| More |
Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
Professional engineering services
|
Task DC007A: (Subtask 2): Submittal and FDEP approval of the groundwater monitoring field documentat...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task DC007A: (Subtask 2): Submittal and FDEP approval of the groundwater monitoring field documentation and laboratory report; IDW disposal documentation $5,618.77; (Subtasks 1 & 3): Submittal and FDEP approval of the Annual Groundwater Monitoring Report; ADaPT/GIS update; Project Management $2,361.12.
|
| Deliverable Price: $7,979.89 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance to the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: DC007A |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task DC008A: Submittal and FDEP approval of the Groundwater monitoring/ soil sampling field document...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task DC008A: Submittal and FDEP approval of the Groundwater monitoring/ soil sampling field documentation and laboratory report; IDW disposal documentation (Subtask 2) - $11,965.73; Submittal and FDEP approval of the Supplemental Assessment Report; ADaPT/GIS update; Project Management (Subtasks 1 & 3) - $5,398.22.
|
| Deliverable Price: $17,363.95 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance to the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: DC008A |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Deliverables are assigned by Task Assignments
under the Master Agreement.
|
No Cost
|
| Major Deliverable: Deliverables are assigned by Task Assignments
under the Master Agreement.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Agreement without a financial exchange or impact |
| Performance Metrics: All work must be in accordance with the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task SA181: FDEP Approval of Field Notes Package ($9,654.23) - Subtasks 2-4; FDEP Approval of Projec...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task SA181: FDEP Approval of Field Notes Package ($9,654.23) - Subtasks 2-4; FDEP Approval of Project Management ($1,791.83) and Supplemental Site Assessment Report ($5,584.13) - Subtasks 1 & 5.
|
| Deliverable Price: $17,030.19 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance with the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: SA181 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task DC008B: Submittal of documentation Pre-Construction Activities including daily logs, excavation...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task DC008B: Submittal of documentation Pre-Construction Activities including daily logs, excavation volumes, weight tickets, manifests, and photographs of final site conditions Subtask 2; AND Contaminated soil removal subtask 3 $14,546.94 ; Submittal of the Interim Source Removal Report Subtask 4 ; AND Project Management Subtask 1 $3,123.30.
|
| Deliverable Price: $17,670.24 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance to the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: DC008B |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task DC014A: Subtasks 1 & 2: Upon submittal and FDEP approval of the Site Assessment Work Plan + Pro...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task DC014A: Subtasks 1 & 2: Upon submittal and FDEP approval of the Site Assessment Work Plan + Project Management $5,000.
|
| Deliverable Price: $5,000.00 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance to the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: DC014A |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task DC013A: Subtasks 1 & 2: Upon submittal and FDEP approval of the Site Assessment Work Plan + Pro...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task DC013A: Subtasks 1 & 2: Upon submittal and FDEP approval of the Site Assessment Work Plan + Project Management $5,000.
|
| Deliverable Price: $5,000.00 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance to the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: DC013A |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task DC005B: Submittal and FDEP approval of the SRC Report including; GW sampling field documentatio...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task DC005B: Submittal and FDEP approval of the SRC Report including; GW sampling field documentation and IDW manifest; Project management. Subtask 1,2, and 3. Total task amount $8,739.04.
|
| Deliverable Price: $8,739.04 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance to the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: DC005B |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task DC010A: Task DC010A: Subtask 2: Submittal and FDEP approval of the Construction plan review/ si...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task DC010A: Task DC010A: Subtask 2: Submittal and FDEP approval of the Construction plan review/ site visit documentation $1,575.84 ; Subtasks 1 & 3: Submittal and FDEP approval of the Construction Observation documentation. Project management $2,370.89; Subtask 4: Submittal and FDEP approval of the letter report deliverable documenting the re-piping for the Haines City site $4,966.43.
CO1: Cost increase |
| Deliverable Price: $8,913.16 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance to the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: CO1 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task SA190: Subtask 1 - Project Management ($1,451.44); Subtask 2 - Field Documentation ($16,144.88)...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task SA190: Subtask 1 - Project Management ($1,451.44); Subtask 2 - Field Documentation ($16,144.88).
|
| Deliverable Price: $17,596.32 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance with the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: SA190 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task SA191: Subtask 1 - Project Management ($1,203.59); Subtasks 2 through 5 - Field Documentation a...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task SA191: Subtask 1 - Project Management ($1,203.59); Subtasks 2 through 5 - Field Documentation and Supplemental Site Assessment Report ($20,076.33). |
| Deliverable Price: $21,279.92 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance with the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: SA191 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task HW002A: Subtasks 1 & 2 Submittal and FDEP approval of the Groundwater Monitoring Report and PFA...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task HW002A: Subtasks 1 & 2 Submittal and FDEP approval of the Groundwater Monitoring Report and PFAS Summary, IDW manifest AND PM - $9,142.68; Subtask 3 Submittal and FDEP approval of the PFAS Email Summary - $1,298.51.
|
| Deliverable Price: $10,441.19 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance to the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: HW002A |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task SA204: Subtask 1 - Project Management ($1,488.74); Subtask 2 - Field Documentation ($16,431.83)...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task SA204: Subtask 1 - Project Management ($1,488.74); Subtask 2 - Field Documentation ($16,431.83).
|
| Deliverable Price: $17,920.57 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance with the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: SA204 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task DC004B: Subtasks 1,2&3: Submittal and FDEP approval of the Updated groundwater analytical tabl...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task DC004B: Subtasks 1,2&3: Submittal and FDEP approval of the Updated groundwater analytical tables, updated maps, RAE screening matrix table and meeting notes from the teleconference between the FDEP and PSI & PM $17,168.84.
|
| Deliverable Price: $17,168.84 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance to the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: DC004B |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task HW013A: Subtasks 1 & 2 Submittal and FDEP approval of the PFAS email deliverable & Project Mana...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task HW013A: Subtasks 1 & 2 Submittal and FDEP approval of the PFAS email deliverable & Project Management $2,536.81.
CO1: Task time extension. |
| Deliverable Price: $2,536.81 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance to the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: CO1 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task SA187: Subcontractor invoices and weight tickets for purge water disposal - Subtask 1-Project ...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task SA187: Subcontractor invoices and weight tickets for purge water disposal - Subtask 1-Project Management ($960.63) and Subtask 2-5 ($32,307.77). Total task amount = $33,268.40.
CO1: Cost reduction.
|
| Deliverable Price: $33,268.40 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance with the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: CO1 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task DC009C: FDEP Approval of Supplemental Site Assessment – Groundwater Monitoring Well Installatio...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task DC009C: FDEP Approval of Supplemental Site Assessment – Groundwater Monitoring Well Installation Report - Subtasks 1-4 = $15,884.63.
|
| Deliverable Price: $15,884.63 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance to the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: DC009C |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task DC002A: FDEP approval of Quarter 1 Equipment Storage Status Report - Subtasks 2 and 3 - $13,634...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task DC002A: FDEP approval of Quarter 1 Equipment Storage Status Report - Subtasks 2 and 3 - $13,634.68; FDEP approval of Quarter 2 Equipment Storage Status Report - Subtask 4 - $11,336.28; FDEP approval of Quarter 4 Equipment Storage Status Report - Subtask 5 - $11,336.28; FDEP approval of Quarter 4 Equipment Storage Status Report and Project Management - Subtasks 1 and 6 - $14,121.33
CO1:change the names of the quarterly deliverables |
| Deliverable Price: $50,428.57 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance to the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: DC002A CO1 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task DC006A: FDEP approval of Operation and maintenance (O&M) email submittal including field docume...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task DC006A: FDEP approval of Operation and maintenance (O&M) email submittal including field documentation, laboratory reports, and tables - Subtask 2, $3,202.71. FDEP approval of O&M email submittal including field documentation, laboratory reports, and tables - Subtask 3, $3445.04. FDEP approval of Remedial Action Status Report, ADaPT/GIS updates, and Project Management - Subtasks 1, 5, and 6 $9169.22. FDEP receipt of utility invoices for 6 months; Utilities (Cost Plus Fixed Fee) = not to exceed $3,420; Utilities Handling Fee = $240 - Subtask 4 $3660.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: All work must be in accordance to the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: DC006A |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task DC009A: Q1 and Q2 - Quarterly O&M email submittals including field documentation, laboratory re...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task DC009A: Q1 and Q2 - Quarterly O&M email submittals including field documentation, laboratory reports, and tables - Subtasks 2 and 3; AND Remedial Action Status Report - Subtask 4 $17,575.74; Q3 and Q4 - Quarterly O&M email submittals including field documentation, laboratory reports, and tables - Subtasks 5 and 6; AND Annual Remedial Action Status Report, ADaPT/GIS, and Project Management - Subtasks 1, 7, and 9 $30,726.16; FDEP receipt of utility invoices for 12 months; Utilities (Cost Plus Fixed Fee) = not to exceed $5,640; Utilities Handling Fee = $480 - Subtask 8 $6120 |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: All work must be in accordance to the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: DC009A |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task DC001C: The signature of the 2 staff members in attendance on workshop sign in and sign out she...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task DC001C: The signature of the 2 staff members in attendance on workshop sign in and sign out sheets $4,500.00
|
| Deliverable Price: $4,500.00 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance to the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: DC001C |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task DC001B: Submittal and FDEP approval of the meeting minutes and project management $10,622.28
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task DC001B: Submittal and FDEP approval of the meeting minutes and project management $10,622.28
|
| Deliverable Price: $10,622.28 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance to the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: DC001B |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task SA180: Completion of field activities-Field notes, GW sampling logs, COCs, photos (Subtask 1-Pr...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task SA180: Completion of field activities-Field notes, GW sampling logs, COCs, photos (Subtask 1-Project Management ($1,492.00) and Subtask 2-Groundwater Sampling ($16,456.91) |
| Deliverable Price: $17,948.91 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance with the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed. |
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract. |
| Source Documentation Page Reference: SA180 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task DC015A: Subtasks 1 & 2: Upon submittal and FDEP approval of the Site Assessment Work Plan + Pro...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task DC015A: Subtasks 1 & 2: Upon submittal and FDEP approval of the Site Assessment Work Plan + Project Management $5,000
|
| Deliverable Price: $5,000.00 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance to the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: DC015A |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task DC012A: Subtasks 1 & 2: Submittal and FDEP approval of the Annual Groundwater Monitoring
Report...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Task DC012A: Subtasks 1 & 2: Submittal and FDEP approval of the Annual Groundwater Monitoring
Report including field documentation and laboratory report; IDW disposal documentation; ADaPT update; Project Management $4,488.69.
|
| Deliverable Price: $4,488.69 |
| Non Price Justification: |
| Performance Metrics: All work must be in accordance to the Contract, the Standard Operating Procedures and the terms and conditions referenced in the Task Assignment. The Contractor represents that its services shall be performed in a manner consistent with the level of care and skill ordinarily exercised by other professional consultants under similar circumstances at the time the services are performed.
|
| Financial Consequences: Failure to implement any of the terms and conditions of this Task Assignment shall be considered a breach of contract and shall subject the Contractor to cancellation of this Task Assignment, loss of payment, or termination of the Contract.
|
| Source Documentation Page Reference: DC012A |
| Deliverable Number: |
|