| More |
Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
Botanical science services
|
Contractor will perform research services based on issued Task Assignment(s) with scope of services ...
|
Cost Reimbursement
|
| Major Deliverable: Contractor will perform research services based on issued Task Assignment(s) with scope of services to achieve research project objectives outlined the proposal(s). |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: Contractor will perform research services based on issued Task Assignment(s) with scope of services to achieve research project objectives outlined the proposal(s). Contractor will submit a mid-term report detailing progress of project along with detailed research data. The contractor will submit a final report addressing each project objective along detailed research data and a final analysis of this data and/or materials |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR; Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task assignments for the project or program. Any and all equipment, products or materials necessary to perform this CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
22128-C23-01 - Quarterly Status Report
|
Cost Reimbursement
|
| Major Deliverable: 22128-C23-01 - Quarterly Status Report |
| Deliverable Price: $71,058.10 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 4/7/23. Status report should detail all progress
towards tasks as detailed in the SOW |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
C23-01 - Year 1 Report
|
Cost Reimbursement
|
| Major Deliverable: C23-01 - Year 1 Report |
| Deliverable Price: $44,059.00 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 6/16/23. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by
CONTRACTOR; Disallow all or part of the cost of the activity or action not in compliance; Request refund of
previously disbursed payments related to deficiency; Wholly or partly suspend or terminate this agreement;
Withhold future task assignments for the project or program. Any and all equipment, products, or materials
necessary to perform this CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
C23-01 (3) - Quarterly Status Report
|
Cost Reimbursement
|
| Major Deliverable: C23-01 (3) - Quarterly Status Report |
| Deliverable Price: $35,345.05 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 10/7/23. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
C23-01 (4) - Mid-year Report
|
Cost Reimbursement
|
| Major Deliverable: C23-01 (4) - Mid-year Report |
| Deliverable Price: $35,347.00 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 1/6/24. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
C23-01 (5) - Quarterly Status Report
|
Cost Reimbursement
|
| Major Deliverable: C23-01 (5) - Quarterly Status Report |
| Deliverable Price: $35,347.00 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 4/7/24. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
C23-01 (6) - Year 2 Report
|
Cost Reimbursement
|
| Major Deliverable: C23-01 (6) - Year 2 Report |
| Deliverable Price: $35,347.00 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 6/16/24. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
C23-01 (7) - Quarterly Status Report
|
Cost Reimbursement
|
| Major Deliverable: C23-01 (7) - Quarterly Status Report |
| Deliverable Price: $31,182.99 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 10/7/24. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
C23-01 (8) - Final Project Report
|
Cost Reimbursement
|
| Major Deliverable: C23-01 (8) - Final Project Report |
| Deliverable Price: $31,183.00 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 12/31/24. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
1 Quarterly Status Report
|
Cost Reimbursement
|
| Major Deliverable: 1 Quarterly Status Report |
| Deliverable Price: $20,359.83 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 4/7/23. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
2 - End of Fiscal Year Status Report
|
Cost Reimbursement
|
| Major Deliverable: 2 - End of Fiscal Year Status Report |
| Deliverable Price: $20,359.82 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 6/16/23. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: CONTRACTOR will provide a status report, due to Commission on 6/16/23. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
3 - Quarterly Status Report
|
Cost Reimbursement
|
| Major Deliverable: 3 - Quarterly Status Report |
| Deliverable Price: $55,864.00 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 10/7/23. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
4 - Mid-year Report
|
Cost Reimbursement
|
| Major Deliverable: 4 - Mid-year Report |
| Deliverable Price: $37,866.00 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 1/6/24. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
5 - Quarterly Status Report
|
Cost Reimbursement
|
| Major Deliverable: 5 - Quarterly Status Report |
| Deliverable Price: $37,866.00 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 4/7/24. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
6 - End of the Fiscal Year (2) Report
|
Cost Reimbursement
|
| Major Deliverable: 6 - End of the Fiscal Year (2) Report |
| Deliverable Price: $37,866.00 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 6/16/24. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
7 - Quarterly Status Report
|
Cost Reimbursement
|
| Major Deliverable: 7 - Quarterly Status Report |
| Deliverable Price: $27,337.00 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 10/7/24. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
8 - Mid-year Report
|
Cost Reimbursement
|
| Major Deliverable: 8 - Mid-year Report |
| Deliverable Price: $27,337.00 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 1/6/25. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
9 - Quarterly Status Report
|
Cost Reimbursement
|
| Major Deliverable: 9 - Quarterly Status Report |
| Deliverable Price: $27,337.00 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 4/7/25. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
10 - End of Project Final Report
|
Cost Reimbursement
|
| Major Deliverable: 10 - End of Project Final Report |
| Deliverable Price: $81,170,000.00 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 6/16/25. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
C25-01 (3) - Year 1, Quarter 3 Status Report
|
Cost Reimbursement
|
| Major Deliverable: C25-01 (3) - Year 1, Quarter 3 Status Report |
| Deliverable Price: $31,143.20 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 4/15/26. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
C25-01 (4) - Year 1, Quarter 4 Status Report
|
Cost Reimbursement
|
| Major Deliverable: C25-01 (4) - Year 1, Quarter 4 Status Report |
| Deliverable Price: $31,143.22 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 6/15/26. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
C25-01 (5) - Year 2, Quarter 1 Status Report
|
Cost Reimbursement
|
| Major Deliverable: C25-01 (5) - Year 2, Quarter 1 Status Report |
| Deliverable Price: $30,057.71 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 10/15/26. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
C25-01 (6) - Year 2, Quarter 2 Status Report
|
Cost Reimbursement
|
| Major Deliverable: C25-01 (6) - Year 2, Quarter 2 Status Report |
| Deliverable Price: $30,057.71 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 1/15/27. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
C25-01 (7) - Year 2, Quarter 3 Status Report
|
Cost Reimbursement
|
| Major Deliverable: C25-01 (7) - Year 2, Quarter 3 Status Report |
| Deliverable Price: $30,057.71 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 4/15/26. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Biological science services
|
C25-01 (8) - Year 2, Quarter 4 Status Report
|
Cost Reimbursement
|
| Major Deliverable: C25-01 (8) - Year 2, Quarter 4 Status Report |
| Deliverable Price: $30,057.71 |
| Non Price Justification: |
| Performance Metrics: CONTRACTOR will provide a status report, due to Commission on 6/15/26. Status report should detail all progress
towards tasks as detailed in the SOW. |
| Financial Consequences: The COMMISSION will temporarily withhold cash payments pending correction of a deficiency by CONTRACTOR;
Disallow all or part of the cost of the activity or action not in compliance; Request refund of previously disbursed
payments related to deficiency; Wholly or partly suspend or terminate this agreement; Withhold future task
assignments for the project or program. Any and all equipment, products, or materials necessary to perform this
CONTRACT shall be supplied by the CONTRACTOR, unless otherwise specified herein. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|