Professional engineering services
|
N/A
|
No Cost
|
| Major Deliverable: N/A |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: N/A |
| Financial Consequences: N/A |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Engineering and Research and Technology Based Services
|
101 Topographic Survey
102 Civil Engineering Master Plan
201 Conceptual Schematic Design
FWRI Review...
|
Fixed Price - Lump Sum
|
| Major Deliverable: 101 Topographic Survey
102 Civil Engineering Master Plan
201 Conceptual Schematic Design
FWRI Review & Approval of Conceptual Schematic Design
301 50% Construction Documents w/ Opinion of Probable Construction Cost
FWRI Review & Approval of 50% CDs
401 90% Construction Documents w/ Opinion of Probable Construction Cost
FWRI Review & Approval of 90% CDs
501 100% Construction Documents w/ Opinion of Probable Construction Cost
502 FL Energy Code Calculations
FWRI Review & Approval of 100% CDs
803 Owner Directed Changes (redesign) |
| Deliverable Price: $209,559.30 |
| Non Price Justification: |
| Performance Metrics: Payments for the following stipulated sum portions of the Basic Services shall be made at the completion of each
phase of the work in proportion to services performed as follows:
Progress payments shall be based on actual work completed. Pay requests shall be submitted in accordance with
these contract documents to the attention of the Owner designee. Backup material in the form of schedule of values
or equivalent approved by the Owner, shall be attached to the pay requests. |
| Financial Consequences: Should the Contractor fail to complete the subtask(s) by the due date noted above, FWC shall assess $250 for each
business day thereafter until completion is achieved. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Engineering and Research and Technology Based Services
|
- Site visit (field survey) to document existing conditions.
- 50% Construction Documents (PDF) with...
|
Fixed Price - Lump Sum
|
| Major Deliverable: - Site visit (field survey) to document existing conditions.
- 50% Construction Documents (PDF) with opinion of probable construction cost.
- 100% Construction Documents (PDF & include CAD w/ final S&S submission) with opinion of probable construction cost.
- Structural Engineering allowance.
|
| Deliverable Price: $71,197.92 |
| Non Price Justification: |
| Performance Metrics: CONSTRUCTION DOCUMENTS
Site Visit = Concurrent with 50% CDs deliverable = Due 60 Days from Notification from Contract Manager to begin TA
50% Construction Documents w/ Opinion of Cost = TBD
FWRI Review of 50% CD’s = 50 Days from Notification from Contract Manager that LBR Construction funding has been secured
100% Construction Documents w/ Opinion of Cost = Concurrent with 100% CDs deliverable
Structural Engineering of rooftop equipment FWRI Review of 100% CD’s = TBD
|
| Financial Consequences: Should the Contractor fail to complete the subtask(s) by the due date noted above, FWC shall assess $250 for each business day thereafter until completion is achieved. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Engineering and Research and Technology Based Services
|
TA2-1. Bidding Services
a. Conduct virtual pre-bid conference and site walk-through via MS Teams.
i)...
|
Fixed Price - Lump Sum
|
| Major Deliverable: TA2-1. Bidding Services
a. Conduct virtual pre-bid conference and site walk-through via MS Teams.
i) This includes a meeting prior to site-walk through to discuss project overview and a followup
meeting immediately after to answer questions (if any).
b. Provide written responses to pre-bid requests for information (RFI).
c. Provide addendums to the drawings or specifications as required.
2. Construction Administration
a. Review of product data submittals and shop drawings.
b. Response to contractor’s request for information during construction phase.
c. Review and approval of Contractor pay applications.
d. Review of final TAB report(s).
e. Substantial completion inspection and generation of final punch-list.
i) Close-out of final punch-list items will be conducted by FWC.
DELIVERABLES:
- Bidding assistance
- Review of awarded contractor’s submittals and shop drawings
- Substantial Completion Inspection & Punch List |
| Deliverable Price: $7,117.44 |
| Non Price Justification: |
| Performance Metrics: - Bidding assistance
- Review of awarded contractor’s submittals and shop drawings
- Substantial Completion Inspection & Punch List |
| Financial Consequences: Should the Contractor fail to complete the subtask(s) by the due date noted above, FWC shall assess $250 for each
business day thereafter until completion is achieved. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Engineering and Research and Technology Based Services
|
TA3-101 Topographic Survey
102 Civil Engineering Master Plan
103 50% Construction Documents w/
Opini...
|
Fixed Price - Lump Sum
|
| Major Deliverable: TA3-101 Topographic Survey
102 Civil Engineering Master Plan
103 50% Construction Documents w/
Opinion of Probable Construction Cost
FWRI Review & Approval of 50% CDs
401 90% Construction Documents w/
Opinion of Probable Construction Cost
FWRI Review & Approval of 90% CDs
501 100% Construction Documents w/
Opinion of Probable Construction Cost
502 FL Energy Code Calculations
FWRI Review & Approval of 100% CDs |
| Deliverable Price: $231,273.18 |
| Non Price Justification: |
| Performance Metrics: Payments for the following stipulated sum portions of the Basic Services shall be made at the completion of each
phase of the work in proportion to services performed as follows:
Progress payments shall be based on actual work completed. Pay requests shall be submitted in accordance with
these contract documents to the attention of the Owner designee. Backup material in the form of schedule of values
or equivalent approved by the Owner, shall be attached to the pay requests. |
| Financial Consequences: Should the Contractor fail to complete the subtask(s) by the due date noted above, FWC shall assess $250 for each
business day thereafter until completion is achieved. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Engineering and Research and Technology Based Services
|
TA4-201 Field Survey N/A 7 days $ 5,000.00
401 50% Construction Documents PDF 30 days $32,479.00
501...
|
Fixed Price - Lump Sum
|
| Major Deliverable: TA4-201 Field Survey N/A 7 days $ 5,000.00
401 50% Construction Documents PDF 30 days $32,479.00
501 100% Construction Documents PDF (S&S) 21 days (before June 30th) $26,574.00 |
| Deliverable Price: $64,053.00 |
| Non Price Justification: |
| Performance Metrics: Payments for the following stipulated sum portions of the Basic Services shall be made at the completion of each phase of the work in proportion to services performed as follows:
Progress payments shall be based on actual work completed. Pay requests shall be submitted in accordance with these contract documents to the attention of the Owner designee. Backup material in the form of schedule of values or equivalent approved by the Owner, shall be attached to the pay requests. |
| Financial Consequences: Should the Contractor fail to complete the subtask(s) by the due date noted above, FWC shall assess $250 for each
business day thereafter until completion is achieved. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Engineering and Research and Technology Based Services
|
TA5-1. Boundary Survey & Legal Description of proposed FWC site 2. Geotechnical Survey & report of p...
|
Fixed Price - Lump Sum
|
| Major Deliverable: TA5-1. Boundary Survey & Legal Description of proposed FWC site 2. Geotechnical Survey & report of proposed FWC site. |
| Deliverable Price: $8,700.00 |
| Non Price Justification: |
| Performance Metrics: Payments for the following stipulated sum portions of the basic services shall be made at the completion of each phase of the work in proportion to services performed. The actual phase parameters will be determined by the Contract Manager.
Pay requests shall be submitted in accordance with these contract documents and to the attention of the Contract Manager. Backup material in the form of schedule of values or equivalent approved by the Contract Manager, shall be attached to the pay requests. |
| Financial Consequences: Should the Contractor fail to complete the subtask(s) by the due date noted above, FWC shall assess $250 for each
business day thereafter until completion is achieved. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Engineering and Research and Technology Based Services
|
TA6 - Bidding & Permit Assistance
- Review of awarded contractor’s submittals and shop drawings
- Su...
|
Fixed Price - Lump Sum
|
| Major Deliverable: TA6 - Bidding & Permit Assistance
- Review of awarded contractor’s submittals and shop drawings
- Substantial Completion Inspection & Punch List |
| Deliverable Price: $6,832.32 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Payments for the following stipulated sum portions of the basic services shall be made at the completion of each phase of the work in proportion to services performed. The actual phase parameters will be determined by the Contract Manager.
Pay requests shall be submitted in accordance with these contract documents and to the attention of the Contract Manager. Backup material in the form of schedule of values or equivalent approved by the Contract Manager, shall be attached to the pay requests. |
| Financial Consequences: Should the Contractor fail to complete the subtask(s) by the due date noted above, FWC shall assess $250 for each business day thereafter until completion is achieved. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|