Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
Engineering testing services
|
Collect necessary suspect ACM samples from various locations in Koger Hall. Services shall be in ac...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Collect necessary suspect ACM samples from various locations in Koger Hall. Services shall be in accordance with proposal dated 03/03/2015 for a total authorized amount of $600.00. Payment shall be made upon submittal of a detailed summary report of the findings, approved invoice and a copy of the activation. |
| Deliverable Price: $600.00 |
| Non Price Justification: |
| Performance Metrics: Contractual shall use the highest professional skills and best judgment to complete 100% of the services prescribed in the activation. |
| Financial Consequences: Payment shall not be made unless all services are provided. Failure to provide services may result in cancellation of the continuing contract. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Engineering testing services
|
Activation #8 - Total lump sum amount of $11,905.00 for testing of groundwater and preparation of Re...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Activation #8 - Total lump sum amount of $11,905.00 for testing of groundwater and preparation of Remedial Action System Status Report (RASS Report).
Task 1 - Field Services and laboratory for groundwater monitoring and testing. Lump sum amount of $7,518.00.
Task 2 - Semi-Annual Report preparation and submittal to FL DEP. Lump sum amount of $4,387.00. |
| Deliverable Price: $11,905.00 |
| Non Price Justification: |
| Performance Metrics: Contractor shall use the highest professional skills and best judgment to complete 100% of the services prescribed in the activation. |
| Financial Consequences: Payment shall not be made unless all services are provided. Failure to provide services may result in cancellation of the continuing contract. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Engineering testing services
|
Perform Active Groundwater Remediation Tasks in accordance with Contractor's proposal dated 10/15/20...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Perform Active Groundwater Remediation Tasks in accordance with Contractor's proposal dated 10/15/2015. Payment will be made upon completion of the remediation and Owner's receipt and approval of a detailed invoice as certified complete by the FSDB Project Manager. |
| Deliverable Price: $58,904.00 |
| Non Price Justification: |
| Performance Metrics: Implement a recommended strategy for active remediation of the CVOC groundwater plume, i.e. enhanced anaerobic bioremediation. The strategy includes the injection of dechlorinating bacteria in 8 intermediate and deep injection points for in situ bioremediation of the CVOCs. Contractor shall provide field/office services RAP Mod, remedial electron donor solution, and drilling subcontractor. |
| Financial Consequences: Failure to provide the contracted deliverable will result in non-payment of the contract, invoice or statement amount. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Engineering testing services
|
Task 1 Field Services and Laboratory Testing: Provide the Remedial Action System Status Report (RASS...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 1 Field Services and Laboratory Testing: Provide the Remedial Action System Status Report (RASS Report) for the Semi-Annual Ground Water Monitoring for CVOC concentrations, geochemical parameters, and underground injection control permit parameters and access the groundwater's continued suitability for reductive dechlorination. Dispose of three (3) 55 gallon drums of regulated IDW. |
| Deliverable Price: $8,663.75 |
| Non Price Justification: |
| Performance Metrics: Payment will be made for Task 1 upon completion of monitoring well sampling, receipt of laboratory analysis and Owner's receipt and approval of a detailed invoice as certified complete by the FSDB Project Manager. |
| Financial Consequences: Failure to provide the contracted deliverable will result in non-payment of the contract, invoice or statement amount. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Engineering testing services
|
Task 2 Semi-annual Report Preparation and Submittal to FDEP: Provide the Remedial Action System Stat...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Task 2 Semi-annual Report Preparation and Submittal to FDEP: Provide the Remedial Action System Status Report (RASS Report) for the Semi-Annual Ground Water Monitoring for CVOC concentrations, geochemical parameters, and underground injection control permit parameters and access the groundwater's continued suitability for reductive dechlorination. |
| Deliverable Price: $4,167.00 |
| Non Price Justification: |
| Performance Metrics: Payment will be made for Task 2 upon completion of monitoring well sampling, receipt of laboratory analysis and Owner's receipt and approval of a detailed invoice as certified complete by the FSDB Project Manager. |
| Financial Consequences: Failure to provide the contracted deliverable will result in non-payment of the contract, invoice or statement amount. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
ENVIRONMENTAL ENGINEERS
|
Contractor shall provide remedial action systems status report, year 5 semi-annual groundwater monit...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Contractor shall provide remedial action systems status report, year 5 semi-annual groundwater monitoring |
| Deliverable Price: $13,670.00 |
| Non Price Justification: |
| Performance Metrics: Contractor will provide the contracted deliverable for a fixed price lump sum payable upon successful completion of work and submittal of an approved invoice. |
| Financial Consequences: Failure to provide the contracted deliverable will result in non-payment of contract, invoice or statement amount. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
ENVIRONMENTAL ENGINEERS
|
Contractor will provide field and laboratory services per your proposal dated April 1, 2014. Prepare...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Contractor will provide field and laboratory services per your proposal dated April 1, 2014. Prepare the 5 year semi-annual FDEP report. |
| Deliverable Price: $12,819.00 |
| Non Price Justification: |
| Performance Metrics: Provide field and laboratory services to prepare the 5 year semi-annual FDEP report at a fixed price payable upon successful completion of work and submittal of an approved invoice. |
| Financial Consequences: Failure to provide the contracted deliverable will result in non-payment of contract, invoice or statement amount. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
ENGINEERING SERVICES
|
Activation #3. Contractor will prepare and submit a Non-Title V Source Air Permit Renewal Applicatio...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Activation #3. Contractor will prepare and submit a Non-Title V Source Air Permit Renewal Application for an Air Pollutant Emitting Facility. |
| Deliverable Price: $4,200.00 |
| Non Price Justification: |
| Performance Metrics: Prepare and submit the renewal application at a fixed price payable upon successful completion of work and submittal of an approved invoice. |
| Financial Consequences: Failure to provide the contracted deliverable will result in non-payment of contract, invoice or statement amount. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
ENGINEERING SERVICES
|
Contractor will collect air samples from Moore Hall and the President's Residence and provide a writ...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Contractor will collect air samples from Moore Hall and the President's Residence and provide a written summary report of the findings and provide a report to Dr. Chris Teaf for interpretation and recommendations. |
| Deliverable Price: $6,964.00 |
| Non Price Justification: |
| Performance Metrics: Collect the air samples and provide a written report to FSDB and Dr. Teaf at a fixed price payable upon receipt of the findings and submittal of an approved invoice. |
| Financial Consequences: Failure to provide the contracted deliverable will result in non-payment of contract, invoice or statement amount. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Engineering testing services
|
Activation 6: Task 2: Provide the Remedial Action System Status Report (RASS Report) for the Semi-An...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Activation 6: Task 2: Provide the Remedial Action System Status Report (RASS Report) for the Semi-Annual Ground Water Monitoring for CVOC concentrations, geochemical parameters, and underground injection control permit parameters and access the groundwater's continued suitability for reductive dechlorination. Task 2 - Semi-Annual Report preparation and FDEP approval will be $5307.00. |
| Deliverable Price: $5,307.00 |
| Non Price Justification: |
| Performance Metrics: Payment for Task 2 will be made upon submittal of a RASS Report to the FDEP and receipt of a detailed invoice certified complete by the FSDB Project Manager and FDEP's approval of the RASS report. |
| Financial Consequences: Failure to provide the contracted deliverable will result in non-payment of the contract, invoice or statement amount. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Engineering testing services
|
Activation 6: Task 1: Provide the Remedial Action System Status Report (RASS Report) for the Semi-An...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Activation 6: Task 1: Provide the Remedial Action System Status Report (RASS Report) for the Semi-Annual Ground Water Monitoring for CVOC concentrations, geochemical parameters, and underground injection control permit parameters and access the groundwater's continued suitability for reductive dechlorination. Dispose of two (2) 55 gallon drums of regulated IDW. Task 1 - Field Services and Laboratory services will be $6418.00. |
| Deliverable Price: $6,418.00 |
| Non Price Justification: |
| Performance Metrics: Payment will be made for Task 1 upon completion of monitoring well sampling, receipt of laboratory analysis and Owner's receipt and approval of a detailed invoice as certified complete by the FSDB Project Manager |
| Financial Consequences: Failure to provide the contracted deliverable will result in non-payment of the contract, invoice or statement amount. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Engineering testing services
|
Terracon will provide an AHERA-accredited asbestos building inspector to collect bulk samples of sus...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Terracon will provide an AHERA-accredited asbestos building inspector to collect bulk samples of suspect ACM and submit to an independent laboratory for asbestos analysis. Contractor will collect approximately 18 samples, and will provide a letter report summarizing the findings. |
| Deliverable Price: $775.00 |
| Non Price Justification: |
| Performance Metrics: Terracon will provide an AHERA-accredited asbestos building inspector to collect bulk samples of suspect ACM and submit to an independent laboratory for asbestos analysis. Contractor will collect approximately 18 samples, and will provide a letter report summarizing the findings. |
| Financial Consequences: Contractor will receive payment upon documented completion and acceptance of the deliverable by the contract manager. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|