| More |
Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 1: i. A map showing the location of accumulated debris within the assigned wastewate...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 1: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and ii. Calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $21,882.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T1 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 2: i. A map showing the location of accumulated debris within the assigned wastewate...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 2: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and ii. Calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $58,955.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T2 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 5: i. A map showing the location of accumulated debris within the assigned wastewate...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 5: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and ii. Calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $55,070.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T5 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 6: i. A map showing the location of accumulated debris within the assigned wastewate...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 6: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and ii. Calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $38,450.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T6 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 7: i. A map showing the location of accumulated debris within the assigned wastewate...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 7: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and ii. Calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $33,760.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T7 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 15: i. A map showing the location of accumulated debris within the assigned wastewat...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 15: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and ii. Calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $19,041.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T15 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 16: i. A map showing the location of accumulated debris within the assigned wastewat...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 16: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and ii. Calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $22,107.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T16 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 24: i. A map showing the location of accumulated debris within the assigned wastewat...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 24: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and
ii. Its calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $21,041.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T24 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 25: i. A map showing the location of accumulated debris within the assigned wastewat...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 25: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and
ii. Its calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $55,147.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T25 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 28: i. A map showing the location of accumulated debris within the assigned wastewat...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 28: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and
ii. Its calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $24,857.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T28 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 36: i.A map showing the location of accumulated debris within the assigned wastewate...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 36: i.A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and
ii. Its calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $42,047.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T36 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 26: i.A map showing the location of accumulated debris within the assigned wastewate...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 26: i.A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and
ii. Its calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $56,301.00.
CO1: Revision in Scope of Work "
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the
Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T26 CO1 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 45: i. A map showing the location of accumulated debris within the assigned wastewat...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 45: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and
ii. Its calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $22,192.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T45 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 47: i. A map showing the location of accumulated debris within the assigned wastewat...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 47: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and
ii. Its calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $18,136.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the
Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T47 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 50: i. A map showing the location of accumulated debris within the assigned wastewat...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 50: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and
ii. Its calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $87,014.00.
CO1: Scope of Work Revision
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T50 CO1 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 57: i. A map showing the location of accumulated debris within the assigned wastewat...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 57: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and
ii. Its calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $36,902.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T57 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 58: i. A map showing the location of accumulated debris within the assigned wastewat...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 58: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and
ii. Its calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $36,437.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T58 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 60: i. A map showing the location of accumulated debris within the assigned wastewat...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 60: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and
ii. Its calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $68,937.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T60 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 63: i. A map showing the location of accumulated debris within the assigned wastewat...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 63: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and
ii. Its calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $21,521.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T63 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 64: i. A map showing the location of accumulated debris within the assigned wastewat...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 64: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and
ii. Its calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $13,704.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T64 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
For each task assignment issued, the Contractor will provide to the Department and the public utilit...
|
Cost Reimbursement
|
| Major Deliverable: For each task assignment issued, the Contractor will provide to the Department and the public utility: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and ii. Calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations
were achieved.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal. |
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: Attachment 3, pg 1 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 4: i. A map showing the location of accumulated debris within the assigned wastewate...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 4: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and ii. Calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $65,434.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T4 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 9: i. A map showing the location of accumulated debris within the assigned wastewate...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 9: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and ii. Calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $29,200.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T9 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 12: i. A map showing the location of accumulated debris within the assigned wastewat...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 12: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and ii. Calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $22,297.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by the Department’s Contract Manager, the Contractor may proceed with payment request submittal. |
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T12 |
| Deliverable Number: |
|
|
|
|
Hydrogeology assessment service
|
Task Assignment 11: i. A map showing the location of accumulated debris within the assigned wastewat...
|
Cost Reimbursement
|
| Major Deliverable: Task Assignment 11: i. A map showing the location of accumulated debris within the assigned wastewater tank(s), along with any supporting data (quantitative and/or visual) collected during the mapping process; and ii. Calculations of volume-proportioning amounts for the debris and the loss of capacity of the assigned tank(s) as a percentage, along with a sufficient explanation of how these calculations were achieved. Total cost not to exceed: $42,832.00.
|
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: The Department’s Contract Manager will review the documentation to verify that the deliverables are completed as described above. Upon review and written acceptance by then Department’s Contract Manager, the Contractor may proceed with payment request submittal.
|
| Financial Consequences: No payment will be made for deliverables deemed unsatisfactory by the Department. In addition, as a financial consequence the Department will reduce an invoice by 1% for each day that the Contractor fails to meet an agreed upon timeline, unless the timeline is extended in writing by the Department.
|
| Source Documentation Page Reference: T11 |
| Deliverable Number: |
|