| More |
Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
Professional engineering services
|
Task 1: The Florida Department of Environmental Protection (Department) intends to contract with the...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1: The Florida Department of Environmental Protection (Department) intends to contract with the Association of State Dam Safety Officials, Inc. (ASDSO), to provide professional dam safety training. Training events include Dam Owner Workshops and Technical Seminars. Dam Owner Workshops are intended to provide dam safety training tailored to the needs of dam owners and operators. A) Dan Owner Workshops B) Technical Seminars C) Customized Training.
|
| Deliverable Price: $10,000.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T1 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 2: The Florida Department of Environmental Protection (Department) intends to contract with the...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 2: The Florida Department of Environmental Protection (Department) intends to contract with the Association of State Dam Safety Officials, Inc. (ASDSO), to provide professional dam safety training. Training events include Dam Owner Workshops and Technical Seminars. Dam Owner Workshops are intended to provide dam safety training tailored to the needs of dam owners and operators. A) Dan Owner Workshops B) Technical Seminars C) Customized Training.
|
| Deliverable Price: $38,127.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T2 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task: 3The Florida Department of Environmental Protection (Department) intends to contract with the ...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task: 3The Florida Department of Environmental Protection (Department) intends to contract with the Association of State Dam Safety Officials, Inc. (ASDSO), to provide professional dam safety training. Training events include Dam Owner Workshops and Technical Seminars. Dam Owner Workshops are intended to provide dam safety training tailored to the needs of dam owners and operators. A) Dan Owner Workshops B) Technical Seminars C) Customized Training
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: T3 |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
Task 4 - Task 1: 1) ASDSO will provide a coordination meeting summary, attendee log, final agenda, t...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 4 - Task 1: 1) ASDSO will provide a coordination meeting summary, attendee log, final agenda, training
recording, and presentations to FDEP. And 2) Certificates of Completion/Professional Development Hours
to attendees. ASDSO will provide the 2026 Florida Dam Safety Program Dam Owner Workshop, Operation and
Maintenance. The workshop will be held before June 30, 2026 in a virtual format by a qualified instructor. See the attached scope of services.
|
| Deliverable Price: $12,000.00 |
| Non Price Justification: |
| Performance Metrics: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to Department, within fifteen (15) days of being notified of the unsatisfactory deliverable. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion: 1) assess liquidated damages if specified in the Contract or its attachments; 2) request from the Contractor agreement to a reduction in the amount payable; 3) suspend all Work until satisfactory performance is achieved, or 4) terminate the Contract for failure to perform.
|
| Source Documentation Page Reference: Pgs 1-2 |
| Deliverable Number: |
|