Deliverable Number
|
Commodity/Service Type
|
Major Deliverable
|
Method of Payment
|
|
|
|
Professional engineering services
|
Documentation of fulfillment of professional services for various projects as outlined in related Ta...
|
Fixed Fee / Unit Rate
|
| Major Deliverable: Documentation of fulfillment of professional services for various projects as outlined in related Task Assignment. |
| Deliverable Price: $0.00 |
| Non Price Justification: Price cannot be determined until the work has been completed |
| Performance Metrics: If Contractor fails to produce each deliverable within the time frame specified in the TA or CO, the budget amount allocated for that deliverable will be deducted from Contractor’s payment. The Commission shall apply any additional financial consequences identified in the TA or CO. |
| Financial Consequences: If Contractor fails to produce each deliverable within the time frame specified in the TA or CO, the budget amount allocated for that deliverable will be deducted from Contractor’s payment. The Commission shall apply any additional financial consequences identified in the TA or CO. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
TA1-Preliminary services to provide an Engineer Opinion of Probable Cost (EOPC) per their proposal d...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA1-Preliminary services to provide an Engineer Opinion of Probable Cost (EOPC) per their proposal dated 04/28/2026. |
| Deliverable Price: $44,799.40 |
| Non Price Justification: |
| Performance Metrics: Should the Contractor fail to complete the subtask(s) in the critical path for project success (2), by the Due Date noted above, a fee shall be assessed. |
| Financial Consequences: FWC shall assess $40 for each calendar day thereafter until completion is achieved. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
TA2-Permitting and design for Location 1 Culvert Crossing at Dinner Island Caracara Unit per their p...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA2-Permitting and design for Location 1 Culvert Crossing at Dinner Island Caracara Unit per their proposal dated 09/09/2026. |
| Deliverable Price: $118,280.00 |
| Non Price Justification: |
| Performance Metrics: Progress payments shall be based on actual work completed. They may be submitted monthly or on an alternate schedule per the Consultant’s billing processes. In any case, invoices for all completed work shall be submitted within 14 calendar days of the end date of the TA. Pay requests shall be submitted in accordance with these contract documents to the attention of the Owner designee. Backup material in the form of a schedule of values or equivalent approved by the Owner, shall be attached to the pay request. |
| Financial Consequences: Should the Contractor fail to complete the subtask(s) in the critical path for project success (1.5A, 1.7A, 1.8A & 1.9A, 1.10A & 1.11A), by the Due Date noted above, FWC
shall assess $100 for each calendar day thereafter until completion is achieved. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|
|
|
|
Professional engineering services
|
TA3-Permitting and design for Locations 2-8 Culvert Crossings at Dinner Island Caracara Unit per the...
|
Cost Reimbursement Plus Fixed Fee(s), including Fixed Price Components
|
| Major Deliverable: TA3-Permitting and design for Locations 2-8 Culvert Crossings at Dinner Island Caracara Unit per their proposal dated 09/09/2026. |
| Deliverable Price: $85,005.50 |
| Non Price Justification: |
| Performance Metrics: Progress payments shall be based on actual work completed. They may be submitted monthly or on an alternate schedule per the Consultant’s billing processes. In any case, invoices for all completed work shall be submitted within 14 calendar days of the end date of the TA. Pay requests shall be submitted in accordance with these contract documents to the attention of the Owner designee. Backup material in the form of a schedule of values or equivalent approved by the Owner, shall be attached to the pay request. |
| Financial Consequences: Should the Contractor fail to complete the subtask(s) in the critical path for project success (1.5A, 1.7A, 1.8A & 1.9A, 1.10A & 1.11A), by the Due Date noted above, FWC
shall assess $100 for each calendar day thereafter until completion is achieved. |
| Source Documentation Page Reference: |
| Deliverable Number: |
|