| More |
Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
Financial assistance
|
1 - The Recipient will, through own staff or through contracted services, design, and engineer plans...
|
Cost Reimbursement
|
| Major Deliverable: 1 - The Recipient will, through own staff or through contracted services, design, and engineer plans for renovations to the proposed Lofton Island Marina and acquire all permits required for construction. |
| Deliverable Price: $71,857.39 |
| Non Price Justification: |
| Performance Metrics: •The Recipient will complete all required environmental surveys;
•Create final plans to be approved by the BIGP grant manager of the proposed project including but not limited to:
? Site plans
? Technical specifications
? Finished construction drawings
? Surveys and reports;
•The Recipient will prepare and submit applications to the Florida Department of Environmental Protection (FDEP), U.S. Army Corps of Engineers (ACOE), and any other agencies that require permitting be applied for, and
•Upon receipt of approval or other notices by the permitting agencies, provide copies to the BIGP grant manager.
•BIGP Grant Manager will obtain regulatory agency compliance approvals of the permits and submit to US Fish and Wildlife Service (USFWS) for removal of the grant award special condition(s). The BIGP Grant Manager will notify the Recipient when USFWS has determined that in-water and ground-disturbing activity may begin.
|
| Financial Consequences: A.Pursuant to 215.971(1)(c), Florida Statutes, the Commission will withhold payment of Program funds for failure to complete the Project as described herein within the timeframe allowed, or for failure to correct any Project deficiencies, as noted in the final Project inspection. Only those deliverables completed, or items purchased and received in accordance with the scope of work and within the agreement period of performance will be eligible for reimbursement. Failure of the Grantee to provide the deliverable shall be considered non-compliance with terms and payment will not be processed.
B.In addition to nonpayment for deliverables which are not satisfactorily or timely completed, or for failure to correct any project deficiencies, as noted in the final project inspection, the Commission will impose a financial consequence of twenty-five percent (25%) of the total contract amount for failure to complete any deliverables satisfactorily or timely, or for failure to correct any project deficiencies, as noted in the final project inspection. The final project inspection will be done by a Commission employee verifying that the project was completed according to the project scope of work.
C.Failure of Grantee to have all receipts and evidence of project performance reflecting costs were incurred within the period of performance may jeopardize payment of funds to the Grantee per the Agreement.
D.Following the end of the term of this Agreement, the Grantee shall repay any Program funds received for the Project for failure to maintain the Project site as a public boating access facility according to the terms and conditions herein for a period of twenty (20) years. This section shall survive any Agreement termination.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Financial assistance
|
2 - The Recipient will use grant funds to procure and install two (2) ADA wheelchair accessible gang...
|
Cost Reimbursement
|
| Major Deliverable: 2 - The Recipient will use grant funds to procure and install two (2) ADA wheelchair accessible gangways for the South Dock. |
| Deliverable Price: $9,163.00 |
| Non Price Justification: |
| Performance Metrics: •Install two (2) approximately 5’ x 30’ aluminum ADA Wheelchair accessible gangways. |
| Financial Consequences: A.Pursuant to 215.971(1)(c), Florida Statutes, the Commission will withhold payment of Program funds for failure to complete the Project as described herein within the timeframe allowed, or for failure to correct any Project deficiencies, as noted in the final Project inspection. Only those deliverables completed, or items purchased and received in accordance with the scope of work and within the agreement period of performance will be eligible for reimbursement. Failure of the Grantee to provide the deliverable shall be considered non-compliance with terms and payment will not be processed.
B.In addition to nonpayment for deliverables which are not satisfactorily or timely completed, or for failure to correct any project deficiencies, as noted in the final project inspection, the Commission will impose a financial consequence of twenty-five percent (25%) of the total contract amount for failure to complete any deliverables satisfactorily or timely, or for failure to correct any project deficiencies, as noted in the final project inspection. The final project inspection will be done by a Commission employee verifying that the project was completed according to the project scope of work.
C.Failure of Grantee to have all receipts and evidence of project performance reflecting costs were incurred within the period of performance may jeopardize payment of funds to the Grantee per the Agreement.
D.Following the end of the term of this Agreement, the Grantee shall repay any Program funds received for the Project for failure to maintain the Project site as a public boating access facility according to the terms and conditions herein for a period of twenty (20) years. This section shall survive any Agreement termination.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Financial assistance
|
3 - The Recipient will use grant funds to construct seventy (74) dedicated transient vessel slips an...
|
Cost Reimbursement
|
| Major Deliverable: 3 - The Recipient will use grant funds to construct seventy (74) dedicated transient vessel slips and side tie dockage with utilities. |
| Deliverable Price: $1,017,371.12 |
| Non Price Justification: |
| Performance Metrics: •Construct two (2) docks – North and South – to accommodate a minimum of seventy (70) dedicated transient vessel slips with side-tie dockage and utilities. Square footage may vary slightly based upon final plans if minimum slips are completed.
•North Dock to include:
? 4,848 sq. ft. Fixed Wood Dock
? 36Fender/Mooring Pilings
? 568 linear ft. Outside Wave Break/Protection
•South Dock to include:
? 4,008 sq. ft. Fixed Wood Dock, ADA Wheelchair Accessible
? 5,408 sq. ft. Floating Dock
? 2 Gangways
? 30Mooring Pilings
? 560 linear ft. Outside Wave Break/Protection
•Install # utility pedestals to include water and electric service.
•Install Wireless internet (Wi-Fi) for transient boaters
|
| Financial Consequences: A. Pursuant to 215.971(1)(c), Florida Statutes, the Commission will withhold payment of Program funds for failure to complete the Project as described herein within the timeframe allowed, or for failure to correct any Project deficiencies, as noted in the final Project inspection. Only those tasks completed, or items purchased and received in accordance with the scope of work and within the agreement period of performance will be eligible for reimbursement. Failure of the Recipient to perform the tasks and provide the deliverable shall be considered non-compliant with terms and payment will not be processed.
B. In addition to nonpayment for tasks which are not satisfactorily or timely completed, or for failure to correct any project deficiencies, as noted in the final project inspection, the Commission will impose a financial consequence of twenty-five percent (25%) of the total contract amount for failure to complete any tasks satisfactorily or timely, or for failure to correct any project deficiencies, as noted in the final project inspection. The final project inspection will be done by a Commission employee verifying that the project was completed according to the project scope of work.
C. Failure of Recipient to have all receipts and evidence of project performance reflecting costs were incurred within the period of performance may jeopardize payment of funds to the Recipient per the Agreement.
D. Following the end of the term of this Agreement, the Recipient shall repay any Program funds received for the Project for failure to maintain the Project site as a public boating access facility according to the terms and conditions herein for a period of twenty (20) years. This section shall survive any Agreement termination.
|
| Source Documentation Page Reference: |