More |
Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
Financial assistance
|
1 - The Grantee will, through own staff or through contracted services, design, and engineer plans f...
|
Cost Reimbursement
|
Major Deliverable: 1 - The Grantee will, through own staff or through contracted services, design, and engineer plans for renovations to the proposed NE 2nd Way (Tudeen) Boat Ramp and acquire all permits required for demolition, removal, and construction. |
Deliverable Price: $57,367.00 |
Non Price Justification: |
Performance Metrics: ? Complete all required environmental surveys.
? Submit draft plans to FWC’s grant manager for review and approval.
? Upon approval by FWC’s grant manager, prepare final plans.
? Prepare and submit applications to the Florida Department of Environmental Protection (FDEP), U.S. Army Corps of Engineers (USACE), Broward County and any other local or statewide agencies that require permits to be applied for.
? Provide copies of permits or other final action by permitting agencies to FWC’s grant manager.
|
Financial Consequences: A. Pursuant to 215.971(1)(c), Florida Statutes, the Commission will withhold payment of Program funds for failure to complete the Project as described herein within the timeframe allowed, or for failure to correct any Project deficiencies, as noted in the final Project inspection. Only those deliverables completed, or items purchased and received in accordance with the scope of work and within the agreement period of performance will be eligible for reimbursement. Failure of the Grantee to provide the deliverable shall be considered non-compliance with terms and payment will not be processed.
B. In addition to nonpayment for tasks which are not satisfactorily or timely completed, or for failure to correct any project deficiencies, as noted in the final project inspection, the Commission will impose a financial consequence of twenty-five percent (25%) of the total contract amount for failure to complete any tasks satisfactorily or timely, or for failure to correct any project deficiencies, as noted in the final project inspection. The final project inspection will be done by a Commission employee verifying that the project was completed according to the project scope of work.
C. Failure of Grantee to have all receipts and evidence of project performance reflecting costs were incurred within the period of performance may jeopardize payment of funds to the Grantee per the Agreement.
D. Following the end of the term of this Agreement, the Grantee shall repay any Program funds received for the Project for failure to maintain the Project site as a public boating access facility according to the terms and conditions herein for a period of twenty (20) years. This section shall survive any Agreement termination
|
Source Documentation Page Reference: |
Deliverable Number: |
|
|
|
Financial assistance
|
2- The Grantee will, through own staff or through contracted services, demolish and remove the exist...
|
Cost Reimbursement
|
Major Deliverable: 2- The Grantee will, through own staff or through contracted services, demolish and remove the existing structures. |
Deliverable Price: $12,320.00 |
Non Price Justification: |
Performance Metrics: ? Bid Solicitation and contractor selection.
? Contractor equipment Mobilization and Demobilization.
? Demolish and remove approximately 555 sq. ft. of existing concrete ramp, or other structures to allow for construction and installation of BIG funded structures.
|
Financial Consequences: A. Pursuant to 215.971(1)(c), Florida Statutes, the Commission will withhold payment of Program funds for failure to complete the Project as described herein within the timeframe allowed, or for failure to correct any Project deficiencies, as noted in the final Project inspection. Only those deliverables completed, or items purchased and received in accordance with the scope of work and within the agreement period of performance will be eligible for reimbursement. Failure of the Grantee to provide the deliverable shall be considered non-compliance with terms and payment will not be processed.
B. In addition to nonpayment for tasks which are not satisfactorily or timely completed, or for failure to correct any project deficiencies, as noted in the final project inspection, the Commission will impose a financial consequence of twenty-five percent (25%) of the total contract amount for failure to complete any tasks satisfactorily or timely, or for failure to correct any project deficiencies, as noted in the final project inspection. The final project inspection will be done by a Commission employee verifying that the project was completed according to the project scope of work.
C. Failure of Grantee to have all receipts and evidence of project performance reflecting costs were incurred within the period of performance may jeopardize payment of funds to the Grantee per the Agreement.
D. Following the end of the term of this Agreement, the Grantee shall repay any Program funds received for the Project for failure to maintain the Project site as a public boating access facility according to the terms and conditions herein for a period of twenty (20) years. This section shall survive any Agreement termination
|
Source Documentation Page Reference: |
Deliverable Number: |
|
|
|
Financial assistance
|
3 - The Grantee will, through own staff or through contracted services, construct and install a boat...
|
Cost Reimbursement
|
Major Deliverable: 3 - The Grantee will, through own staff or through contracted services, construct and install a boat ramp and dock at the NE 2nd Way, also known as Tudeen Boat Ramp. |
Deliverable Price: $98,287.00 |
Non Price Justification: |
Performance Metrics: ? Construct (4) 10’x15’reinforced concrete push slabs.
? Install 16 sq. yards of 6” concrete approach slab (3,000 PSI).
? Install 60 sq. yards of 18" thick Alabama Class II riprap over D-2 filter fabric.
? Install 240 sq. ft. (40' L x 6' W) wide wheelchair accessbile wood dock.
|
Financial Consequences: A. Pursuant to 215.971(1)(c), Florida Statutes, the Commission will withhold payment of Program funds for failure to complete the Project as described herein within the timeframe allowed, or for failure to correct any Project deficiencies, as noted in the final Project inspection. Only those deliverables completed, or items purchased and received in accordance with the scope of work and within the agreement period of performance will be eligible for reimbursement. Failure of the Grantee to provide the deliverable shall be considered non-compliance with terms and payment will not be processed.
B. In addition to nonpayment for tasks which are not satisfactorily or timely completed, or for failure to correct any project deficiencies, as noted in the final project inspection, the Commission will impose a financial consequence of twenty-five percent (25%) of the total contract amount for failure to complete any tasks satisfactorily or timely, or for failure to correct any project deficiencies, as noted in the final project inspection. The final project inspection will be done by a Commission employee verifying that the project was completed according to the project scope of work.
C. Failure of Grantee to have all receipts and evidence of project performance reflecting costs were incurred within the period of performance may jeopardize payment of funds to the Grantee per the Agreement.
D. Following the end of the term of this Agreement, the Grantee shall repay any Program funds received for the Project for failure to maintain the Project site as a public boating access facility according to the terms and conditions herein for a period of twenty (20) years. This section shall survive any Agreement termination.
|
Source Documentation Page Reference: |
Deliverable Number: |
|