Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
Architectural engineering
|
TA1 - Design and Permitting for the proposed Marine Mammal Pathology Lab at Eckerd College in accord...
|
Fixed Price - Lump Sum
|
| Major Deliverable: TA1 - Design and Permitting for the proposed Marine Mammal Pathology Lab at Eckerd College in accordance with the proposal dated April 1, 2022. |
| Deliverable Price: $431,833.00 |
| Non Price Justification: |
| Performance Metrics: Payment will be made upon receipt of relevant documents, including PDF and AutoCAD files. |
| Financial Consequences: $100 per day for late completion of task(s). |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Architectural engineering
|
TA1CO1 - Revise time for deliverables
|
Fixed Price - Lump Sum
|
| Major Deliverable: TA1CO1 - Revise time for deliverables |
| Deliverable Price: $0.00 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Payment will be made upon receipt of relevant documents, including PDF and AutoCAD files. |
| Financial Consequences: $100 per day for late completion of task(s). |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Architectural engineering
|
TA2 - Completion of final design and permitting for the Marine Mammal Pathology Lab in accordance wi...
|
Fixed Price - Lump Sum
|
| Major Deliverable: TA2 - Completion of final design and permitting for the Marine Mammal Pathology Lab in accordance with the HOK proposal
date December 28, 2023t |
| Deliverable Price: $78,422.00 |
| Non Price Justification: |
| Performance Metrics: If Contractor fails to produce each deliverable within the time frame specified in the TA or CO, the budget amount
allocated for that deliverable will be deducted from Contractor’s payment. The Commission shall apply any additional
financial consequences identified in the TA or CO. |
| Financial Consequences: Should the Contractor fail to complete the subtask(s) in the critical path for project success ( (subtask 4C), by the
Due Date noted above, FWC shall assess $60.00 for each calendar day thereafter until completion is achieved. . |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Architectural engineering
|
TA2CO1 - Add in Eckerd lift station monitoring (2) and surveys in order to be able to properly desig...
|
Fixed Price - Lump Sum
|
| Major Deliverable: TA2CO1 - Add in Eckerd lift station monitoring (2) and surveys in order to be able to properly design and permit the lift station for
the Path Lab. Due to this additional unforeseen work, the deliverable dates of the other deliverables also need to be
modified. Work to be completed in accordance with the proposal dated February 14, 2024 |
| Deliverable Price: $46,000.00 |
| Non Price Justification: |
| Performance Metrics: If Contractor fails to produce each deliverable within the time frame specified in the TA or CO, the budget amount
allocated for that deliverable will be deducted from Contractor’s payment. The Commission shall apply any additional
financial consequences identified in the TA or CO. |
| Financial Consequences: Should the Contractor fail to complete the subtask(s) in the critical path for project success ( (subtask 4C), by the
Due Date noted above, FWC shall assess $100.00 for each calendar day thereafter until completion is achieved. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Architectural engineering
|
TA3 - Provide survey for easements required by the City of St Petersburg in accordance with the prop...
|
Fixed Price - Lump Sum
|
| Major Deliverable: TA3 - Provide survey for easements required by the City of St Petersburg in accordance with the proposal dated August 1, 2024. |
| Deliverable Price: $3,700.00 |
| Non Price Justification: |
| Performance Metrics: If Contractor fails to produce each deliverable within the time frame specified in the TA or CO, the budget amount allocated for that deliverable will be deducted from Contractor’s payment. The Commission shall apply any additional financial consequences identified in the TA or CO. |
| Financial Consequences: Should the Contractor fail to complete the subtask(s) in the critical path for project success ( (subtask 4C), by the Due Date noted above, FWC shall assess $10.00 for each calendar day thereafter until completion is achieved. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Architectural engineering
|
Revise time for deliverables due to coordination issues with Eckerd to resolve zoning.
|
Fixed Price - Lump Sum
|
| Major Deliverable: Revise time for deliverables due to coordination issues with Eckerd to resolve zoning. |
| Deliverable Price: $0.00 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Payment will be made upon receipt of relevant documents, including PDF and AutoCAD files. |
| Financial Consequences: $100 per day for late completion of task(s). |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Architectural engineering
|
TA4-Completion of final design and permitting for the Marine Mammal Pathology Lab in accordance with...
|
Fixed Price - Lump Sum
|
| Major Deliverable: TA4-Completion of final design and permitting for the Marine Mammal Pathology Lab in accordance with the HOK proposal dated September 12, 2024 |
| Deliverable Price: $73,822.00 |
| Non Price Justification: |
| Performance Metrics: If Contractor fails to produce each deliverable within the time frame specified in the TA or CO, the budget amount allocated for that deliverable will be deducted from Contractor’s payment. The Commission shall apply any additional financial consequences identified in the TA or CO. |
| Financial Consequences: Should the Contractor fail to complete the subtask(s) in the critical path for project success ( (subtask 4C), by the Due Date noted above, FWC shall assess $60.00 for each calendar day thereafter until completion is achieved. . |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Architectural engineering
|
TA4CO1-Extend deliverable dates to account for permitting delays from the City of St Petersburg, add...
|
Fixed Price - Lump Sum
|
| Major Deliverable: TA4CO1-Extend deliverable dates to account for permitting delays from the City of St Petersburg, add in additional tree survey required late in the game from the City of St. Petersburg, and revise the scope to take the project through the RFI permitting process all in accordance with the scope date April 15, 2025 |
| Deliverable Price: $1,620.00 |
| Non Price Justification: |
| Performance Metrics: If Contractor fails to produce each deliverable within the time frame specified in the TA or CO, the budget amount allocated for that deliverable will be deducted from Contractor’s payment. The Commission shall apply any additional financial consequences identified in the TA or CO. |
| Financial Consequences: Should the Contractor fail to complete the subtask(s) in the critical path for project success ( (subtask 4C), by the Due Date noted above, FWC shall assess $60.00 for each calendar day thereafter until completion is achieved. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Architectural engineering
|
TA-5 Provision of bidding support for plan clarifications/RFI’s in accordance with the proposal date...
|
Fixed Price - Lump Sum
|
| Major Deliverable: TA-5 Provision of bidding support for plan clarifications/RFI’s in accordance with the proposal date 9/4/2025 |
| Deliverable Price: $8,640.00 |
| Non Price Justification: |
| Performance Metrics: If Contractor fails to produce each deliverable within the time frame specified in the TA or CO, the budget amount allocated for that deliverable will be deducted from Contractor’s payment. The Commission shall apply any additional financial consequences identified in the TA or CO. |
| Financial Consequences: Should the Contractor fail to complete the subtask(s) in the critical path for project success ((subtask 4C), by the Due Date noted above, FWC shall assess $10.00 for each calendar day thereafter until completion is achieved |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Architectural engineering
|
TA 6-Prepare a technical memorandum and submittal to address the City of St Petersburg request for a...
|
Fixed Price - Lump Sum
|
| Major Deliverable: TA 6-Prepare a technical memorandum and submittal to address the City of St Petersburg request for a wave run analysis in accordance with the proposal dated January 27,2026. |
| Deliverable Price: $22,900.00 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Should the Contractor fail to complete the subtask(s) in the critical path for project
success including delivering PDF's by due date a fee will be enforced. |
| Financial Consequences: FWC shall assess $25.00 for each calendar day after the subtask due date until completion is achieved. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Architectural engineering
|
TA7-Provision of an updated construction cost estimate based on the current market conditions for th...
|
Fixed Price - Lump Sum
|
| Major Deliverable: TA7-Provision of an updated construction cost estimate based on the current market conditions for the Marine Mammal Pathology Lab per their proposal dated October 5, 2026. |
| Deliverable Price: $13,500.00 |
| Non Price Justification: |
| Performance Metrics: Should the Contractor fail to complete the subtask(s) in the critical path for project
success including delivering PDF's by due date a fee will be enforced. |
| Financial Consequences: Should the Contractor fail to complete the subtask(s) in the critical path for project success (6B.3), by the Due Date noted above, FWC shall assess $10.00 for each calendar day thereafter until completion is achieved. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|