| More |
Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
ENVIRONMENTAL STUDIES SERVICES &
|
Technical support for restoration planning and natural resource damage assessment activities related...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Technical support for restoration planning and natural resource damage assessment activities related to Deepwater Horizon. Deliverables established on a task assignment basis |
| Deliverable Price: $0.00 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Deliverables reviewed and evaluated by DEP Contract Manager to determine if stated deliverables are complete and have been submitted by due date. |
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the DEP, within 15 days. If a satisfactory deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the contract for failure to perform. |
| Source Documentation Page Reference: Attachment A |
| Deliverable Number: |
|
|
|
|
ENVIRONMENTAL STUDIES SERVICES &
|
TA#1, Subtask 2 - Specific deliverables/timelines outlined in weekly meeting emails. Invoicing month...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA#1, Subtask 2 - Specific deliverables/timelines outlined in weekly meeting emails. Invoicing monthly for deliverables submitted that month. Potential subtask deliverables - written comments, participation in teleconferences, presentations of projects. Fee Schedule Max - $15,970. Authorized Labor categories: Berenguel - $62.22/hr.; Callow-$121.37/hr.; $Donahue-$84.30/hr.; Ebbets-$84.30/hr.; Jones,R.-$156.57/hr. Lipton-$68.39/hr.; Leahy-$60.05/hr.; Maloney-$63.66/hr.; Mills-$156.57/hr.; Miles-$63.66/hr.; Quinn-$78.18/hr.; Ritter-$156.57/hr.; Rising-$68.39/hr.; Steeter-$103.51/hr.; Visser-$88.10/hr. |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables reviewed and evaluated by DEP Contract Manager to determine if stated deliverables are complete and submitted by due date. |
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the DEP, within 15 days. If a satisfactory deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the contract for failure to perform. |
| Source Documentation Page Reference: Contract, A1-A3 and TA1 |
| Deliverable Number: |
|
|
|
|
ENVIRONMENTAL STUDIES SERVICES &
|
TA#1, Subtask 3 - Specific deliverables/timelines outlined in weekly meeting emails. Invoicing month...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA#1, Subtask 3 - Specific deliverables/timelines outlined in weekly meeting emails. Invoicing monthly for deliverables submitted that month. Potential subtask deliverables- quantitative estimates of potential ecological services, presentations, participation in discussions of offset for Florida projects, participation in Early Restoration offset discussions. Fee Schedule Max - $11,273. Authorized Labor categories: Berenguel - $62.22/hr.; Callow-$121.37/hr.; $Donahue-$84.30/hr.; Ebbets-$84.30/hr.; Jones,R.-$156.57/hr. Lipton-$68.39/hr.; Leahy-$60.05/hr.; Maloney-$63.66/hr.; Mills-$156.57/hr.; Miles-$63.66/hr.; Quinn-$78.18/hr.; Ritter-$156.57/hr.; Rising-$68.39/hr.; Steeter-$103.51/hr.; Visser-$88.10/hr. |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables reviewed and evaluated by DEP Contract Manager to determine if stated deliverables are complete and submitted by due date. |
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the DEP, within 15 days. If a satisfactory deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the contract for failure to perform. |
| Source Documentation Page Reference: Contract A1-A3 & TA1 |
| Deliverable Number: |
|
|
|
|
ENVIRONMENTAL STUDIES SERVICES &
|
TA#1, Subtask 4 - Specific deliverables/timelines outlined in weekly meeting emails. Invoicing month...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA#1, Subtask 4 - Specific deliverables/timelines outlined in weekly meeting emails. Invoicing monthly for deliverables submitted that month. Potential subtask deliverables - participation in phone conferences or in-person meetings for project negotiations, presentations, responses to counter-offers, verbal or written summaries. Fee Schedule Max - $4,697. Authorized Labor categories: Berenguel - $62.22/hr.; Callow-$121.37/hr.; $Donahue-$84.30/hr.; Ebbets-$84.30/hr.; Jones,R.-$156.57/hr. Lipton-$68.39/hr.; Leahy-$60.05/hr.; Maloney-$63.66/hr.; Mills-$156.57/hr.; Miles-$63.66/hr.; Quinn-$78.18/hr.; Ritter-$156.57/hr.; Rising-$68.39/hr.; Steeter-$103.51/hr.; Visser-$88.10/hr. |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables reviewed and evaluated by DEP Contract Manager to determine if stated deliverables are complete and submitted by due date. |
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the DEP, within 15 days. If a satisfactory deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the contract for failure to perform. |
| Source Documentation Page Reference: Contract, A1-A3, & TA1 |
| Deliverable Number: |
|
|
|
|
ENVIRONMENTAL STUDIES SERVICES &
|
TA#1, Subtask 6 - Specific deliverables/timelines outlined in weekly meeting emails. Invoicing month...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA#1, Subtask 6 - Specific deliverables/timelines outlined in weekly meeting emails. Invoicing monthly for deliverables submitted that month. Potential subtask deliverables - drafts of potential project plans, support at review sessions, electronic database of potential projects, evaluation of potential projects, public documents to support project selection, draft/final monitoring plans. Fee Schedule Max - $84,314. Authorized Labor categories: Berenguel - $62.22/hr.; Callow-$121.37/hr.; $Donahue-$84.30/hr.; Ebbets-$84.30/hr.; Jones,R.-$156.57/hr. Lipton-$68.39/hr.; Leahy-$60.05/hr.; Maloney-$63.66/hr.; Mills-$156.57/hr.; Miles-$63.66/hr.; Quinn-$78.18/hr.; Ritter-$156.57/hr.; Rising-$68.39/hr.; Steeter-$103.51/hr.; Visser-$88.10/hr. |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables reviewed and evaluated by DEP Contract Manager to determine if stated deliverables are complete and submitted by due date. |
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the DEP, within 15 days. If a satisfactory deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the contract for failure to perform. |
| Source Documentation Page Reference: Contract, A1-A3 and TA1 |
| Deliverable Number: |
|
|
|
|
ENVIRONMENTAL STUDIES SERVICES &
|
TA#1, Subtask 1 - Specific deliverables/timelines outlined in weekly meeting emails. Invoicing month...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA#1, Subtask 1 - Specific deliverables/timelines outlined in weekly meeting emails. Invoicing monthly for deliverables submitted that month. Potential subtask deliverables participation in phone calls, written comments & summaries, attendance at Council meetings. Fee Schedule Max $21,438/Cost Reimbursement for Travel Max $18,775. Authorized Labor categories: Berenguel - $62.22/hr.; Callow-$121.37/hr.; $Donahue-$84.30/hr.; Ebbets-$84.30/hr.; Jones,R.-$156.57/hr. Lipton-$68.39/hr.; Leahy-$60.05/hr.; Maloney-$63.66/hr.; Mills-$156.57/hr.; Miles-$63.66/hr.; Quinn-$78.18/hr.; Ritter-$156.57/hr.; Rissing-$68.39/hr.; Steeter-$103.51/hr.; Visser-$88.10/hr. |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables reviewed and evaluated by DEP Contract Manager to determine if stated deliverables are complete and submitted by due date. |
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the DEP, within 15 days. If a satisfactory deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the contract for failure to perform. |
| Source Documentation Page Reference: Contract, A1-A3 and TA1 |
| Deliverable Number: |
|
|
|
|
ENVIRONMENTAL STUDIES SERVICES &
|
TA#1, Subtask 5 - Specific deliverables/timelines outlined in weekly meeting emails. Invoicing month...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA#1, Subtask 5 - Specific deliverables/timelines outlined in weekly meeting emails. Invoicing monthly for deliverables submitted that month. Potential subtask deliverables - text, figures, or image; participation in calls for environmental compliance, draft/final versions of restoration plans, public presentations materials, responses to public comments, information for BP reporting. Fee Schedule Max - $299,217. Authorized Labor categories: Berenguel - $62.22/hr.; Callow-$121.37/hr.; $Donahue-$84.30/hr.; Ebbets-$84.30/hr.; Jones,R.-$156.57/hr. Lipton-$68.39/hr.; Leahy-$60.05/hr.; Maloney-$63.66/hr.; Mills-$156.57/hr.; Miles-$63.66/hr.; Quinn-$78.18/hr.; Ritter-$156.57/hr.; Rissing-$68.39/hr.; Steeter-$103.51/hr.; Visser-$88.10/hr. |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables reviewed and evaluated by DEP Contract Manager to determine if stated deliverables are complete and submitted by due date. |
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the DEP, within 15 days. If a satisfactory deliverable is not submitted within the specified timeframe, the DEP may, at its sole discretion, terminate the contract for failure to perform. |
| Source Documentation Page Reference: Contract, A1-A3 and TA1 |
| Deliverable Number: |
|