| More |
Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
Hazardous waste disposal
|
Contractor shall provide the services specified in the work assignments by Work Authorization Form (...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Contractor shall provide the services specified in the work assignments by Work Authorization Form (WAF)/Supplemental Form (WASF) (“Work Authorization”). Rates listed in attachment B.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: Attachment B |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 2022-4I-69023: 30 gallons used oil in ditch, not to exceed $5,425.
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 2022-4I-69023: 30 gallons used oil in ditch, not to exceed $5,425.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely.
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: 4I-69023 |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 2022-4I-68982: 55-gallon drum gasoline/water, not to exceed $2,000.
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 2022-4I-68982: 55-gallon drum gasoline/water, not to exceed $2,000.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely.
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: 4I-68982 |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 2022-2I-69330: Spill response motor oil, not to exceed $5,000.
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 2022-2I-69330: Spill response motor oil, not to exceed $5,000.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely.
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: 2I-69330 |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 2023-2I-70222Z: Respond to 500-gallon poly tank for disposal, contents unknown liquid, not to e...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 2023-2I-70222Z: Respond to 500-gallon poly tank for disposal, contents unknown liquid, not to exceed $3,000.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely.
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: 2I-70222Z |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Deploy vac truck and tanker to the Piney Point site in Manatee Co. -remove and dispose of 24,000 ga...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Deploy vac truck and tanker to the Piney Point site in Manatee Co. -remove and dispose of 24,000 gallons wastewater, not to exceed $24,000. |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely |
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform. |
| Source Documentation Page Reference: 21-0323 |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 3C-69543: Fuel on waterbody of canal may require pressure washing of bulkheads and debris ( oil...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 3C-69543: Fuel on waterbody of canal may require pressure washing of bulkheads and debris ( oily boom and pads, palm frons and coconuts)removal, not to exceed $5,000 (FD091).
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: Attachment B |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 3I-69046: Respond to Muratic acid spill to remove damaged one gallon containers, not to exceed ...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 3I-69046: Respond to Muratic acid spill to remove damaged one gallon containers, not to exceed $6,500.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: Attachment B |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 2I-70535: spill response, pool chemicals, not to exceed $5,000.
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 2I-70535: spill response, pool chemicals, not to exceed $5,000.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: Attachment B |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
2I-70825-drum assessment, unk petroleum, not to exceed $5,000
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: 2I-70825-drum assessment, unk petroleum, not to exceed $5,000
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: Attachment B |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task70660ZS-Supplemental for spill response, diesel 80-gal, not to exceed $600
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task70660ZS-Supplemental for spill response, diesel 80-gal, not to exceed $600
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: Attachment B |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 2I-70747-petroleum spill response, not to exceed $27,000.
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 2I-70747-petroleum spill response, not to exceed $27,000.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: Attachment B |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 2I-70825S- Respond to unknowns, not to exceed $1,674.
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 2I-70825S- Respond to unknowns, not to exceed $1,674.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: Attachment B |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 2024-4I-71565: Waste Oil and Petroleum Contact Water and possibly contaminated soil. 100 gals+...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 2024-4I-71565: Waste Oil and Petroleum Contact Water and possibly contaminated soil. 100 gals+, not to exceed $7,500.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: 4I-71565 |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 2024-4I-71565 (FD096) - Supplemental. Waste Oil and Petroleum Contact Water and possibly conta...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 2024-4I-71565 (FD096) - Supplemental. Waste Oil and Petroleum Contact Water and possibly contaminated soil. 100 gals+, not to exceed $1700.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: 4I71565S |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 2I-71036: Respond to multiple small containers of unknown content not to exceed $6,000.
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 2I-71036: Respond to multiple small containers of unknown content not to exceed $6,000.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: 2I-71036 |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 2023-3I-70660Z: Spill response, diesel 80-gal, not to exceed $5,000.
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 2023-3I-70660Z: Spill response, diesel 80-gal, not to exceed $5,000.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: 3I-70660Z |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 2024-3I-70773: Spill response, not to exceed $13,200
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 2024-3I-70773: Spill response, not to exceed $13,200
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: 3I-70773 |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 2024-4I-70913: Spill response, 50-60 gallons used oil, not to exceed $3,000.
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 2024-4I-70913: Spill response, 50-60 gallons used oil, not to exceed $3,000.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: 4I-70913 |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 2025-3I-72269 - respond and clean up 150-gallon diesel spill, not to exceed $26,000.
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 2025-3I-72269 - respond and clean up 150-gallon diesel spill, not to exceed $26,000.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: 3I-72269 |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 2025-3I-73384 - manage drums and soil clean-up, not to exceed $20734.80.
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 2025-3I-73384 - manage drums and soil clean-up, not to exceed $20734.80.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: 3I-73384 |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task: WAF 2025-2C-72063 - diesel and motor oil spill response and disposal, not to exceed $15,000.
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task: WAF 2025-2C-72063 - diesel and motor oil spill response and disposal, not to exceed $15,000.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: Attachment B |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 2026-2I-73509C - respond, consolidate and transport waste, not to exceed $3,000.
|
Cost Reimbursement
|
| Major Deliverable: Task 2026-2I-73509C - respond, consolidate and transport waste, not to exceed $3,000.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: 2I-73509C |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 2026-2I-73620- 12-drum disposal & spill response, not to exceed $10,000.
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 2026-2I-73620- 12-drum disposal & spill response, not to exceed $10,000.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: Attachment B |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 2026-3I-73584 - clean-up and disposal, not to exceed $13,500.
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 2026-3I-73584 - clean-up and disposal, not to exceed $13,500.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverable will be reviewed and evaluated by the DEP Contract Manager to ensure appropriate documentation reviewed and/or provided and that the documentation submitted is complete, accurate, and submitted timely.
|
| Financial Consequences: No payment will be made for deliverable deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the department, Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, in its sole discretion, terminate the Agreement for failure to perform.
|
| Source Documentation Page Reference: 3I-73584 |
| Deliverable Number: |
|