|
DC030B
|
Annual Groundwater Monitoring
|
06/07/2023
|
06/07/2023
|
|
|
Amendment
|
$0.00
|
DC022B
|
Operation and Maintenance + Groundwater Monitoring
|
06/07/2023
|
06/07/2023
|
|
|
Amendment
|
$0.00
|
DC013B
|
Operation and Maintenance + Groundwater Monitoring
|
06/07/2023
|
06/07/2023
|
|
|
Amendment
|
$0.00
|
HW010A
|
Updated site parcel
|
06/05/2023
|
06/05/2023
|
|
|
Amendment
|
$0.00
|
DC006B
|
Sampling
|
06/05/2023
|
06/05/2023
|
|
|
Amendment
|
$0.00
|
DC11BCO1
|
Change in scope
|
05/30/2023
|
05/30/2023
|
|
|
Amendment
|
$0.00
|
DC08BCO1
|
Time extension
|
05/30/2023
|
05/30/2023
|
|
|
Amendment
|
$0.00
|
DC041A
|
Site assessment Work plan
|
05/25/2023
|
05/25/2023
|
|
|
Amendment
|
$0.00
|
DC042A
|
Site Assessment Work Plan
|
05/25/2023
|
05/25/2023
|
|
|
Amendment
|
$0.00
|
DC040A
|
Site Assessment work Plan
|
05/22/2023
|
05/22/2023
|
|
|
Amendment
|
$0.00
|
DC001D
|
Authroizes CDM to send staff 3 members
|
05/16/2023
|
05/16/2023
|
|
|
Amendment
|
$0.00
|
DC029B
|
Conduct annual groundwater monitoring
|
05/16/2023
|
05/16/2023
|
|
|
Amendment
|
$0.00
|
DC015B
|
O&M and groundwater sampling
|
05/09/2023
|
05/09/2023
|
|
|
Amendment
|
$0.00
|
PA249
|
SAWP & Site Recon - City of Hialeah FTF; ERIC_7419
|
04/28/2023
|
04/28/2023
|
|
|
Amendment
|
$0.00
|
DC16ACO2
|
Reconciles WCD #4
|
04/13/2023
|
04/13/2023
|
|
|
Amendment
|
$0.00
|
HW007A
|
PFAS Screening
|
04/11/2023
|
04/11/2023
|
|
|
Amendment
|
$0.00
|
DC26BCO1
|
Reconcile WCD #1
|
04/05/2023
|
04/05/2023
|
|
|
Amendment
|
$0.00
|
DC28BCO1
|
Reconciles WCD #1
|
04/05/2023
|
04/05/2023
|
|
|
Amendment
|
$0.00
|
DC14ACO2
|
Reconciles WCD #1
|
04/05/2023
|
04/05/2023
|
|
|
Amendment
|
$0.00
|
DC27BCO1
|
Reconciles WCD #1
|
04/05/2023
|
04/05/2023
|
|
|
Amendment
|
$0.00
|
DC03BCO2
|
Reconciles WCD #1 and reduces price as per change in scope
|
04/05/2023
|
04/05/2023
|
|
|
Amendment
|
$0.00
|
DC002B
|
Supplemental Site Assessment
|
03/30/2023
|
03/30/2023
|
|
|
Amendment
|
$0.00
|
DC11ACO1
|
Reconciles WCD #1
|
03/30/2023
|
03/30/2023
|
|
|
Amendment
|
$0.00
|
DC16ACO1
|
Reconiles WCDs
|
03/28/2023
|
03/28/2023
|
|
|
Amendment
|
$0.00
|
DC23ACO1
|
Reconiles WCDs
|
03/28/2023
|
03/28/2023
|
|
|
Amendment
|
$0.00
|
DC05BCO1
|
Reconiles WCD 1, 2, and 3
|
03/22/2023
|
03/22/2023
|
|
|
Amendment
|
$0.00
|
DC24ACO2
|
Increase in cost to facilitate well installations
|
03/21/2023
|
03/21/2023
|
|
|
Amendment
|
$0.00
|
DC012B
|
groundwater sampling
|
03/20/2023
|
03/20/2023
|
|
|
Amendment
|
$0.00
|
HW003B
|
groundwater sampling
|
03/20/2023
|
03/20/2023
|
|
|
Amendment
|
$0.00
|
DC34ACO1
|
Reconciles WCD #1
|
03/17/2023
|
03/17/2023
|
|
|
Amendment
|
$0.00
|
HW05ACO1
|
Time extension
|
03/02/2023
|
03/02/2023
|
|
|
Amendment
|
$0.00
|
DC25ACO1
|
Time extension
|
02/27/2023
|
02/27/2023
|
|
|
Amendment
|
$0.00
|
DC35ACO1
|
Task time extension
|
02/27/2023
|
02/27/2023
|
|
|
Amendment
|
$0.00
|
DC24ACO1
|
Task time extension
|
02/27/2023
|
02/27/2023
|
|
|
Amendment
|
$0.00
|
DC09BCO1
|
Reconciling WCD 1
|
02/27/2023
|
02/27/2023
|
|
|
Amendment
|
$0.00
|
DC07ACO1
|
Time Extension
|
02/13/2023
|
02/13/2023
|
|
|
Amendment
|
$0.00
|
PA231
|
ERIC_7415 Coral Springs Fire Academy-Site Recon
|
02/09/2023
|
02/09/2023
|
|
|
Amendment
|
$0.00
|
DC011B
|
CDM to conduct operation and maintenance
|
02/09/2023
|
02/09/2023
|
|
|
Amendment
|
$0.00
|
DC035A
|
Site Assessment Work Plan
|
01/23/2023
|
01/23/2023
|
|
|
Amendment
|
$0.00
|
DC036A
|
Site Assessment Work Plan
|
01/23/2023
|
01/23/2023
|
|
|
Amendment
|
$0.00
|
DC037A
|
Site Assessment Work Plan
|
01/23/2023
|
01/23/2023
|
|
|
Amendment
|
$0.00
|
DC038A
|
Site Assessment Work Plan
|
01/23/2023
|
01/23/2023
|
|
|
Amendment
|
$0.00
|
DC03BCO1
|
Time extension
|
01/12/2023
|
01/12/2023
|
|
|
Amendment
|
$0.00
|
DC026B
|
Site assessment
|
01/12/2023
|
01/12/2023
|
|
|
Amendment
|
$0.00
|
DC01ACO1
|
increase in cost
|
01/03/2023
|
01/03/2023
|
|
|
Amendment
|
$0.00
|
HW02ACO1
|
Time extension
|
01/01/2023
|
01/01/2023
|
|
|
Amendment
|
$0.00
|
HW01ACO1
|
Time extension
|
12/15/2022
|
12/15/2022
|
|
|
Amendment
|
$0.00
|
DC028B
|
Site Assessment
|
12/12/2022
|
12/12/2022
|
|
|
Amendment
|
$0.00
|
DC17ACO1
|
90 day time extension
|
12/12/2022
|
12/12/2022
|
|
|
Amendment
|
$0.00
|
DC18ACO1
|
90 day extension
|
12/12/2022
|
12/12/2022
|
|
|
Amendment
|
$0.00
|
DC19ACO1
|
Time extension
|
12/12/2022
|
12/12/2022
|
|
|
Amendment
|
$0.00
|
DC20ACO1
|
Time extension
|
12/12/2022
|
12/12/2022
|
|
|
Amendment
|
$0.00
|
DC14ACO1
|
Adds costs for private utility location
|
12/08/2022
|
12/08/2022
|
|
|
Amendment
|
$0.00
|
HW009A
|
Supplemental Site Assessment
|
11/21/2022
|
11/21/2022
|
|
|
Amendment
|
$0.00
|
DC027B
|
Site assessment
|
11/18/2022
|
11/18/2022
|
|
|
Amendment
|
$0.00
|
HW006A
|
PFAS sampling
|
11/07/2022
|
11/07/2022
|
|
|
Amendment
|
$0.00
|
HW005A
|
PFAS sampling
|
11/07/2022
|
11/07/2022
|
|
|
Amendment
|
$0.00
|
DC034A
|
Groundwater monitoring
|
11/04/2022
|
11/04/2022
|
|
|
Amendment
|
$290,718.82
|
FIL5
|
Funding Increment Increase
|
11/01/2022
|
11/01/2022
|
|
|
Amendment
|
$0.00
|
DC033A
|
Groundwater Monitoring
|
10/31/2022
|
10/31/2022
|
|
|
Amendment
|
$0.00
|
DC032A
|
"Operations and maintenance + groundwater monitoring"
|
10/17/2022
|
10/17/2022
|
|
|
Amendment
|
$0.00
|
HW008A
|
PFAS sampling
|
10/17/2022
|
10/17/2022
|
|
|
Amendment
|
$0.00
|
SA203
|
ENTER IN ERROR
|
10/07/2022
|
10/07/2022
|
|
|
Amendment
|
$0.00
|
HW004A
|
Soil sampling and ISR work plan
|
08/04/2022
|
08/04/2022
|
|
|
Amendment
|
$0.00
|
DC005B
|
Supplemental site assessment
|
08/04/2022
|
08/04/2022
|
|
|
Amendment
|
$0.00
|
DC010B
|
Site Assessment
|
08/02/2022
|
08/02/2022
|
|
|
Amendment
|
$0.00
|
DC031A
|
Supplemental site assessment
|
08/01/2022
|
08/01/2022
|
|
|
Amendment
|
$0.00
|
DC027A
|
Site Assessment Work Plan
|
07/27/2022
|
07/27/2022
|
|
|
Amendment
|
$0.00
|
DC028A
|
Site Assessment Work Plan
|
07/21/2022
|
07/21/2022
|
|
|
Amendment
|
$0.00
|
DC026A
|
Site Assessment Work Plan
|
07/21/2022
|
07/21/2022
|
|
|
Amendment
|
$0.00
|
DC030A
|
Annual groundwater monitoring
|
07/19/2022
|
07/19/2022
|
|
|
Amendment
|
$0.00
|
DC029A
|
Groundwater monitoring
|
07/19/2022
|
07/19/2022
|
|
|
Amendment
|
$0.00
|
DC009B
|
Initial site assessment
|
07/15/2022
|
07/15/2022
|
|
|
Amendment
|
$2,200,000.00
|
FIL4
|
Funding Increment Increase
|
07/14/2022
|
07/14/2022
|
|
|
Amendment
|
$0.00
|
DC025A
|
Supplemental site assessment
|
06/29/2022
|
06/29/2022
|
|
|
Amendment
|
$0.00
|
DC024A
|
Supplemental site assessment
|
06/29/2022
|
06/29/2022
|
|
|
Amendment
|
$0.00
|
HW003A
|
Site transfer to new contractor
|
06/29/2022
|
06/29/2022
|
|
|
Amendment
|
$0.00
|
DC017A
|
Groundwater monitoring
|
06/23/2022
|
06/23/2022
|
|
|
Amendment
|
$0.00
|
DC013A
|
Operation and maintenance (12 months)
|
06/23/2022
|
06/23/2022
|
|
|
Amendment
|
$0.00
|
DC016A
|
Operation and maintenance (12 months)
|
06/23/2022
|
06/23/2022
|
|
|
Amendment
|
$0.00
|
DC022A
|
Operation and maintenance (12 months)
|
06/23/2022
|
06/23/2022
|
|
|
Amendment
|
$0.00
|
DC021A
|
Operation and maintenance (12 months)
|
06/23/2022
|
06/23/2022
|
|
|
Amendment
|
$0.00
|
DC020A
|
Groundwater monitoring
|
06/22/2022
|
06/22/2022
|
|
|
Amendment
|
$0.00
|
DC018A
|
Groundwater Monitoring
|
06/22/2022
|
06/22/2022
|
|
|
Amendment
|
$0.00
|
DC023A
|
Site assessment
|
06/22/2022
|
06/22/2022
|
|
|
Amendment
|
$0.00
|
DC019A
|
Groundwater monitoring
|
06/22/2022
|
06/22/2022
|
|
|
Amendment
|
$0.00
|
DC015A
|
Operation and maintenance (12 months)
|
06/22/2022
|
06/22/2022
|
|
|
Amendment
|
$350,000.00
|
FIL3
|
Funding Increment Increase
|
06/21/2022
|
06/21/2022
|
|
|
Amendment
|
$0.00
|
HW002A
|
Annual Groundwater Sampling
|
06/21/2022
|
06/21/2022
|
|
|
Amendment
|
$0.00
|
DC012A
|
Annual Groundwater Monitoring
|
06/14/2022
|
06/14/2022
|
|
|
Amendment
|
$0.00
|
DC014A
|
Prepare interim source removal plan
|
06/14/2022
|
06/14/2022
|
|
|
Amendment
|
$0.00
|
DC008B
|
Annual operation and maintenance
|
06/14/2022
|
06/14/2022
|
|
|
Amendment
|
$0.00
|
DC003B
|
Interim source removal implementation
|
06/13/2022
|
06/13/2022
|
|
|
Amendment
|
$0.00
|
DC06ACO1
|
Authorize soil erosion control
|
06/02/2022
|
06/02/2022
|
|
|
Amendment
|
$0.00
|
DC011A
|
Six months of operation and maintenance
|
05/23/2022
|
05/23/2022
|
|
|
Amendment
|
$0.00
|
DC010A
|
Site Assessment Work Plan
|
05/23/2022
|
05/23/2022
|
|
|
Amendment
|
$0.00
|
DC009A
|
Site Assessment Work Plan
|
05/12/2022
|
05/12/2022
|
|
|
Amendment
|
$0.00
|
DC001C
|
Annual contractor workshop
|
05/12/2022
|
05/12/2022
|
|
|
Amendment
|
$369,583.70
|
FIL2
|
Funding Increment Increase
|
05/02/2022
|
05/02/2022
|
|
|
Amendment
|
$0.00
|
DOD01
|
technical report reviews for FPS
|
04/20/2022
|
04/20/2022
|
|
|
Amendment
|
$0.00
|
DC001B
|
Annual site review meeting
|
04/18/2022
|
04/18/2022
|
|
|
Amendment
|
$0.00
|
HW001A
|
Supplemental site assessment
|
04/14/2022
|
04/14/2022
|
|
|
Amendment
|
$0.00
|
DC008A
|
Site transition activities
|
03/29/2022
|
03/29/2022
|
|
|
Amendment
|
$0.00
|
DC007A
|
Well installation and groundwater monitoring
|
03/16/2022
|
03/16/2022
|
|
|
Amendment
|
$0.00
|
DC006A
|
File review and site visit
|
03/08/2022
|
03/08/2022
|
|
|
Amendment
|
$0.00
|
DC005A
|
Additional assessment work plan
|
02/10/2022
|
02/10/2022
|
|
|
Amendment
|
$0.00
|
DC004A
|
Biennial groundwater monitoring
|
02/08/2022
|
02/08/2022
|
|
|
Amendment
|
$0.00
|
DC03A
|
File review, site visit, File review letter report
|
01/24/2022
|
01/24/2022
|
|
|
Amendment
|
$0.00
|
DC02A
|
File review, site visit, Site Assessment Work Plan
|
01/21/2022
|
01/21/2022
|
|
|
Amendment
|
$1,330,416.30
|
FIL1
|
Funding Increment Increase
|
01/20/2022
|
01/20/2022
|
|
|
Amendment
|
$0.00
|
DC001A
|
Critical Response
|
01/10/2022
|
01/10/2022
|
|