| More |
LINE ITEM NUMBER
|
COMMODITY TYPE
|
STATE TERM CONTRACT ID
|
AGENCY SOLICITATION NUMBER
|
Quantity |
Unit Price |
Total Unit Price |
|
|
1
|
Stone or tile flooring
|
|
|
6276.1200
|
$1.0000
|
$6,276.12
|
| Line 1 is for (50%) advanced pay (required by vendor). ------------------------- Park Manager House BL045032 At Koreshan State Park. Quote number: 202445 & Change order Quote #202452 ... |
| Line Item Description: Line 1 is for (50%) advanced pay (required by vendor). ------------------------- Park Manager House BL045032 At Koreshan State Park. Quote number: 202445 & Change order Quote #202452 ----------- Quote number: 202445 ------------ Total amount of Job = $7,307.00 PAYMENTS: 50% DEPOSIT = $3653.50 50% UPON COMPLETION = $3,653.50 -Remove carpet, padding, and tackstrip and dispose. dispose of in supplied dumpster @ $450.00 -Supply and install tile, ($5 per sf budget), over properly prepared floor, thin set method using specified thin set mortar and grout. @ $5,850.00 -Supply and install lippage clips for large format tile. @ $562.50 -Mapei Keraflex SG, Standard, Extra Smooth, Large-and-Heavy-Tile Mortar with Polymer 50Lb bag @ $409.50 -IMapei Ultrcolor Plus grout. Meets ansi 118.7 25lb bag @ $35.00 Total Cost = $7,307.00 ----------- Change Order Quote number: 202452 ------------ Total amount of Job = $5,245.25 PAYMENTS: 50% DEPOSIT = $2,622.62 50% UPON COMPLETION = $,2622.63 -Remove VCT tile, tooling included @ $1,026.00 -Mechanically grind floor to remove glue, and take down lippage at cold joint. @ $550.00 -Supply and install uncoupling membrane over floor to bridge cold joint @ $3,480.00 -Mapei Keraflex SG, Standard, Extra Smooth, Large-and-Heavy-Tile Mortar with Polymer 50Lb bag to install membrane @ $159.25 Total Cost = $5,245.25 The above work will be performed with the materials and specifications submitted for above work and completed in a substantial workmanlike manner. Contractor is responsible for all supervision, labor, permits, materials, equipment, and supplies, and cleanup required to complete this job. Should additional work be required that is not included in the Scope of Work for this project, Contractor will discuss with the Park Manager (or delegate) and provide a quote. Once the additional work is identified and agreed upon by both parties, the contract manager will submi |
| Method of Procurement: Informally quoted purchase not exceeding Category Two [Rule 60A-1.002(3), F.A.C. & s. 287.017(2)] |
Line Split Details:
| Split Accounting Line Number: 1 |
| FLAIR Contract ID: |
| Org. Code and Description: 37504000045 - |
| Object Code and Description: 243018 - |
| Account Code: 37-20-2-423001-37500300-00-100718-00 |
| Split Amount: $6,276.12 |
|
|
|
2
|
Stone or tile flooring
|
|
|
6276.1300
|
$1.0000
|
$6,276.13
|
| Line 2 is Balance upon Completion (50%) - $6276.12 Park Manager House BL045032 At Koreshan State Park. Quote number: 202445 Total amount of Job = $7,307.00 PAYMENTS: 50% DEPOSIT = $3653.50 ... |
| Line Item Description: Line 2 is Balance upon Completion (50%) - $6276.12 Park Manager House BL045032 At Koreshan State Park. Quote number: 202445 Total amount of Job = $7,307.00 PAYMENTS: 50% DEPOSIT = $3653.50 50% UPON COMPLETION = $3,653.50 Remove carpet, padding, and tackstrip and dispose. dispose of in supplied dumpster @ $450.00 Supply and install tile, ($5 per sf budget), over properly prepared floor, thin set method using specified thin set mortar and grout. @ $5,850.00 Supply and install lippage clips for large format tile. @ $562.50 Mapei Keraflex SG, Standard, Extra Smooth, Large-and-Heavy-Tile Mortar with Polymer 50Lb bag @ $409.50 IMapei Ultrcolor Plus grout. Meets ansi 118.7 25lb bag @ $35.00 Park Manager House BL045032 At Koreshan State Park. Quote number: 202445 & Change order Quote #202452 ----------- Quote number: 202445 ------------ Total amount of Job = $7,307.00 PAYMENTS: 50% DEPOSIT = $3653.50 50% UPON COMPLETION = $3,653.50 -Remove carpet, padding, and tackstrip and dispose. dispose of in supplied dumpster @ $450.00 -Supply and install tile, ($5 per sf budget), over properly prepared floor, thin set method using specified thin set mortar and grout. @ $5,850.00 -Supply and install lippage clips for large format tile. @ $562.50 -Mapei Keraflex SG, Standard, Extra Smooth, Large-and-Heavy-Tile Mortar with Polymer 50Lb bag @ $409.50 -IMapei Ultrcolor Plus grout. Meets ansi 118.7 25lb bag @ $35.00 Total Cost = $7,307.00 ----------- Change Order Quote number: 202452 ------------ Total amount of Job = $5,245.25 PAYMENTS: 50% DEPOSIT = $2,622.62 50% UPON COMPLETION = $,2622.63 -Remove VCT tile, tooling included @ $1,026.00 -Mechanically grind floor to remove glue, and take down lippage at cold joint. @ $550.00 -Supply and install uncoupling membrane over floor to bridge cold joint @ $3,480.00 -Mapei Keraflex SG, Standard, Extra Smooth, Large-and-Heavy-Tile Mortar with Polymer |
| Method of Procurement: Informally quoted purchase not exceeding Category Two [Rule 60A-1.002(3), F.A.C. & s. 287.017(2)] |
Line Split Details:
| Split Accounting Line Number: 1 |
| FLAIR Contract ID: |
| Org. Code and Description: 37504000045 - |
| Object Code and Description: 243018 - |
| Account Code: 37-20-2-423001-37500300-00-100718-00 |
| Split Amount: $6,276.13 |
|