Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
Professional engineering services
|
Documentation of fulfillment of professional services for various projects as outlined in related Ta...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Documentation of fulfillment of professional services for various projects as outlined in related Task Assignment. |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: If Contractor fails to produce each deliverable within the time frame specified in the TA or CO, the budget amount allocated for that deliverable will be deducted from Contractor’s payment. The Commission shall apply any additional financial consequences identified in the TA or CO. |
| Financial Consequences: If Contractor fails to produce each deliverable within the time frame specified in the TA or CO, the budget amount allocated for that deliverable will be deducted from Contractor’s payment. The Commission shall apply any additional financial consequences identified in the TA or CO. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
TA1-JMT will provide comprehensive permitting, pre-construction coordination, construction engineeri...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA1-JMT will provide comprehensive permitting, pre-construction coordination, construction engineering and inspection, and project closeout services for the project including agency coordination to secure required Clean Water Act authorizations, plan updates and permit preparation, contractor coordination and submittal review, construction oversight and environmental compliance monitoring, progress documentation and limited survey verification, and final inspections and record transfer to support regulatory compliance and successful project completion, per their proposal dated 02/09/2026. |
| Deliverable Price: $166,275.07 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Should the Contractor fail to complete the subtask(s) in the critical path for project success (1C, 2a-12, 2c-1), by the Due Date noted above. |
| Financial Consequences: FWC shall assess $150 for each calendar day after the due date noted above until completion is achieved. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
TA2-JMT will expand on the services completed under contract 19161 Task Assignment (TA) 6, and devel...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA2-JMT will expand on the services completed under contract 19161 Task Assignment (TA) 6, and develop a habitat and shoreline restoration solution for the south shore
of Escribano Point Wildlife Management Area, per their proposal dated 04/14/2026. |
| Deliverable Price: $270,761.07 |
| Non Price Justification: |
| Performance Metrics: Should the Contractor fail to complete the subtask(s) in the critical path for project success (8.1 and 8.5a), by the Due Date noted above. |
| Financial Consequences: FWC shall assess $150 for each calendar day after the due date noted above until completion is achieved. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
TA3-Consultant will expand on the services completed under contract 19161 Task Assignment (TA) 4 to ...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA3-Consultant will expand on the services completed under contract 19161 Task Assignment (TA) 4 to help FWC secure the FDEP permit for the Oyster Shell Rakes Enhancement Project at Gomez Key, per their proposal dated 05/15/2026. |
| Deliverable Price: $42,566.78 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Should the Contractor fail to complete the subtask(s) in the critical path for project success (9), by the Due Date noted above. |
| Financial Consequences: FWC shall assess $40 for each calendar day after the due date noted above until completion is achieved.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
TA1CO1-Changes to deliverable dates due to delays in the execution of the construction contract, whi...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA1CO1-Changes to deliverable dates due to delays in the execution of the construction contract, which held back the start of construction and JMT’s services, per the consultant’s proposal dated 5/21/2026. |
| Deliverable Price: $0.00 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Should the Contractor fail to complete the subtask(s) in the critical path for project success (1C, 2a-12, 2c-1), by the Due Date noted above. |
| Financial Consequences: FWC shall assess $150 for each calendar day after the due date noted above until completion is achieved.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
TA 2 CO1-JMT proposed schedule modifications in subtasks that dealt with cost and the schedule of de...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA 2 CO1-JMT proposed schedule modifications in subtasks that dealt with cost and the schedule of deliverables to meet the end of the fiscal year parameters, per their proposal dated 05/19/2026. Deleted a subtask and broke another subtask in 2 and are only able to complete the first part, therefore that amount is reduced. |
| Deliverable Price: ($13,855.06) |
| Non Price Justification: |
| Performance Metrics: Should the Contractor fail to complete the subtask(s) in the critical path for project success (8.1 and 8.5a), by the Due Date noted above. |
| Financial Consequences: FWC shall assess $150 for each calendar day after the due date noted above until completion is achieved.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
TA4-JMT will provide construction site visits, coordination meetings and project closeout services f...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA4-JMT will provide construction site visits, coordination meetings and project closeout services for the project per their proposal dated 08/20/2026. |
| Deliverable Price: $26,867.95 |
| Non Price Justification: Rate Agreement |
| Performance Metrics: Should the Contractor fail to complete the subtask(s) in the critical path for project success (3), by the Due Date noted above. |
| Financial Consequences: Should the Contractor fail to complete the subtask(s) in the critical path for project success (3), by the Due Date noted above |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
TA1-The subtasks to be unencumbered depended on the construction of the project being completed in t...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA1-The subtasks to be unencumbered depended on the construction of the project being completed in time. The construction contract is being managed by the Florida Fish & Wildlife Foundation of Florida and is running several weeks late. Therefore, the consultant could not perform the services before the end date of the Task Assignment. |
| Deliverable Price: ($17,078.65) |
| Non Price Justification: |
| Performance Metrics: Should the Contractor fail to complete the subtask(s) in the critical path for project success (1C, 2a-12, 2c-1), by the Due Date noted above. |
| Financial Consequences: FWC shall assess $150 for each calendar day after the due date noted above until completion is achieved.
|
| Source Documentation Page Reference: |
| Deliverable Number: |
|