| More |
Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
Architectural engineering
|
Documentation of fullfillment of professional services for various projects as outlined in related T...
|
Fixed Price - Lump Sum
|
| Major Deliverable: Documentation of fullfillment of professional services for various projects as outlined in related Task Assignment |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: If Contractor fails to produce each deliverable within the time frame specified in the TA or CO, the budget amount allocated for that deliverable will be deducted from Contractor’s payment. The Commission shall apply any additional financial consequences identified in the TA or CO. |
| Financial Consequences: If Contractor fails to produce each deliverable within the time frame specified in the TA or CO, the budget amount allocated for that deliverable will be deducted from Contractor’s payment. The Commission shall apply any additional financial consequences identified in the TA or CO. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Architectural engineering
|
TA1 - Consultant will provide design and permitting services for the entrance to the Johnson Tract i...
|
Fixed Price - Lump Sum
|
| Major Deliverable: TA1 - Consultant will provide design and permitting services for the entrance to the Johnson Tract in the Florida Keys Wildlife
and Environmental Area per their proposal dated, 11/20/2023. |
| Deliverable Price: $33,725.00 |
| Non Price Justification: |
| Performance Metrics: If Contractor fails to produce each deliverable within the time frame specified in the TA or CO, the budget amount
allocated for that deliverable will be deducted from Contractor’s payment. The Commission shall apply any additional
financial consequences identified in the TA or CO. |
| Financial Consequences: 40.00 |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Architectural engineering
|
TA2-WEC will design and engineer the civil and structural components of the mobile office space inst...
|
Fixed Price - Lump Sum
|
| Major Deliverable: TA2-WEC will design and engineer the civil and structural components of the mobile office space installation. This is to include site placement, stormwater, parking, ADA access, restroom facility review and upgrades where necessary, including plumbing engineering, and accessibility as needed. Survey and Landscape Architecture will be subcontracted. Review of the trailer technical documentation, foundation design, as well as framing design for an accessible stair and ramp is inclusive. Bid assistance and response to RFI may be included as an Additional Service. CEI services such as submittal review, on-site inspections, and assistance with any close-out documentation are not included in this proposal dated March 14, 2025 but may be contracted under a separate scope and fee if desired. |
| Deliverable Price: $60,770.00 |
| Non Price Justification: |
| Performance Metrics: If Contractor fails to produce each deliverable within the time frame specified in the TA or CO, the budget amount allocated for that deliverable will be deducted from Contractor’s payment. The Commission shall apply any additional financial consequences identified in the TA or CO. |
| Financial Consequences: 60.00 |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Architectural engineering
|
TA2CO1 - Completion of the permitting for the construction of the building needs additional time due...
|
Fixed Price - Lump Sum
|
| Major Deliverable: TA2CO1 - Completion of the permitting for the construction of the building needs additional time due to the City of Naples timelines. Only the permitting and permit fee tasks remain to be completed. Work shall be done in accordance with the proposal date 9/2/2025. |
| Deliverable Price: $60,770.00 |
| Non Price Justification: |
| Performance Metrics: If Contractor fails to produce each deliverable within the time frame specified in the TA or CO, the budget amount allocated for that deliverable will be deducted from Contractor’s payment. The Commission shall apply any additional financial consequences identified in the TA or CO. |
| Financial Consequences: 60.00 |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Architectural engineering
|
TA4CO1 - Revised delivery dates to accommodate FWC project start timeline.
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA4CO1 - Revised delivery dates to accommodate FWC project start timeline. |
| Deliverable Price: $0.00 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Payments shall be made at the completion of Subtasks and receipt of deliverables. |
| Financial Consequences: Should the Contractor fail to complete the subtask(s) in the critical path for project success (5), by the Due Date noted above, FWC shall assess $10.00 for each calendar
day thereafter until completion is achieved. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Architectural engineering
|
TA4 - Unencumber - Closing TA due to expiration date has passed. Moving unfinished subtasks 6 and 7 ...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA4 - Unencumber - Closing TA due to expiration date has passed. Moving unfinished subtasks 6 and 7 to a new TA. |
| Deliverable Price: ($6,490.00) |
| Non Price Justification: |
| Performance Metrics: Payments shall be made at the completion of Subtasks and receipt of deliverables. |
| Financial Consequences: Should the Contractor fail to complete the subtask(s) in the critical path for project success (5), by the Due Date noted above, FWC shall assess $10.00 for each calendar
day thereafter until completion is achieved. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Architectural engineering
|
TA 3-Provide Monroe County permits, SFWMD exemption (or permits), and 100% plans per their proposal ...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA 3-Provide Monroe County permits, SFWMD exemption (or permits), and 100% plans per their proposal dated 12/2/2025. |
| Deliverable Price: $23,265.00 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Payments shall be made at the completion of Subtasks and receipt of deliverables. |
| Financial Consequences: $25 per calendar day after due date of subtask |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Architectural engineering
|
TA4-Provision of construction oversight, review of shop drawings, RFI responses and project close ou...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA4-Provision of construction oversight, review of shop drawings, RFI responses and project close out in accordance with the proposal dated March 13, 2026 |
| Deliverable Price: $13,024.00 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Payments shall be made at the completion of Subtasks and receipt of deliverables. |
| Financial Consequences: Should the Contractor fail to complete the subtask(s) in the critical path for project success (5), by the Due Date noted above, FWC shall assess $10.00 for each calendar
day thereafter until completion is achieved. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Architectural engineering
|
TA3CO1-Revise Tasks and Due Dates based on agency permit type determinations per the marked-up propo...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA3CO1-Revise Tasks and Due Dates based on agency permit type determinations per the marked-up proposal as agreed upon per email dated 6/18/2026. Removing subtasks that result in a decrease in funding. |
| Deliverable Price: ($8,145.00) |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Payments shall be made at the completion of Subtasks and receipt of deliverables. |
| Financial Consequences: $25 per calendar day after due date of subtask |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Architectural engineering
|
TA5 - WEC has designed and engineered the civil and structural components of the mobile office space...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA5 - WEC has designed and engineered the civil and structural components of the mobile office space installation, including site placement, stormwater, ADA access, and restroom facility review. The prior contract ended with the close of the fiscal period before all contracted tasks were completed. This is a continuation of services from TA 4 to complete project. |
| Deliverable Price: $6,490.00 |
| Non Price Justification: |
| Performance Metrics: Pay requests shall be submitted in accordance with these contract documents to the attention of the Owner designee. |
| Financial Consequences: Should the Contractor fail to complete the subtask(s) in the critical path for project success (5), by the Due Date noted above, FWC shall assess $10.00 for each calendar
day thereafter until completion is achieved. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|