Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
ENVIRONMENTAL CLEANUP AND RESTORATION
|
Task Assignments Completed and Closed Prior to FACTS.
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task Assignments Completed and Closed Prior to FACTS. |
| Deliverable Price: $2,875,037.81 |
| Non Price Justification: |
| Performance Metrics: Deliverables reviewed to ensure compliance with specifications in task assignment and applications complete. |
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that deliverable is deemed unsatisfactory, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department. Contract can be terminated for failure to perform. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
ENVIRONMENTAL CLEANUP AND RESTORATION
|
P.E. services for the reclamation and mitigation of the Upper Peace River Watershed. Deliverables wi...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: P.E. services for the reclamation and mitigation of the Upper Peace River Watershed. Deliverables will be established on a task assignment basis. |
| Deliverable Price: $0.00 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Deliverables will be reviewed to ensure compliance with specifications in task assignment and contract scope of services. |
| Financial Consequences: No payment for unsatisfactory services/deliverables. Contract can be terminated for failure to perform. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
ENVIRONMENTAL CLEANUP AND RESTORATION
|
Task 60(2.38): Routine Field Inspections, Professional Engineering signed and sealed certifications,...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: Task 60(2.38): Routine Field Inspections, Professional Engineering signed and sealed certifications, Contractor coordination activities and construction modifications, and Administrative Support.Eligible cost categories: salaries, subcontracts, and expenses. |
| Deliverable Price: $100,000.00 |
| Non Price Justification: |
| Performance Metrics: Deliverable reviewed to ensure specifications in scope have been met. |
| Financial Consequences: No payment will be made for unsatisfactory deliverables. In the event that deliverable is deemed unsatisfactory, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department. Contract can be terminated for failure to perform. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
ENVIRONMENTAL STUDIES SERVICES &
|
TA#62 (2.40) - GIS File conversions for Phase III-A. Deliverables - GIS files for Phase III-A plant...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA#62 (2.40) - GIS File conversions for Phase III-A. Deliverables - GIS files for Phase III-A planting plans for all seven areas. Professional opinions for meetings related to the Tri-City Landfill Closure. Change Orders 1 & 2 added time. Eligible cost categories: salaries, subcontracts, and expenses. CO3- decreased funding. |
| Deliverable Price: $5,509.51 |
| Non Price Justification: |
| Performance Metrics: Deliverables reviewed to ensure compliance with Task Assignment specifications. |
| Financial Consequences: No payment for unsatisfactory deliverables. Contract can be terminated for failure to perform. |
| Source Documentation Page Reference: Task Assignment 62 (2.40) |
| Deliverable Number: |
|
|
|
|
ENVIRONMENTAL CLEANUP AND RESTORATION
|
Task 63(2.41): (st1) Field Investigation Report and a proposed additional survey requirements summa...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 63(2.41): (st1) Field Investigation Report and a proposed additional survey requirements summary memo $12,600. (st2) Three draft conceptual design plans and Net Meetings with FDEP with FDEP providing meeting minutes $22,700. (st3) Draft structure plans including locations, geometric configuration of the structures, and preliminary costs; preliminary weir and pipe sizes ; aerial maps showing proposed configuration and ICPR node-link diagram; technical memo describing the modeling process; and copy of the field sheets from the geotechnical field work $12,600. (st4) Map of existing topography and proposed topographic design map; structure placement and specification; cut and fill calculations with drawings; 60% Plan set of all drawings by AMEC to include cover sheet, general notes, clearing plan, earth moving plan, planting plan, plating tables, structure details, and misc details; minimal labeling; preliminary construction cost estimates, and a final geotechnical report $34,700. (st5) Design plan sets; construction specifications (methods, materials and cost estimates) presented in the format required to assist in bidding; provide FDEP with post construction land use GIS shape files, and final design report $26,300. |
| Deliverable Price: $108,900.00 |
| Non Price Justification: |
| Performance Metrics: Deliverable reviewed to ensure all required elements included. |
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Consultant shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified timeframe with Department may, in its sole discretion, terminate the Contract for failure to perform. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
ENVIRONMENTAL STUDIES SERVICES &
|
Task 65(2.43): Excell spreadsheet with post-processed logger data and stage-discharge rating curve,...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 65(2.43): Excell spreadsheet with post-processed logger data and stage-discharge rating curve, memo describing data collection efforts and results. |
| Deliverable Price: $14,566.00 |
| Non Price Justification: |
| Performance Metrics: Delverable reviewed to ensure technical review completed and findings reported. |
| Financial Consequences: No payment for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, at its sole discretion, terminate the contract for failure to perform. |
| Source Documentation Page Reference: T65-2.43 |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 67(2.45): (st.12) Gopher Tortoise Relocation Permit Applications and summary of relocation eff...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 67(2.45): (st.12) Gopher Tortoise Relocation Permit Applications and summary of relocation efforts $17,600. (st 13) Summary of consultation meetings, one copy of all written communications and summary of telephone conversationsbetween AMEC and USFWS $3.700. |
| Deliverable Price: $21,300.00 |
| Non Price Justification: |
| Performance Metrics: Deliverable reviewed to ensure technical review completed and findings reported. |
| Financial Consequences: No payment for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, at its sole discretion, terminate the contract for failure to perform. |
| Source Documentation Page Reference: T67(2.45) |
| Deliverable Number: |
|
|
|
|
Hazardous waste disposal
|
Task 66(2.44): Permitting and bidding process for the designed 34.28 acres of herbaceous wetlands, ...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 66(2.44): Permitting and bidding process for the designed 34.28 acres of herbaceous wetlands, 14.38 acres of forested wetlands at Chicora Tract on the South Prong of the Alafia River. The Bid Document in Word and PDF format; signed and sealed permit application forms and required support data; construction plans in PDF, AutoCAD, and meeting minutes from Public meeting and Bid Site meeting. |
| Deliverable Price: $16,320.00 |
| Non Price Justification: |
| Performance Metrics: Deliverable reviewed to ensure technical review completed and findings reported. |
| Financial Consequences: No payment for unsatisfactory deliverable. In the event that a deliverable is deemed unsatisfactory, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, at its sole discretion, terminate the contract for failure to perform. |
| Source Documentation Page Reference: Attachment A |
| Deliverable Number: |
|
|
|
|
Environmental advisory services
|
Task 64(2.42): Listed Species Investigation Report and a proposed additional survey requirements su...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 64(2.42): Listed Species Investigation Report and a proposed additional survey requirements summary memo.
Due 06/30/14 |
| Deliverable Price: $4,400.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables reviewed to ensure technical review completed and findings reported. |
| Financial Consequences: No payment for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Contractor shall re-perfom the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 15 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, at its sole discretion, terminate the contract for failure to perform. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Environmental advisory services
|
Task 64(2.42): Gopher Tortoise survey report.
Due 06/30/2014
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 64(2.42): Gopher Tortoise survey report.
Due 06/30/2014 |
| Deliverable Price: $9,500.00 |
| Non Price Justification: |
| Performance Metrics: Deliverable reviewed to ensure technical review completed and findings reported. |
| Financial Consequences: No payment for unsatisfactory deliverable. In the event that a deliverable is deemed unsatisfactory, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, at its sole discretion, terminate the contract for failure to perform. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Environmental advisory services
|
Task 64(2.42): Florida Sand Sink Pedestrian survey report. Due 06/30/2014
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 64(2.42): Florida Sand Sink Pedestrian survey report. Due 06/30/2014 |
| Deliverable Price: $1,700.00 |
| Non Price Justification: |
| Performance Metrics: Deliverable reviewed to ensure technical review completed and findings reported. |
| Financial Consequences: No payment for unsatisfactory deliverable. In the event that a deliverable is deemed unsatisfactory, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department, within 20 days. If a satisfactory deliverable is not submitted within the specified timeframe, the Department may, at its sole discretion, terminate the contract for failure to perform. |
| Source Documentation Page Reference: |