Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
1
|
Commercial and office building construction services
|
1 - Base Bid: Remove and replace metal roofing system, lightning protections, gutters, downspouts, a...
|
Fixed Price - Lump Sum
|
| Major Deliverable: 1 - Base Bid: Remove and replace metal roofing system, lightning protections, gutters, downspouts, and provide continuous
gutter system and downspouts and manifold drainage pipe in accordance with plans and specifications. |
| Deliverable Price: $179,248.16 |
| Non Price Justification: |
| Performance Metrics: In accordance with the General Terms and Conditions, the number of days from Notice to Proceed with Construction to
Substantial Completion shall be sixty (60) calendar days and Final Completion shall be thirty (30) calendar days
thereafter. If alternate #1 is awarded, add thirty (30) calendar days to Substantial Completion. If Alt. #2 is awarded, add
10 additional days to substantial completion. |
| Financial Consequences: In accordance with the General Terms and Conditions, the Liquidated Damages amount for Substantial Completion
is $100 per calendar day. |
| Source Documentation Page Reference: |
| Deliverable Number: 1 |
|
|
|
2
|
Commercial and office building construction services
|
2 - Alternate No. 1: Remove and replace wood cedar columns in accordance with plans and specificatio...
|
Fixed Price - Lump Sum
|
| Major Deliverable: 2 - Alternate No. 1: Remove and replace wood cedar columns in accordance with plans and specifications. |
| Deliverable Price: $33,393.70 |
| Non Price Justification: |
| Performance Metrics: In accordance with the General Terms and Conditions, the number of days from Notice to Proceed with Construction
to Substantial Completion shall be sixty (60) calendar days and Final Completion shall be thirty (30) calendar days
thereafter. If alternate #1 is awarded, add thirty (30) calendar days to Substantial Completion. If Alt. #2 is awarded,
add 10 additional days to substantial completion. |
| Financial Consequences: In accordance with the General Terms and Conditions, the Liquidated Damages amount for Substantial
Completion is $100 per calendar day. |
| Source Documentation Page Reference: |
| Deliverable Number: 2 |
|
|
|
3
|
Commercial and office building construction services
|
3 - Alternate No. 2: Remove and replace metal roof at shop building in accordance with the plans and...
|
Fixed Price - Lump Sum
|
| Major Deliverable: 3 - Alternate No. 2: Remove and replace metal roof at shop building in accordance with the plans and specifications. |
| Deliverable Price: $36,775.00 |
| Non Price Justification: |
| Performance Metrics: In accordance with the General Terms and Conditions, the number of days from Notice to Proceed with Construction
to Substantial Completion shall be sixty (60) calendar days and Final Completion shall be thirty (30) calendar days
thereafter. If alternate #1 is awarded, add thirty (30) calendar days to Substantial Completion. If Alt. #2 is awarded,
add 10 additional days to substantial completion. |
| Financial Consequences: In accordance with the General Terms and Conditions, the Liquidated Damages amount for Substantial
Completion is $100 per calendar day. |
| Source Documentation Page Reference: |
| Deliverable Number: 3 |
|
|
|
4
|
Commercial and office building construction services
|
4 - Alternate No. 3: 12 pieces of fascia Total
|
Fixed Price - Lump Sum
|
| Major Deliverable: 4 - Alternate No. 3: 12 pieces of fascia Total |
| Deliverable Price: $156.00 |
| Non Price Justification: |
| Performance Metrics: In accordance with the General Terms and Conditions, the number of days from Notice to Proceed with Construction
to Substantial Completion shall be sixty (60) calendar days and Final Completion shall be thirty (30) calendar days
thereafter. If alternate #1 is awarded, add thirty (30) calendar days to Substantial Completion. If Alt. #2 is awarded,
add 10 additional days to substantial completion. |
| Financial Consequences: In accordance with the General Terms and Conditions, the Liquidated Damages amount for Substantial
Completion is $100 per calendar day. |
| Source Documentation Page Reference: |
| Deliverable Number: 4 |
|
|
|
5
|
Commercial and office building construction services
|
5 - Alternate No. 4: 4X8 Sheathing plywood
|
Fixed Price - Lump Sum
|
| Major Deliverable: 5 - Alternate No. 4: 4X8 Sheathing plywood |
| Deliverable Price: $110.00 |
| Non Price Justification: |
| Performance Metrics: In accordance with the General Terms and Conditions, the number of days from Notice to Proceed with Construction
to Substantial Completion shall be sixty (60) calendar days and Final Completion shall be thirty (30) calendar days
thereafter. If alternate #1 is awarded, add thirty (30) calendar days to Substantial Completion. If Alt. #2 is awarded,
add 10 additional days to substantial completion. |
| Financial Consequences: In accordance with the General Terms and Conditions, the Liquidated Damages amount for Substantial
Completion is $100 per calendar day. |
| Source Documentation Page Reference: |